C-number: C-73-17-027-5
Vote — approved
| Steve Gallardo | abstain |
| Bill Gates | abstain |
| Clint Hickman | abstain |
| and Clint Hickman | yes |
| Denny Barney | abstain |
| Gallardo Government Relations | yes |
| Steve Chucri | yes |
40.CENTRAL PLANT HVAC EQUIPMENT MODIFICATIONS (179001-DBB)Approve and authorize the award of a Design Bid-Build (DBB) construction contract between Maricopa County and Karber Corporation, Phoenix, Arizona ,in an amount not-to-exceed $363,377.00 to upgrade the Courts Complex Central Plant, a multi-phase project, to include demolition work, and two (2) additional heat exchangers. (C-73-17-027-5-00) Motion to approve by Supervisor Chucri, seconded by Supervisor Gallardo Ayes: Barney, Chucri, Gates,
Item Text
40. CENTRAL PLANT HVAC EQUIPMENT MODIFICATIONS (179001-DBB) Approve and authorize the award of a Design Bid-Build (DBB) construction contract between Maricopa County and Karber Corporation, Phoenix, Arizona, in an amount not-to-exceed $363,377.00 to upgrade the Courts Complex Central Plant, a multi-phase project, to include demolition work, and two (2) additional heat exchangers. (C-73-17-027-5-00)
Attachments (1)
1 item(s) sharing C-number base C-73-17-027-5