95. CHANGE ORDER TO CONTRACT WITH PARSONS TRANSPORTATION GROUP, INC. Approve Change Order No. 4 with Parsons Transportation Group, Inc. in the amount of $995,704.73 for a total contract amount of $3,575,633.27. MCDOT has requested a higher level of detail which is more a preliminary design for the Gilbert Road Bridge Project. This Change Order No. 4 authorizes contract modifications to the original Scope of Work to perform additional Environmental Assessments (EA), Geotechnical Investigations and 40% Engineering Plans Detail. Approval of this change order establishes a new contract amount of $3,575,633.27 and a new completion date of March 31, 2010. Contract Awarded on November 15, 2006 under C64071045 for the sum of $2,526,102.30 for project Dobson Road Bridge at Salt River, Design Concept Report, Job No. TT199. Supervisory District No. 2 (C-64-07-104-5-02)