← Back

C-number: C-64-23-236-X

C-number: C-64-23-236-X-00
Item: #77
Revision: 00
Vote — approved
Clint Hickman yes
Jack Sellers yes
Thomas Galvin yes
Bill Gates yes
Steve Gallardo yes
Ayes: Clint Hickman, Jack Sellers, Thomas Galvin, Bill Gates, Steve Gallardo
Item Text
77. CHANGE ORDER WITH CACTUS ASPHALT Approve Construction Services Contract No. 2022-024, with Cactus Asphalt, A Division of Cactus Transport, Inc., Change Order No. 06 in the amount of $940,951.51 for inefficiencies the Contractor encountered during the construction of the project that was not within their control. Supervisory District No. 1 (C-64-23-236-X-00)

1 item(s) sharing C-number base C-64-23-236-X