Vote — approved
Clint Hickman yes
Jack Sellers yes
Thomas Galvin yes
Bill Gates yes
Steve Gallardo yes
Ayes: Clint Hickman, Jack Sellers, Thomas Galvin, Bill Gates, Steve Gallardo
Item Text
134. CHANGE ORDER NO. 5 TO CONTRACT FOR ON-CALL DAM SAFETY GEOTECHNICAL ENGINEERING Approve Change Order No. 5 to On-Call Dam Safety Geotechnical Engineering Contract FCD 2021C007 for required annual maintenance, such as instrumentation installation oversight and monitoring, geotechnical investigations at dams, future Dam Safety related engineering projects, District studies, and other assignments as needed. Change Order No. 5 for On-Call Contract FCD 2021C007 adds funds in the amount of $1,000,000 to the existing contract, increasing the value of the contract to $2,600,000 and a new completion date of June 29, 2026. This item impacts all Supervisorial Districts. (C-69-22-114-X-01)
Attachments (1)

1 item(s) sharing C-number base C-69-22-114-X