C-number: C-73-17-017-7
Vote — approved
| Clint Hickman | yes |
| Jack Sellers | yes |
| Steve Chucri | yes |
| Bill Gates | yes |
| Steve Gallardo | yes |
102.MARICOPA ASSESSOR REPLACEMENT SYSTEM (MARS) PROJECT CHANGE REQUEST #5 Approve the Assessor’s Office proposed 13129-1-RFP Project Change Request #5 (PCR05) with ESRI Canada. The change will accommodate critical software development work and create a single Go-Live date. This PCR will allow the Contractor to develop necessary business statutory items with the official Go-Live date changed from February 2021 to February 2022. The financial impact for this contract change will be $1,530,101 for
Item Text
102. MARICOPA ASSESSOR REPLACEMENT SYSTEM (MARS) PROJECT CHANGE REQUEST #5 Approve the Assessor’s Office proposed 13129-1-RFP Project Change Request #5 (PCR05) with ESRI Canada. The change will accommodate critical software development work and create a single Go-Live date. This PCR will allow the Contractor to develop necessary business statutory items with the official Go-Live date changed from February 2021 to February 2022. The financial impact for this contract change will be $1,530,101 for project costs, for a total project change of $3,984,198 including direct and indirect costs. The contract also includes operating expenses for Azure Cloud Maintenance and software subscriptions through FY 2026 with an optional ten-year renewal. These costs are detailed in the attachments and will be addressed through the annual budget process. (C-73-17-017-7-01)
Attachments (5)
MARS PCR 05 BRIEFING 110220.DOCX
pdf
MARICOPA COUNTY_13129-1-CONTRACT PCR05 CLEAN NOVEMBER 03 2020.DOCX
pdf
MARS PCR 05 SIGNATURE PAGE (002).PDF
pdf
MARICOPA COUNTY_13129-1-CONTRACT PCR05_FINAL VERSION_ NOVEMBER 3 2020.DOCX
pdf
MARICOPA COUNTY_13129-1-CONTRACT PCR05_EC REVIEW VERSION_NOVEMBER 3 201103 1501.DOCX
pdf
Vote — approved
| Jack Sellers | yes |
| Bill Gates | yes |
| Thomas Galvin | yes |
| Clint Hickman | yes |
| Steve Gallardo | abstain |
22.ASSESSOR’S OFFICE MARS PROJECT CHANGE REQUEST #6 AND BUDGET ADJUSTMENT Approve the Assessor’s Office proposed 13129-1 RFP Project Change Request #6 (PCR06) with ESRI Canada. This change request will accommodate additional critical software development work and adjust the Go-Live date from February 25, 2022, to Production Ready System date between May 24, 2022 and June 30, 2022. Financial Impact Request: These adjustments have an overall net impact of zero on the FY 2022 budget. 1. Approve an
Item Text
22. ASSESSOR’S OFFICE MARS PROJECT CHANGE REQUEST #6 AND BUDGET ADJUSTMENT Approve the Assessor’s Office proposed 13129-1 RFP Project Change Request #6 (PCR06) with ESRI Canada. This change request will accommodate additional critical software development work and adjust the Go-Live date from February 25, 2022, to Production Ready System date between May 24, 2022 and June 30, 2022. Financial Impact Request: These adjustments have an overall net impact of zero on the FY 2022 budget. 1. Approve an increase to the Computer Aided Mass Appraisal (CAMA) project (13129-1 RFP) in the amount of $200,000 from a total of $28,871,921 to $29,071,921. 2. Approve the following fund transfer in FY 2022: a. $200,000 from the General Fund (100) to the County Improvement COPS Series 2015 Fund (440) 3. In accordance with A.R.S. §42-17106(B), authorize the following amendments to the FY 2022 budget: a. Decrease the expenditure appropriation in the Assessor (D120) General Fund (100) Operating (OPER) budget by $200,000. b. Increase the expenditure appropriation in the Non Departmental (D470) General Fund (100) Operating (OPER) budget in the line “Unassigned Contingency” (4711) by $200,000. c. Increase the expenditure appropriation in the Non Departmental (D470) County Improvement COPS Series 2015 (440) Computer Aided Mass Appraisal (CAMA) by $200,000. d. Increase the revenue appropriation in the Non Departmental (D470) County Improvement COPS Series 2015 (440) Non Recurring (NRNP) budget by $200,000. e. Increase the revenue and expenditure appropriation in the Eliminations (D980) Eliminations Fund (900) Non Recurring (NRNP) budget by $200,000. (C-73-17-017-7-02)
Attachments (4)
MARICOPA COUNTY_13129-1-CONTRACT_PCR06 FINAL.PDF
pdf
MARICOPA COUNTY_PSA_AMENDMENT 6_SF7743_FEB 2022_PARTIALLYSIGNED.PDF
pdf
MARICOPA COUNTY_13129-1-CONTRACT_PCR06 FINAL.DOCX
pdf
(02.23.2022) C-73-17-017-7-02 ASSESSOR'S OFICE MARS PROJECT CHANGE REQUEST #6 AND BUDGET ADJUSTMENT FINANCIAL IMPACT.XLSX
pdf
Vote — approved
| Bill Gates | yes |
| Clint Hickman | yes |
| Jack Sellers | yes |
| Thomas Galvin | yes |
| Steve Gallardo | abstain |
135.ASSESSOR'S OFFICE MARS PROJECT CHANGE REQUEST #7 Approve the Assessor’s Office proposed RFP Project Change Request #7 (PCR07) to the County’s contract with ESRI Canada, in a form to be approved by the County Attorney’s Office. This change request will increase the contract amount within the existing project budget and modify the contract terms to: adjust the date for delivery of a production-ready system from May 24, 2022 to August 1, 2022; adjust the start of subscription payments to August
Item Text
135. ASSESSOR'S OFFICE MARS PROJECT CHANGE REQUEST #7 Approve the Assessor’s Office proposed RFP Project Change Request #7 (PCR07) to the County’s contract with ESRI Canada, in a form to be approved by the County Attorney’s Office. This change request will increase the contract amount within the existing project budget and modify the contract terms to: adjust the date for delivery of a production-ready system from May 24, 2022 to August 1, 2022; adjust the start of subscription payments to August 1, 2022; adjust the Go-Live date from June 30, 2022 to October 3, 2022; adjust the milestones for retainage payouts to reflect appropriate tests of system functionality consistent with the revised delivery timel ine; require the vendor to perform an additional data migration prior to the Go-Live date; and accommodate additional critical software development work, including an additional post Go-Live release of system features. (C-73-17-017-7-02)
Attachments (1)
Vote — approved
| Clint Hickman | yes |
| Jack Sellers | yes |
| Thomas Galvin | yes |
| Bill Gates | yes |
| Steve Gallardo | yes |
Ayes: Clint Hickman, Jack Sellers, Thomas Galvin, Bill Gates, Steve Gallardo
Item Text
125. ASSESSOR'S OFFICE MARS PROJECT CHANGE REQUEST #8 Approve the Assessor's Office proposed 13129-1 RFP Project Change Request #8 (PCR08) with ESRI CA, in a form to be approved by the County Attorney's Office. This change request will adjust the date for which the Azure Cloud tenant will be migrated from Contractor hosted to County hosted. This request would change the deadline date for this Azure Cloud migration from June 30, 2023 to December 31, 2023. (C-73-17-017-7-00)
Attachments (2)
Vote — approved
| Clint Hickman | yes |
| Jack Sellers | yes |
| Thomas Galvin | yes |
| Bill Gates | yes |
| Steve Gallardo | yes |
Ayes: Clint Hickman, Jack Sellers, Thomas Galvin, Bill Gates, Steve Gallardo
Item Text
27. ASSESSOR’S OFFICE MARS PROJECT CHANGE REQUEST #9 Approve the Assessor’s Office proposed 13129-1-RFP Project Change Request #9 (Amendment No. 9) to the County’s MARS Project contract with ESRI Canada. This change request will require a contract increase to the Total Not to Exceed for the Initial Ten (10) Year Term by $4,064,000 to a new total of $20,159,399.80. As outlined the PCR09 Detail document attached: the project change request will allow ESRI Canada to continue to host the GAMA System in their Cloud Environment at a fixed cost to the County through the end of the initial 10-year term ending 12-31-26, removes the Azure Maintenance Costs in FY24-FY26, this change request will also provide an Option for Future Development if requested by the County, and various language updates outlined in the attachment. (C-73-17-017-7-00)
Attachments (2)
5 item(s) sharing C-number base C-73-17-017-7