C-number: C-73-23-067-X
Vote — approved
| Jack Sellers | yes |
| Thomas Galvin | yes |
| Bill Gates | yes |
| Steve Gallardo | yes |
| Clint Hickman | absent |
Ayes: Jack Sellers, Thomas Galvin, Bill Gates, Steve Gallardo Absent: Clint Hickman
Item Text
37. 220083-CMR, EMERGENCY MANAGEMENT FACILITY (PHASE II) Approve and Award a Construction Manager at Risk Phase 2 Construction Contract between Maricopa County and Kitchell Contractors Inc. of Arizona, in an amount n ot to exceed amount of $22,354,866.00 with an estimated completion date of 9/5/2024, subject to the County being in receipt of the performance, and payment bonds after award has been made. The purpose of the contract is for the renovating the existing Mari copa County Emergency Management Facility. (C-73-23-067-X-00)
Attachments (1)
1 item(s) sharing C-number base C-73-23-067-X