← Back

C-number: C-44-17-024-M

C-number: C-44-17-024-M-00
Item: #6
Revision: 00
Item Text
6. ZANJERO TRAILS (WINDROSE) - PHASE 1 THIRD PARTY TRUST ASSURANCE AGREEMENT Approve a Resolution authorizing execution of the Zanjero Trails (Windrose) Phase 1 Third Party Trust Assurance Agreement (the “Assurance Agreement”) among First American Title Insurance Company (Trustee), Maricopa County Municipal Water Conservation District (Beneficiary) and Maricopa County. This Assurance Agreement encompasses approximately 300 acres and would supplement the phased construction of the first phase of the Zanjero Trails Development Master Plan for Development Parcels 35B, 37, 40 and 43 related to off-site subdivision improvements. Phase 1 is bounded by Perryville Rd. to the east, Camelback Rd. to the south, Beardsley Canal along the west and Bethany Home Rd. alignment to the north. This Assurance Agreement must be authorized by Resolution of the Board of Supervisors prior to approval of the Infrastructure Plat associated with the DMP. This agreement is to be recorded as required pursuant to A.R.S. §11-1101. (Supervisor District 4) (C-44-17-024-M-00)

C-number: C-44-17-024-M-01
Item: #43
Revision: 01
Vote — approved
Steve Gallardo abstain
Bill Gates abstain
Clint Hickman abstain
Gallardo Procurement Services yes
and Clint Hickman yes
Denny Barney abstain
Steve Chucri yes
43.AMENDMENT TO PHASE 1 THIRD PARTY TRUST ASSURANCE AGREEMENT FOR ZANJERO TRAILS (WINDROSE)Approve an Amendment to the executed Zanjero Trails (Windrose) Phase 1 Third Party Trust Assurance Agreement (the “Assurance Agreement”) among First American Title Insurance Company (Trustee), Maricopa County Municipal Water Conservation District (Beneficiary) and Maricopa County originally approved by the Board of Supervisors on September 7, 2016. This one-page Amendment is to approve a revised “Exhibit B
Item Text
43. AMENDMENT TO PHASE 1 THIRD PARTY TRUST ASSURANCE AGREEMENT FOR ZANJERO TRAILS (WINDROSE) Approve an Amendment to the executed Zanjero Trails (Windrose) Phase 1 Third Party Trust Assurance Agreement (the “Assurance Agreement”) among First American Title Insurance Company (Trustee), Maricopa County Municipal Water Conservation District (Beneficiary) and Maricopa County originally approved by the Board of Supervisors on September 7, 2016. This one-page Amendment is to approve a revised “Exhibit B” dated January 26, 2017. There are no other changes to the document. This Assurance Agreement encompasses approximately 300 acres and supplements the phased construction of the first phase of the Zanjero Trails Development Master Plan for Development Parcels 35B, 37, 40 and 43 related to off-site subdivision improvements. Phase 1 is bounded by Perryville Rd. to the east, Camelback Rd. to the south, Beardsley Canal along the west and Bethany Home Rd. alignment to the north. This Amendment must be authorized by the Board of Supervisors. This Amendment to the Assurance Agreement is to be re-recorded as required pursuant to A.R.S. §11-1101. (Supervisor District 4) (C-44-17-024-M-01)
Attachments (1)

2 item(s) sharing C-number base C-44-17-024-M