C-number: C-69-18-037-5
Vote — approved
| Clint Hickman | yes |
| Jack Sellers | yes |
| Thomas Galvin | yes |
| Bill Gates | yes |
| Steve Gallardo | yes |
Ayes: Clint Hickman, Jack Sellers, Thomas Galvin, Bill Gates, Steve Gallardo
Item Text
135. CHANGE ORDER NO. 7 FOR MCMICKEN DAM REHABILITATION - PHASE 1 Approve Change Order No. 7 (CO 7) Contract No. 2018C012 for McMicken Dam Rehabilitation - Phase 1. CO No. 7 will reimburse Archer Western Construction, LLC (AWC) for additional costs to cover concrete, rebar, and riprap material escalations because of project delays. CO 7 will also reimburse AWC for additional costs for rebar bends and waterstop modifications required; these escalations will result in the addition of $568,108.08. Approval of this change order establishes a new contract amount of $21,819,229.89. This item impacts Supervisorial District 4. (C-69-18-037-5-01)
1 item(s) sharing C-number base C-69-18-037-5