C-number: C-73-20-029-5

C-number: C-73-20-029-5-00
Item: #100
Revision: 00
Item Text
100. COUNTY ADMINISTRATION BUILDING RE-STACK PHASE II (190097-CMR) Approve the Phase II (Construction Phase) Construction Manager at Risk contract with Layton Construction in the amount of $44,859,484.00. The purpose of the contract is to provide construction services for the County Administration Building Restack located at 301 W. Jefferson Street, Phoenix. (C-73-20-029-5-00)