C-number: C-73-16-046-5
Item Text
40. CHANGE ORDER TO CONTRACT WITH HENSEL PHELPS CONSTRUCTION FOR INTAKE TRANSFER AND RELEASE FACILITY DETENTION FACILITY PHASE 2 Approve Change Order #4 to the Guaranteed Maximum Price (GMP#3) Contract with Hensel Phelps Construction Company in the amount of $87,427.00 increasing the contract from $139,733,035.20 to $139,820,426.20 for new Maricopa County Sheriffs’ Intake Transfer Release Facility (15062-CMR GMP#3). The purpose of this Change Order is Hensel Phelps Construction Company’s final direct and indirect costs based on the settlement agreement dated March 31, 2020. This change order resolves and settles all issues related to the ITR Project. (C-73-16-046-5-04)