← Back

C-number: C-64-18-076-5

C-number: C-64-18-076-5-00
Item: #75
Revision: 00
Vote — approved
Steve Gallardo abstain
Bill Gates abstain
Clint Hickman abstain
Gallardo School Superintendent yes
and Clint Hickman yes
Denny Barney abstain
Steve Chucri yes
75.BID AND AWARD FOR PAVEMENT REHABILITATION PROJECT: SUN VALLEY PARKWAY, I-10 TO TARTESSOApprove the solicitation of bids for the Maricopa County Department of Transportation's Pavement Rehabilitation Project. Award the contract to the lowest responsive responsible bidder, provided that the lowest responsive responsible bidder does not exceed the Engineer’s estimate by more than ten percent. Funds will be budgeted through the Transportation Department (D640) Transportation Capital Projects fund
Item Text
75. BID AND AWARD FOR PAVEMENT REHABILITATION PROJECT: SUN VALLEY PARKWAY, I-10 TO TARTESSO Approve the solicitation of bids for the Maricopa County Department of Transportation's Pavement Rehabilitation Project. Award the contract to the lowest responsive responsible bidder, provided that the lowest responsive responsible bidder does not exceed the Engineer’s estimate by more than ten percent. Funds will be budgeted through the Transportation Department (D640) Transportation Capital Projects fund (234) System Preservation and Reconstruction (SPAR) Project, Sub-Project TT0593. The project's road list is attached to this Agenda Item Summary. Supervisory District No. 4 (C-64-18-076-5-00)
Attachments (2)

1 item(s) sharing C-number base C-64-18-076-5