REPORT OF PLANNING HEARING OFFICER ACTION  
Byron Easton, Planner III, Hearing Officer  
Teresa Garcia, Planner I, Assisting  
 
May 21, 2025 
 
ITEM NO: 1 
 
 
DISTRICT NO. 1 
SUBJECT: 
 
 
 
Application #: 
PHO-1-25--Z-131-04-1 
Location: 
Southwest corner of Pyramid Peak Parkway and Northern 
Lights Way 
Zoning:  
S-1 SP (Approved R1-8) 
Acreage:  
15.8 
Request: 
1) 
Request to modify Stipulation 2 regarding general 
conformance to the site plan date stamped May 9, 
2005. 
2) 
Request to modify Stipulation 4 regarding dedications 
and improvements for Pyramid Peak Parkway. 
Applicant: 
Brian Greathouse, Burch & Cracchiolo, P.A. 
Owner: 
Pyramid Peak GM, South LLC; c/o Camelot Homes, Ryan 
Benscoter 
Representative: 
Brian Greathouse, Burch & Cracchiolo, P.A. 
 
ACTIONS: 
 
Planning Hearing Officer Recommendation: The Planning Hearing Officer took 
this case under advisement.  On May 29, 2025, the Planning Hearing Officer took 
the case out from under advisement and recommended approval with a 
modification. 
 
Village Planning Committee (VPC) Recommendation: The Deer Valley Village 
Planning Committee chose not to hear this request. 
 
DISCUSSION: 
 
Brian Greathouse, representative of Burch & Cracchiolo P.A, gave an overview 
of the current site and the modification request. He stated the applicant is 
withdrawing the request to modify Stipulation 4 and they are seeking to only 
modify Stipulation 2 regarding general conformance to the site plan date 
stamped May 9, 2005.  Representing Camelot Homes, Mr. Greathouse indicated 
the site is located within the Gold Mountain Preserve gated community. He 
stated Camelot Homes built phase one of the community over the last decade 
but could not develop the remaining site due to the mining pit. He stated the pit 
has been filled with inert materials so the remaining homes can be developed. 
Attachment B

Planning Hearing Officer Summary of May 21, 2025 
Application PHO-1-25--Z-14-16-8 
Page 2 
 
He explained how the developer laid out the subdivision indicated on the 2005 
site plan, but did not build homes in the community. He explained that Camelot 
Homes acquired the property and made some modifications to the site plan to 
accommodate the needs of homeowners in the area, resulting in a simpler 
conceptual site plan that contains 31 lots. 
 
Byron Easton, Planning Hearing Officer, asked if the northern portion of Northern 
Lights Way was used for the mining project. Mr. Greathouse was unsure and 
indicated it became a regional retention basin. Mr. Easton asked what the 
approximate timeline was for the site to be developed. Mr. Greathouse answered 
between 1-2 years due to how much materials is going to be available and 
imported. 
 
Mr. Easton asked Mr. Greathouse if he was aware of the discrepancies between 
the final plat and the rezoning case and if he can elaborate. Mr. Greathouse 
stated he is aware of the labeling issues regarding phases 1, 2 and 3 of the 
project. He stated it was a little confusing and may have been labeled incorrectly 
during certain processes, but the lotting, dedication, and easements shown are 
accurate. 
 
Mr. Easton stated his only concern results from the request to modify Stipulation 
4 regarding dedications and improvements for Pyramid Peak Parkway. He 
reiterated Mr. Greathouse withdrew the request to modify Stipulation 4 as the 
Street Transportation Department was not going to support the request. He 
stated the conceptual site plan (date stamped January 27, 2025) did not show 
the offsite street improvements reflected in Stipulation 4; therefore, he cannot 
approve general conformance. He asked Mr. Greathouse to submit a revised site 
plan as soon as possible that shows the offsite improvements.  Once received 
and reviewed, Mr. Easton will take the case out from under advisement.  In the 
meantime, Mr. Easton took the case under advisement. 
 
FINDINGS: 
 
1) The request to modify Stipulation 2 regarding general conformance to a 
site plan is recommended to be approved with a modification to provide 
more standard conformance language and update the date stamp.  The 
stipulated site plan depicted a 26 lot (Lots 36-61) subdivision with a 
density of approximately 1.8 dwelling units per acre.  Due to changing 
housing demands, the conceptual site plan shows smaller lots with an 
increase of 5 lots, for a total of 31 lots and a density of approximately 2.2 
dwelling units an acre.  This change is appropriate for the area and will be 
compatible with adjacent single-family homes. 
 
The proposed landscaping has been increased over the amount shown on 
the stipulated site plan.

Planning Hearing Officer Summary of May 21, 2025 
Application PHO-1-25--Z-14-16-8 
Page 3 
 
2) The applicant chose to withdraw the request to modify Stipulation 4 
regarding dedications and improvements for Pyramid Peak Parkway. 
 
STIPULATIONS: 
 
1. 
That Phase II shall vest and the Special Permit shall be removed upon 
submittal to the Planning Department of documentation that mining and 
landfill operations have ceased. 
 
 
2. 
That THE development shall be in general conformance to the site plan 
date stamped MAY 28, 2025 May 9, 2005 with specific regard to the 
density, lot size and open space, as approved or modified by the 
FOLLOWING STIPULATIONS AND APPROVED BY THE PLANNING 
AND Development Services Department. 
 
 
3. 
That Phase I of the development shall include lots 1 through 35 and shall 
include dedication of the private street connection to north Pyramid Peak 
Parkways as shown on the plan. Construction of the private street 
connection and dedication of right-of-way to north Pyramid Peak Parkway 
are not required under Phase I. 
 
 
4. 
That Phase II shall consist of the remainder of the lots (exclusive of Phase 
I) and shall include dedication and improvements for north Pyramid Peak 
Parkway for the full length of the property or as approved by the 
Development Services Department. The private street connection to north 
Pyramid Peak Parkway shall be constructed with Phase II. 
 
 
5. 
That Prior to final site plan approval, the property owner shall record 
documents that disclose to purchasers of the property within the 
development(s) the existence (or prior existence) and operational 
characteristics of the landfill and any environmental impact of the landfill 
and existence and any operational characteristics of the Glendale Water 
Treatment Plant. The form and content of such documents shall be 
reviewed and approved by the City Attorney.  
 
 
6. 
That Right-of-way totaling 65 feet as measured from the centerline shall 
be dedicated for the west half of Pyramid Peak Parkway per stipulation 3, 
as approved or modified by the Development Services Department. 
 
 
7. 
That The developer shall construct all streets within and adjacent to the 
development with paving, curb, gutter, sidewalk, curb ramps, streetlights, 
median islands, landscaping and other incidentals as per plans approved 
by the Development Services Department per stipulations 3 and 4. All 
improvements shall comply with all ADA accessibility standards.

Planning Hearing Officer Summary of May 21, 2025 
Application PHO-1-25--Z-14-16-8 
Page 4 
 
8. 
That The applicant shall complete and submit the Developer Project 
Information Form for the MAG Transportation Improvement Program to the 
Street Transportation Department. This form is a requirement of the EPA 
to meet clean air quality requirements. 
 
Upon request, this publication will be made available within a reasonable length 
of time through appropriate auxiliary aids or services to accommodate an 
individual with a disability. This publication may be made available through the 
following auxiliary aids or services: large print, Braille, audiotape or computer 
diskette. To request a reasonable accommodation, please contact Saneeya Mir 
at saneeya.mir@phoenix.gov or (602) 686-6461 or TTY: 7-1-1.