45. CONSTRUCTION MANAGER AT RISK CONTRACT WITH WOODRUFF CONSTRUCTION FOR THE LOWER BUCKEYE CENTRAL PLANT UPGRADE PROJECT Approve and award the Phase II Construction Contract (918-11-037) GMP #1 in an amount not-to-exceed $2,842,485 to Woodruff Construction for the Lower Buckeye Central Plant Upgrade Project (1964-11-1096). The project is scheduled for substantial completion in approximately August of 2011. The procurement of this contract was conducted in accordance with all Arizona laws and statutes, and in accordance with Article 5 of the Maricopa County Procurement Code. This facility is located in District 5. (C-91-11-133-5-00)