← Back

C-number: C-64-24-235-X

C-number: C-64-24-235-X-00
Item: #71
Revision: 00
Vote — approved
Jack Sellers yes
Thomas Galvin yes
Bill Gates yes
Clint Hickman yes
Steve Gallardo yes
Ayes: Jack Sellers, Thomas Galvin, Bill Gates, Clint Hickman, Steve Gallardo
Item Text
71. CHANGE ORDER WITH TY LIN INTERNATIONAL FOR FINAL DESIGN ON NORTHERN PARKWAY: 99TH AVENUE TO 87TH AVENUE Request approval of Change Order No. 5 for Contract No. 2021-016 with TY Lin, Intl. for a sum not-to-exceed one million, eighteen thousand, five hundred seventy dollars ($1,018,570). The contract completion date will be extended to June 30, 2028 to encompass the anticipated post-design services schedule. Supervisory District No. 4 (C-64-24-235-X-00)
Attachments (1)

C-number: C-64-24-235-X-01
Item: #58
Revision: 01
Vote — approved
Thomas Galvin yes
Kate Brophy McGee yes
Mark Stewart yes
Debbie Lesko yes
Steve Gallardo yes
Ayes: Thomas Galvin, Kate Brophy McGee, Mark Stewart, Debbie Lesko, Steve Gallardo
Item Text
58. CHANGE ORDER WITH TY LIN INTERNATIONAL FOR ADDITIONAL DESIGN SERVICES ON NORTHERN PARKWAY: 99TH AVENUE TO 87TH AVENUE Request approval of Change Order No. 6 for Contract 2021-016 with TY Lin, International for additional design services on Northern Parkway: 99TH AVENUE TO 87TH AVENUE for a sum not-to-exceed nine hundred eleven thousand, one hundred forty-eight dollars ($911,148). The contract completion date does not require an extension. Supervisory District No. 4 (C-64-24-235-X-01)
Attachments (1)

2 item(s) sharing C-number base C-64-24-235-X