C-number: C-73-22-035-X
Vote — approved
| Jack Sellers | yes |
| Bill Gates | yes |
| Clint Hickman | yes |
| Steve Gallardo | yes |
76.220012-ROQ, WAREHOUSE – DURANGO CAMPUS Approve the Contract for Award at an estimate of $802,706.00 with an estimated completion date of March 30, 2024. The purpose of the contract is to provide professional design services for the MCSO Warehouse at the Durango Campus. Arrington Watkins (C-73-22-035-X-00) Motion to approve by Supervisor Steve Gallardo, seconded by Supervisor Bill Gates Ayes: Jack Sellers, Bill Gates, Clint Hickman, Steve Gallardo
Item Text
76. 220012-ROQ, WAREHOUSE – DURANGO CAMPUS Approve the Contract for Award at an estimate of $802,706.00 with an estimated completion date of March 30, 2024. The purpose of the contract is to provide professional design services for the MCSO Warehouse at the Durango Campus. Arrington Watkins (C-73-22-035-X-00)
Attachments (1)
1 item(s) sharing C-number base C-73-22-035-X