Vote — approved
Steve Gallardo yes
Jack Sellers yes
Bill Gates yes
Steve Chucri yes
99.IGA FOR PHASE II-A OF THE GRANITE REEF WATERSHED DRAINAGE IMPROVEMENTS Approve Intergovernmental Agreement (IGA) FCD 2020A029 for the Design, Rights-of-Way Acquisition & Utility Relocations for the Phase II-A of the Granite Reef Watershed Drainage Improvements (PROJECT) between the City of Scottsdale (CITY) and the Flood Control District of Maricopa County (DISTRICT). This Agreement shall become effective as of the date it has been executed by all PROJECT PARTNERS and shall expire ten years f
Item Text
99. IGA FOR PHASE II-A OF THE GRANITE REEF WATERSHED DRAINAGE IMPROVEMENTS Approve Intergovernmental Agreement (IGA) FCD 2020A029 for the Design, Rights-of-Way Acquisition & Utility Relocations for the Phase II-A of the Granite Reef Watershed Drainage Improvements (PROJECT) between the City of Scottsdale (CITY) and the Flood Control Dist rict of Maricopa County (DISTRICT). This Agreement shall become effective as of the date it has been executed by all PROJECT PARTNERS and shall expire ten years from that date, or upon Project completion, whichever occurs first. The PROJECT consists of the design of a large diameter storm drain that will convey runoff from Granite Reef Wash, just north of Thomas Road south along the Pima Road corridor to McKellips Rd, and ultimately out to the Salt River. Once constructed, this PROJECT will help reduce the flood hazard in the area by capturing and conveying runoff from the 100-year event. This is a joint project with the CITY and the estimated total PROJECT cost is $4,100,000. The cost will be shared 50/50 with the CITY making the DISTRICT’s estimated s hare of the PROJECT cost $2,050,000. The CITY will take the lead for the PROJECT. This Agenda Item impacts Supervisorial District 2. (C-69-22-118-X-00)
Attachments (2)

1 item(s) sharing C-number base C-69-22-118-X