Attachment A - FY25-30 Public Art Plan DRAFT.pdf

City of Phoenix — Economic Development and the Arts Subcommittee (2025-05-28)

View PDF Meeting page

Extracted text (via pymupdf) 45434 characters
phoenix.gov/arts 
 PHOENIX OFFICE OF ARTS AND CULTURE 
FY 2025-2030 PUBLIC ART PLAN 
ATTACHMENT A

Cover Artwork 
Top Left: 
Jenny Boehme and Josie Davis 
The Burrow 
Roesley Park, District 7 
¡Sombra! Experiments in Shade temporary installation 
Top Right: 
Ariana Enriquez 
The Creek Carves A Path 
305 W. Washington Payment Center, District 7 
Bottom:   
Lisa Bernal Brethour 
Moon Dance 
Perry Park, District 8

Introduction and Goals………..………………………………………………………………………………………………………  5 
Fiscal Year (FY) 2024-2025 Completed Public Art Projects………………………………………………………….  7 
FY 2024-2025 Completed Retrofit and Refurbishment Projects.…….……………………………….…………… 10 
FY 2024-2025 Awards and Accomplishments………………………………………………………………….…………… 12 
FY 2025-2030 Public Art Project List………………………………………………………………………………………….… 13 
Organized by Project Number 
General Obligation Bond: Proposition 1 
 14 
General Obligation Bond: Proposition 2 
 14 
General Obligation Bond: Proposition 3 
 14 
General Obligation Bond: Proposition 4 
 15 
32nd Street Drought Pipeline and Neighborhood Improvements 
15 
Shade, Cooling, and Heat Mitigation 
15 
Dobbins Road Improvement Project (Loop 202 to 27th Avenue)       
16 
3rd Street Connector (Rio Salado to Lincoln Street)       
16 
State Route 303 
16 
McDowell Road Revitalization Project 
15 
  NEW: State Road 30 
17 
  Portable Works at Phoenix Sky Harbor International Airport 
17 
Terminal 3 Improvements at Phoenix Sky Harbor International Airport     
17 
Aviation Pooled Funds (Deer Valley Airport) 
18 
 NEW: 35th Avenue Overpass at Grand Avenue 
18 
  27th Avenue Solid Waste Management Facility 
18 
 Public Works Community Projects 
18 
 Artist Initiatives 
19 
 Civic Space Park: Her Secret is Patience (Refurbishment and Retrofit) 
19 
 Mountain Preserve Enhancements – South Mountain Park and Preserve 
19 
 Reach 11 Sports Complex: The Wings (Refurbishment and Retrofit) 
20 
Dreamy Draw Pedestrian Bridge (Refurbishment and Retrofit)      
20 
Laveen Heritage Park 
20 
Lone Mountain Park 
20 
3rd Street Rio Salado Bicycle/Pedestrian Bridge 
21 
Lookout Mountain Park: Desert Passages (Refurbishment and Retrofit) 
21 
 100 W. Washington Street 
21 
North Phoenix Reservoir      
22 
Harmon Park: River of Shade (Refurbishment and Retrofit)      
22 
Sunnyslope Canal Demonstration Project (Refurbishment and Retrofit)    
22 
Table of Contents

Arizona Falls: Waterworks (Refurbishment and Retrofit) 
22 
Water Services West Yard 
23 
Community Well Site Enhancements 
23 
Cortez Park and Well Site 
23 
Maryvale Grand Canal Crossing 
23 
El Reposo Park 
24 
Sueño Park 
24 
Paradise Valley Park 
24 
Western Canalscape (Phase 1 and 2) 
24 
Collaborative Neighborhood Projects 
25 
Identification Plaques and Interpretive Signage      
25 
NEW: Major Refurbishments and Restorations Planning 
25 
Tres Rios Wetlands 
26 
Lift Stations and Neighborhood Facilities 
26 
Rio Reimagined 
26 
FY 2025-2030 Multi-Year Initiatives………..…….…………………………….……………………………………….……… 27 
FY 2025-2030 Public Art Plan Summary…………………….………………………………………………………………… 29

Introduction and Goals 
Introduction 
The Phoenix Office of Arts and Culture is the City's designated local arts agency. It champions, 
promotes, and supports the local arts and culture community, making Phoenix a great place 
to live, work, and visit.   
The Phoenix Office of Arts and Culture (POAC) is a local and national leader in the public art 
field and has garnered numerous awards for design excellence, including Design for 
Transportation awards from the U.S. Department of Transportation and Public Art Network 
Year in Review awards from Americans for the Arts. 
Established in 1986, the Public Art Program works with local, national, and international artists 
to create a more beautiful and vibrant city. By ordinance, one percent of the Capital 
Improvement Program is utilized to enhance the design of public buildings, infrastructure, and 
spaces within the City of Phoenix. Since its inception, the program has completed more than 
200 major projects, including airport terminals, community centers, streetscapes, parks, canals, 
transit centers, bridges, underpasses, recycling centers, and public safety buildings. 
A competitive procurement process identifies artists for public art projects. The process utilizes 
a selection panel containing art and design professionals, project stakeholders, and community 
representatives relevant to the project's location. City staff and project team members often 
serve as non-voting advisors to the panel. Panelists are responsible for reviewing applications 
submitted in response to a Call to Artists, interviewing finalists, and making recommendations 
to the Arts and Culture Commission, a volunteer citizen advisory board appointed by City 
Council. The quality of work, suitability for the project, and the ability to work well with the 
community and other design professionals influence the selection panel's final 
recommendations. The Phoenix City Council approves the final recommendation before the 
contract is executed and artists begin work. 
POAC develops the Public Art Plan annually with input and assistance from the Mayor and 
City Council, city residents, artists, city departments that provide public art project funding, 
and the Arts and Culture Commission. The timing of the plan coincides with the annual Capital 
Improvement Program budgeted per fiscal year (July 1 – June 30; for example, FY 2025-2026 = 
July 2025 – June 2026).  The plan outlines several project types, including design team projects, 
permanent commissions, purchases of existing artwork, temporary commissions, art 
refurbishment and retrofits, and master planning.  Overhead costs to administer the projects in 
the Plan, including staff costs, are approximately 15% of the total five-year budget.

Goals 
Public art projects within the FY 2025-2030 Public Art Plan are prioritized based on 
opportunities to integrate artwork into individual Capital Improvement Program projects and 
their potential impact on the neighborhood and the broader arts community.  These decisions 
are made closely with funding departments and City Council offices.  Under these parameters, 
the FY 2025-2030 Public Art Plan focuses on the equitable distribution of funds, as allowable by 
the percent-for-art ordinance, and the diversification of the public art collection through 
broadening the types of project opportunities and continued outreach to new artists and arts 
organizations.  This year, only a few new projects were added based on the City’s focus on 
General Obligation Bond projects (previously included in the Plan) and the addition of grant-
funded projects. 
Additionally, POAC strives to develop project opportunities and program policies that align with 
strategic goals outlined in several long-range planning documents, like the Climate Action Plan 
and the Shade and Tree Master Plan.  Some of these efforts are realized through the FY 2025-
2030 Public Art Plan, like promoting the use of sustainable materials and sourcing methods to 
commissioned artists and proactively seeking community input on project opportunities.  As the 
FY 2025-2030 Public Art Plan is implemented, POAC will continue integrating these important 
citywide goals. 
For more information about the Phoenix Office of Arts and Culture and the Public Art Program, 
visit www.pheonix.gov/arts.

FY 2024-2025 Completed Public Art Projects 
CAPITAL IMPROVEMENT PROGRAM PROJECTS 
Solano Park 
Council District 4 
Artists Tom Drugan and Laura Haddad were contracted to 
create artwork for Solano Park, with a particular focus on 
the skate park. The artwork, titled Pipe Dreams, was 
designed in partnership with the Parks Department, the 
local skate community, and area residents. It references a 
late 1970s skate spot known as the “Desert Pipes,” a series 
of large concrete pipe sections temporarily stockpiled in 
the desert. The artwork includes three steel pipes; the 
outer pipes are skateable. This project was dedicated in 
November 2024. 
Perry Park 
Council District 8 
This artwork by Lisa Bernal Brethour depicts a 
modern “tortoise and the hare” story with 9 
lithomosaics scattered throughout the park. At the 
center of the park, a lithomosaic labyrinth with a 
night-blooming cereus desert flower encourages 
visitors to move like a bee into the center of the 
flower.  In the skate plaza, pictured right, a trompe 
l’oeil lithomosiac depicts a canyon for skaters to 
jump that complements other obstacles in the 
plaza.  Also at the skate plaza are seven vertical 
shade panels (pictured on the cover) that provide 
much needed respite for skaters.  This project was 
dedicated on April 5, 2025.

305 W. Washington Mural 
Council District 7 
Artist Ariana Enriquez completed an 
interior mural for the utility payment 
center lobby at 305 W. Washington.  
The mural embodies the calm 
characteristics of water by using a cool 
color palette of blues, greens and 
violets. The foreground is abundant 
with botanicals, birds and butterflies 
that are native to Arizona.

EXTERNAL AND INTERNAL PARTNERSHIP PROJECTS 
HIV/AIDS Awareness Mural 
Council District 7 
Mayor Kate Gallego, in partnership with 
the Phoenix Office of Arts and Culture, 
Southwest Center, One N Ten, and Aunt 
Rita's Foundation, and with support from 
Artlink Inc., commissioned a semi-
permanent mural for the south wall of 
The Parsons Center for Health and 
Wellness located in central Phoenix.  
The goal of this project was to raise awareness about HIV prevention, testing, and treatment, 
inspire community engagement, and reduce stigma around HIV. It is to serve as a visual, public 
reminder of the importance of proactive health measures and support for those affected by 
HIV, encouraging people to take action through education, testing, and advocacy while 
enhancing the experience of those seeking health, wellness, and community services from the 
organizations located on the property. 
Sidewalk Shade project 
City-wide 
(Partial completion) 
Providing shade for pedestrians and bicycle riders 
can improve public health and the economic 
vitality of communities. The City will construct 19 
shade structures in high-traffic public rights-of-
way at major intersections and crosswalks where 
people are forced to wait for signal changes. Three 
local artists, Isaac Caruso, Heidi Dauphin, and Sara 
Altieri, were hired to contribute aesthetic designs 
to the canopies. The Office of Heat Response and 
Mitigation, the Streets Transportation 
Department, and the Phoenix Office of Arts and 
Culture are working in partnership to complete 
this project by Spring 2026. 
 Canopy Design by Isaac Caruso

Nature Fest PHX Temporary Installation 
District 8 
In partnership with the Office of Environmental Programs and 
the Parks and Recreation Department, artist Martin Moreno 
was commissioned to create an interactive artwork for Nature 
Fest PHX located at the Rio Salado Habitat Restoration Area. 
The temporary interactive sculpture, Pachamama, was 
featured as part of the annual event that celebrates urban 
green spaces, wildlife, and community.  Throughout the event, 
Martin guided attendees to paint the sculpture that honored 
mother earth and her habitat around Rio Salado (Salt River).

Our Shared Environment 
Council District 4 
Specialists experienced with the 
building material adobe completed 
extensive renovations of Our Shared 
Environment by Marylin Zwak. Several 
issues were addressed, including water 
damage, cracking, and soot from 
vehicle exhaust. The wall treatments 
are at the intersection of SR51 and 
Thomas Road. The 3-year project was 
completed in the spring of 2025. 
Desert Spring 
Council District 2 
This artwork was damaged by a vehicular crash in 2023.  Several linear feet of damage occurred 
to the mosaic glass tiles incorporated into bridges along Desert Sonoran Blvd. Pedestrians and 
cyclists using the sidewalk can appreciate the intricate design of desert flora created by artists    
R & R Studios. Repairs were completed in February of 2025. 
FY 2024-2025 Completed Refurbishment and Retrofit Projects

River of Shade 
Council District 8 
This artwork, located at Harmon Park, was created 
in 2010 and needed several repairs. Artist Stacy 
Levy designed paths embedded with colorful glass 
invoking the flow of water that are integrated into 
the design of the park. The project repaired 
cracked and uneven pavement and replaced worn 
areas of the embedded glass.

FY 2024-2025 Awards and Accomplishments 
Bloomberg Philanthropies Public Art Challenge Award 
In October 2023, Bloomberg Philanthropies selected Phoenix as 
one of eight winners of its prestigious Public Art Challenge. This 
unique program supports temporary public art projects that 
address important local civic issues in cities nationwide. 
Phoenix's project, ¡Sombra! Experiments in Shade, 
received $1,000,000 to commission nine artists to create 
shading and cooling installations in response to extreme 
urban heat.   
These temporary projects were installed at parks across 
Phoenix in Spring 2025 and will be on view through 
September 2025.  The project will conclude with a celebration 
at Memorial Hall at Steele Indian School Park on September 20.  
For mor information, visit www.sombraphx.org.  
US Water Prize – Outstanding Artist 
Bobby Zokaites 
Nominated by the Water Services Department, artist 
Bobby Zokaites was selected as a winner for the 2025 
US Water Prize in the Outstanding Artist category. 
According to the US Water Alliance, Bobby has “gone 
above and beyond in terms of One Water solutions.” 
The award will be made public at their annual 
conference, One Water Summit, in July 2025. 
Example of Bobby’s Zokaites’ work (pictured right): 
A Time Machine Called Tinaja, 2020 
Council District 5

(Organized by Project Number) 
Project Number 
AR00000027 
Project Title  
Proposition 1: Fire, Police, Streets, and Storm Drainage 
Location 
Various project locations 
Type of Project 
Design Team and Permanent Commission 
Funding Sources 
General Obligation Bonds 
Budget 
$1,632,629 
Council District 
1, 3, 5, 6, 8 
Artists will be commissioned to work with design teams to integrate public artwork into capital 
improvement projects within this bond proposition.  Projects include: Fire Station 7, Fire Station 
13, Fires Station 15, and Fire Station 51.  For more information about the General Obligation 
Bond Program, visit: www.phoenix.gov/bond.   
Project Number 
AR00000028 
Project Title  
Proposition 2: Library, Parks, and Historic Preservation 
Location 
Various project locations 
Type of Project 
Design Team and Permanent Commission 
Funding Sources 
General Obligation Bonds 
Budget 
$903,583 
Council District 
2, 7 
Artists will be commissioned to work with design teams to integrate public artwork into capital 
improvement projects within this bond proposition.  Projects include: Estrella Civic Space and 
Branch Library and Desert View Civic Space and Branch Library.  For more information about 
the General Obligation Bond Program, visit: www.phoenix.gov/bond.   
Project Number 
AR00000029 
Project Title  
Proposition 3: Economic Develop., Environment, and Cultural Facilities 
Location 
Various project locations 
Type of Project 
Design Team and Permanent Commission 
Funding Sources 
General Obligation Bonds 
Budget 
$624,603 
Council District 
TBD 
Artists will be commissioned to work with design teams to integrate public artwork into capital 
improvement projects within this bond proposition.  Tentative projects include the Latino 
Cultural Center (a location has not yet been designated for this new facility).  For more 
information about the General Obligation Bond Program, visit: www.phoenix.gov/bond.   
FY 2025-2030 Public Art Project List

Project Number 
AR00000030 
Project Title  
Proposition 4: Affordable Housing, Senior Centers 
Location 
Various project locations 
Type of Project 
Design Team and Permanent Commission 
Funding Sources 
General Obligation Bonds 
Budget 
$600,649 
Council District 
4, 7, 8 
Artists will be commissioned to work with design teams to integrate public artwork into capital 
improvement projects within this bond proposition.  Projects include: McDowell Senior Center 
and the Choice Neighborhood Housing Development.  For more information about the General 
Obligation Bond Program, visit: www.phoenix.gov/bond.   
Project Number 
AR63000030 
Project Title  
32nd Street and Drought Pipeline Neighborhood Improvements 
Location 
Pipeline Corridor, from Cheryl Dr. to Cholla St. 
Type of Project 
Design Team and Permanent Commission 
Funding Sources 
Water Capital Funds 
Budget 
$438,187 
Council District 
3 
Artist Bobby Zokaites was contracted in a previous fiscal year to work with the community, 
Street Transportation and Water Services, to integrate public art elements into the North 32nd 
Street corridor design between Cheryl Drive Blvd. and Cholla St. following the Drought Pipeline 
improvements. This project is in the fabrication phase and is expected to be complete in fall 
2025. 
Project Number 
AR63000032 
Project Title  
Shade, Cooling, and Heat Mitigation 
Location 
Various 
Type of Project 
Design Team, Permanent and Temporary Commissions 
Funding Sources 
Streets, Wastewater and Water Capital Funds 
Budget 
$1,208,141 
Council District 
Citywide 
Artists will be contracted to work with various City Departments to enhance the pedestrian 
experience as part of the City's heat mitigation and cool corridors initiatives. These projects, 
including the 55th Avenue Promenade with artist Creative Machines, are in the planning and 
design and fabrication phases.  This fund also contains supporting funds for the Bloomberg 
Philanthropies Public Art Challenge grant.

Project Number 
AR63000034  
Project Title  
Dobbins Road Improvement Project 
Location 
Loop 202 to 27th Avenue 
Type of Project 
Design Team and Permanent Commission 
Funding Sources 
AHUR and Wastewater Capital Funds 
Budget 
$475,000 
Council District 
7, 8 
Artists Daniel Nez and Miguel Angel Godoy were contracted in a previous fiscal year to work 
with Street Transportation, the community, and the project design team to integrate artwork 
into the Dobbins Road Improvements Project. This project is in the design phase. 
Project Number 
AR63000035 
Project Title  
3rd Street Connector 
Location 
Rio Salado to Lincoln Street 
Type of Project 
Design Team and Permanent Commission 
Funding Sources 
AHUR, Wastewater and Water Capital Funds 
Budget 
$587,720 
Council District 
8 
An artist will be commissioned to work with Street Transportation, the community, and the 
project design team to enhance the pedestrian experience as part of the 3rd Street Connector 
project. This project is in the planning phase. 
Project Number 
AR63850021 
Project Title  
State Route 303 
Location 
Lake Pleasant Parkway to I-17 Interchange 
Type of Project 
Design Team and Permanent Commission 
Funding Source 
AHUR and Water Capital Funds 
Budget 
$524,906 
Council District 
1 
In partnership with Maricopa Association of Governments and AZ Department of 
Transportation, the City will complete State Route 303 from Lake Pleasant to the I-17 
interchange.  Project opportunities include four new ramps/bridges that will be built over 
existing roads, the 67th Avenue interchange, and the Lake Pleasant Parkway interchange.  Artist 
Eric Powell was contracted in a previous fiscal year ($80,000) to work with the design team to 
incorporate permanent public art to enhance the roadway improvements.  This project is in the 
design phase and is expected to be complete in 2026. 
Project Number 
AR63850022 
Project Title  
McDowell Road Revitalization Project 
Location 
McDowell Rd, between 7th St. and SR 51 
Type of Project 
Design Team and Permanent Commission 
Funding Source 
Street Transportation, Water and Wastewater Capital Funds 
Budget 
$300,205 
Council District 
4

The City is in the early planning stages of a project to revitalize the McDowell Road corridor 
between 7th Street and State Route 51. The focus of this study is to identify and confirm 
community-supported safety and aesthetic improvements to achieve four main goals: creating 
a safer and more inviting area for people walking or riding bicycles to locations along the 
corridor; improving navigation in and around the retail areas; enhancing access to transit; and 
fostering a sense of place and identity.  An artist will be commissioned to create artwork in 
support of these goals.  This project is in the planning phase. 
Project Number 
AR63850023 (NEW) 
Project Title  
State Road 30 
Location 
South of Interstate 10 in the southwest Valley 
Type of Project 
Design Team and Permanent Commission 
Funding Source 
AHUR Capital Funds 
Budget 
$100,000 
Council District 
7 
In partnership with Arizona Department of Transpiration, the City is in the early planning stages 
of a project to build an east-west roadway to extend 13 miles between the Loop 202 South 
Mountain Freeway in Phoenix and Sarival Avenue, near Loop 303 in Goodyear. The approved 
alignment is located approximately 4 miles south of and parallel to Interstate 10.  This project is 
in the planning phase. 
Project Number 
AR66000021 
Project Title  
Portable Works 
Location 
Phoenix Sky Harbor International Airport 
Type of Project 
Purchase of Existing Artwork, Temporary Commissions 
Funding Source 
Aviation Capital Funds 
Budget 
$184,330 
Council District 
8 
Artworks will be commissioned and purchased to support the Phoenix Airport Museum’s 
collection. The Museum’s collection presents themed exhibitions in more than 40 display areas 
throughout the Airport system. The artwork enhances the visitor's experience by creating a 
memorable environment, promoting Arizona’s unique artistic and cultural heritage, and 
honoring the airport's aviation history. These projects are in the planning phase. 
Project Number 
AR66000046 
Project Title  
Terminal 3 Modernization 
Location 
Phoenix Sky Harbor International Airport 
Type of Project 
Design Team and Permanent Commissions 
Funding Sources 
Aviation Capital Funds 
Budget 
$4,500,000 
Council District 
8 
Multiple artists will be commissioned to work with Aviation and the project design team to 
integrate artwork into the Terminal 3 Modernization project. This project is in the artist 
selection phase.

Project Number 
AR66000047 
Project Title  
Aviation Pooled Funds 
Location 
Deer Valley Airport 
Type of Project 
Permanent Commission 
Funding Source 
Aviation Capital Funds 
Budget 
$706,492 
Council District 
1 
Funds remaining from previously completed public art projects at the airport have been pooled 
to create a new opportunity to support the ongoing modernization of Deer Valley Airport.  
Specific locations and scopes of work will be developed in partnership with the Aviation 
Department.  This project is in the planning phase. 
Project Number 
AR67000014 (NEW) 
Project Title  
35th Avenue/Grand Avenue Overpass 
Location 
Intersection of 35th Avenue, Grand Avenue, and Indian School Rd. 
Type of Project 
Permanent Commission 
Funding Source 
Streets Capital Funds 
Budget 
$100,000 
Council District 
5 
An artist will be commissioned to work with Street Transportation and Arizona Department of 
Transportation to integrate artwork into the new overpass at 35th Avenue and Indian School Rd. 
The project is in the planning phase. 
Project Number 
AR70160001 
Project Title  
27th Avenue Solid Waste Management Facility 
Location 
3060 S. 27th Ave. (at Lower Buckeye Rd.) 
Type of Project 
Temporary and Permanent Commission 
Funding Source 
Solid Waste Capital Funds 
Budget 
$132,611 
Council District 
7 
Artist Katharine Leigh Simpson was contracted in a previous fiscal year to create artwork from 
materials commonly found in the City’s recycling stream. The work is currently installed at the 
Phoenix Convention Center and was slated to be reinstalled at the 27th Avenue Solid Waste 
Management Facility, however a new location is being sought.  The relocation is in the planning 
phase. 
Project Number 
AR70160004 
Project Title  
Public Works Community Projects 
Location 
Various  
Type of Project 
Temporary Commissions 
Funding Sources 
Solid Waste Capital Funds 
Budget 
$167,671 
Council District 
Citywide

Artists will be contracted to integrate temporary artwork into capital improvements in Public 
Works facilities that will connect the community with the circular economy concepts and 
bolster City efforts to increase awareness about recycling and resource management. These 
projects are in the planning phase. 
Project Number 
AR74000014 
Project Title  
Artist Initiatives 
Location 
Various Sites 
Type of Project 
Temporary Commissions 
Funding Sources 
Wastewater and Water Capital Funds 
Budget 
$776,074 
Council District 
Citywide 
This program supports creating and presenting original, new, or in-process temporary work by 
practicing Phoenix artists. Awarded artists must complete a public presentation inside city 
boundaries that primarily benefits Phoenix residents. Awards are given to artists who activate 
public buildings and spaces with various artistic installations, performances, cultural events, 
and media. These projects are on-going. 
Project Number 
AR74000017 
Project Title  
Civic Space Park: Her Secret is Patience 
Location 
Civic Space Park at 1st Ave. and Taylor St. 
Type of Project 
Refurbishments and Retrofits 
Funding Sources 
Parks and Water Capital Funds 
Budget 
$406,050 
Council District 
7 
Contractors will be hired to replace existing lighting with more efficient LED fixtures for the 
park’s award-winning landmark sculpture, Her Secret is Patience by Janet Echelman, which was 
installed in 2006. This project is in the construction phase and is expected to be complete in 
2026. 
Project Number 
AR74000019 
Project Title  
Mountain Preserve Enhancements 
Location 
South Mountain Park and Preserve 
Type of Project 
Design Team, Permanent and Temporary Commissions 
Funding Sources 
Parks and Water Capital Funds 
Budget 
$932,003 
Council District 
6, 8  
Artists commissioned for this project may create permanent or temporary artwork, interpretive 
elements, or cultural events to celebrate this beloved natural and cultural amenity.  This project 
is in the planning phase.

Project Number 
AR74000023 
Project Title  
Reach 11 Sports Complex: The Wings 
Location 
2425 E. Deer Valley Dr. 
Type of Project 
Refurbishments and Retrofits 
Funding Source 
Parks and Water Capital Funds 
Budget 
$15,000 
Council District 
2 
Contractors will be hired to repaint this functional artwork by artist Yang Chyi Lee. The project 
was completed in 2012 and sees heavy use from park users.  This project is in the 
implementation phase and is expected to be complete in 2025. 
Project Number 
AR74000025 
Project Title  
Dream Draw Pedestrian Bridge 
Location 
State Road 51 at 29th Street 
Type of Project 
Refurbishments and Retrofits 
Funding Source 
AHUR, Water Capital Funds 
Budget 
$690,491 
Council District 
3 
Contractors will be hired to repaint this functional artwork by artist Vicki Scuri. The project was 
completed in 1994 and sees heavy use from pedestrians and bicyclists.  This project is in the 
planning phase. 
Project Number 
AR74000026 
Project Title  
Laveen Heritage Park 
Location 
6925 W. Meadows Loop 
Type of Project 
Permanent Commission 
Funding Source 
Parks and Wastewater Capital Funds 
Budget 
$268,627 
Council District 
7 
Artist Dixie Friend Gay was contracted in a previous fiscal year to work with the project design 
team to enhance the new Laveen Heritage Park.  This project is in the fabrication phase and is 
expected to be complete in 2025.   
Project Number 
AR740000028 
Project Title  
Lone Mountain Park 
Location 
North 56th St & East Montgomery Rd 
Type of Project 
Design Team and Permanent Commission 
Funding Source 
Parks and Water Capital Funds 
Budget 
$424,171 
Council District 
2 
Artist team WOWHAUS was contracted in a previous fiscal year to work with the project design 
team to enhance the new Lone Mountain Park.  The project is in the design phase and is 
expected to be complete in 2026.

Project Number 
AR74000029 
Project Title  
Rio Salado Bike/Pedestrian Bridge 
Location 
3rd Street at Rio Salado 
Type of Project 
Design Team and Permanent Commission 
Funding Source 
Parks and Water Capital Funds 
Budget 
$530,687 
Council District 
8 
This project will provide a comfortable, low-stress connection for residents walking or riding 
bicycles from downtown Phoenix to or across the Rio Salado and was assigned high priority for 
the South Downtown Neighborhoods Mobility Study Area.  Barbara Grygutis was contracted in 
a previous fiscal year  to work with the design team to integrate artwork into the bridge design 
to enhance the bike and pedestrian experience.  This project is in the design phase and is 
expected to be complete in 2026. 
Project Number 
AR74000030 
Project Title  
Lookout Mountain Park: Desert Passages 
Location 
14441 N 18th St. 
Type of Project 
Refurbishments and Retrofits 
Funding Source 
Parks and Wastewater Capital Funds 
Budget 
$220,000 
Council District 
3 
A contractor will be hired to repair elements of Desert Passages by Roger Asay and Rebecca 
Davis.  The project was completed in 1990 and will be restored to the original design, in 
collaboration with the Parks and Recreation Department and the artists.  This project is in the 
implementation phase and is expected to be complete in 2026. 
Project Number 
AR76000004 
Project Title  
100 W. Washington Street 
Location 
West Washington St. and 1st Ave. 
Type of Project 
Design Team and Permanent Commission 
Funding Sources 
Excise Tax Revenue Bond and Water Capital Funds 
Budget 
$360,000 
Council District 
7 
Artist Maria Salenger was contracted in a previous fiscal year to work with the design team to 
improve the security and appearance of 100 W. Washington building, and adjacent areas, which 
will be the new Phoenix Police Department Headquarters. This project is in the design phase 
and is expected to be complete in 2026.

Project Number 
AR84800000 
Project Title  
North Phoenix Reservoir  
Location 
Cave Creek Rd. 
Type of Project 
Design Team and Permanent Commission 
Funding Sources 
Water and Wastewater Capital Funds 
Budget 
$577,356 
Council District 
2 
An artist will be commissioned to work with Water Services and the community to enhance the 
new North Phoenix Reservoir. This project is in the planning phase. 
Project Number 
AR84800001 
Project Title  
Harmon Park: River of Shade 
Location 
1425 S. 5th Ave. 
Type of Project 
Refurbishments and Retrofits 
Funding Source 
Water Capital Funds 
Budget 
$150,000 
Council District 
8 
A contractor will be hired to repair elements of River of Shade by artist Stacy Levy.  The project 
was completed in 2010 and will be restored to the original design, in collaboration with the 
artist.  Some repairs were made in fiscal year 2024-2025.  This project is in the planning phase. 
Project Number 
AR84800002 
Project Title  
Sunnyslope Canal Demonstration Project 
Location 
Arizona Canal between Dunlap Ave. and Northern Blvd. 
Type of Project 
Refurbishments and Retrofits 
Funding Source 
Water Capital Funds 
Budget 
$100,000 
Council District 
3, 6 
A contractor will be hired to repair elements of the Sunnyslope Canal Demonstration project by 
artists Jackie Ferrara and Doug Hollis.  The project was completed in 2000 and will be restored 
to the original design, in collaboration with the artists.  This project is in the planning phase. 
Project Number 
AR84850019 
Project Title  
Arizona Falls: Waterworks 
Location 
Arizona Canal at 58th St. 
Type of Project 
Refurbishments and Retrofits 
Funding Source 
Water Capital Funds 
Budget 
$100,000 
Council District 
6 
Major safety features, such as security lighting, drainage, fencing, and landscape improvements 
will be upgraded as part of improvements to the site. The project is in the planning phase.

Project Number 
AR84850033 
Project Title  
Water Services West Yard 
Location 
North 47th Ave. and West Camelback Rd. 
Type of Project 
Design Team and Permanent Commission 
Funding Sources 
Wastewater Capital Funds 
Budget 
$38,650 
Council District 
5 
An artist will be contracted to work with Water Services and its project team to add 
enhancements to publicly accessible areas of the planned West Yard Facility and Customer 
Service Center. This project is currently on hold. 
Project Number 
AR84850035 
Project Title  
Community Well Site Enhancements 
Location 
Various 
Type of Project 
Permanent Commissions 
Funding Sources 
Water Capital Funds 
Budget 
$250,000 
Council District 
Citywide 
Artists will be commissioned to work with the Water Services Department to enhance or 
upgrade the design of new and existing Water facilities. These projects are currently on hold 
until suitable sites can be identified.  To view previously completed well sites, visit 
www.pheonix.gov/arts.  
Project Number 
AR84850036 
Project Title  
Cortez Park and Well Site 
Location 
35th Ave. and Arizona Canal 
Type of Project 
Design Team and Permanent Commission 
Funding Sources 
Water Capital Funds 
Budget 
$200,000 
Council District 
1 
John Randall Nelson was contracted in a previous fiscal year to work with Water Services, Parks 
and Recreation, and Neighborhood Services to design enhancements to improve the safety and 
security of this Aquifer Storage and Recovery well site and surrounding public spaces along the 
Arizona Canal and Cortez Park. This project is in the fabrication phase and is expected to be 
complete in 2025. 
Project Number 
AR84850038 
Project Title  
Maryvale Grand Canal Crossing 
Location 
Grand Canal and 51st Ave. 
Type of Project 
Permanent Commission 
Funding Sources 
Water Capital Funds 
Budget 
$200,000 
Council District 
5

Reinaldo Correra was contracted in a previous fiscal year to work with Street Transportation, SRP, 
and the community to enhance the design of the Grand Canal trail and crossing near 51st Ave. 
in Maryvale. This project is in the design phase and is expected to be complete in 2026. 
Project Number 
AR84850040 
Project Title  
El Reposo Park 
Location 
502 East Alta Vista Rd.  
Type of Project 
Refurbishments and Retrofits 
Funding Sources 
Water and Wastewater Capital Funds 
Budget 
$344,483 
Council District 
7 
Due to new construction, a previously completed artwork titled Bloomcanopy by Matter 
Architecture Practice will be relocated and integrated into the landscape at El Reposo Park. The 
project is in the design phase and is expected to be complete in 2026.  
Project Number 
AR84850041 
Project Title  
Sueño Park  
Location 
4401 West Encanto Blvd. 
Type of Project 
Permanent Commission 
Funding Sources 
Water Capital Funds 
Budget 
$166,700 
Council District 
4 
An artist will be commissioned to work with Parks and the community to enhance the 
experience of Sueño Park. This project is in the planning phase and will utilize artists from the 
Pre-Qualified Roster for City Parks. 
Project Number 
AR84850042 
Project Title  
Paradise Valley Park  
Location 
17642 North 40th St. 
Type of Project 
Permanent Commission 
Funding Sources 
Water Capital Funds 
Budget 
$371,785 
Council District 
2 
Artist Donald Lipski was contracted in a previous fiscal year to work with Parks and the 
community to enhance the experience of Paradise Valley Park. This project is in the design 
phase and is expected to be complete in 2026. 
Project Number 
AR84850044 
Project Title  
Western Canalscape (Phase 1 and 2) 
Location 
Western Canal, 4th Avenue to 24th Street  
Type of Project 
Purchase of Existing Artwork, Permanent Commission 
Funding Sources 
Water Capital Funds 
Budget 
$592,339 
Council District 
7, 8

Existing three-dimensional artwork was purchased from artists Ken McCall and Hector Ortega 
for placement along the Western Canal at 20th Street. Phase 1 of this project is in the 
construction phase; Phase 2 is in the planning phase where new opportunities for public art will 
be identified. 
Project Number 
AR84850045 
Project Title  
Collaborative Neighborhood Projects 
Location 
Various 
Type of Project 
Temporary and Permanent Commissions, Purchase of Existing Artwork 
Funding Sources 
Water and Wastewater Capital Funds 
Budget 
$675,496 
Council District 
Citywide 
Artists will be selected to work directly with neighborhood and business associations to 
enhance parks, business corridors, and other community amenities.  Two projects are currently 
underway with the Hatcher Urban Business and the Bell Road Business Alliance.  These projects 
are in construction and design phases, respectively. 
Project Number 
AR84850046  
Project Title  
Identification Plaques and Interpretive Signage 
Location 
Various 
Type of Project 
Refurbishments and Retrofits 
Funding Sources 
Water Capital Funds 
Budget 
$225,000 
Council District 
Citywide 
Contractors will be selected to work with Arts and Culture to update, replace, and produce 
identification plaques and interpretive signage for the public art collection.  This project is in the 
planning phase and will be on-going. 
Project Number 
AR84850048 (NEW) 
Project Title  
Major Refurbishment and Restoration Planning 
Location 
Various 
Type of Project 
Refurbishments and Retrofits 
Funding Sources 
Water and Wastewater Capital Funds 
Budget 
$150,000 
Council District 
Citywide 
Specialty contractors will be selected to work with Arts and Culture to plan, budget, and 
schedule major refurbishments and restorations of existing public art projects.  This project is in 
the planning phase and will be on-going.

Project Number 
AR84900010 
Project Title  
Tres Rios Wetlands 
Location 
91st Ave. and Baseline Rd. 
Type of Project 
Design Team and Permanent Commission 
Funding Source 
Wastewater Capital Funds 
Budget 
$1,745,000 
Council District 
7 
Adam Kuby was contracted in a previous fiscal year to work with a design team, various City 
departments, consultants, and the community to create significant recreation and 
environmental education experiences as part of this multi-year effort to improve the seven-
mile, 1,500-acre wetland at the confluence of the Salt and Gila Rivers in southwestern Phoenix. 
Kuby and the team have designed raptor towers, viewing areas, paths, and demonstration 
gardens in the wetlands. This project is currently on hold pending federal funds. 
Project Number 
AR84900011 
Project Title  
Lift Stations and Neighborhood Facilities 
Location 
Citywide 
Type of Project 
Permanent Commissions 
Funding Source 
Wastewater Capital Funds 
Budget 
$47,500 
Council District 
Citywide 
Artists will be contracted to work with City consultants to enhance or upgrade the design of 
new or existing lift stations and other neighborhood facilities essential to the City's wastewater 
collection system. In addition to wall enhancements, the projects may include upgraded 
landscaping, security fencing, and other features. This project is currently on hold. 
Project Number 
AR84900015 
Project Title  
Rio Reimagined  
Location 
7th St. to 7th Ave. 
Type of Project 
Design Team, Temporary and Permanent Commissions 
Funding Source 
Wastewater Capital Funds 
Budget 
$662,515 
Council District 
7, 8 
The Rio Reimagined Project is a vision to revitalize the Rio Salado (Salt River), Aqua Fria, and 
Gila Rivers, and the region by transforming over 45 miles of the river stretching from the Salt 
River Pima Maricopa Indian Community at the eastern most boundary to the City of Buckeye to 
the west and encompassing more than 78,000 acres.  Artists will be selected at several phases 
of the project to engage the community and design permanent and temporary artwork to 
enhance the visitor experience.  This project is in the planning phase.

Completing the following projects requires significant funding resources over the next five fiscal 
years. Funding for the planning and implementation of these projects is included in the FY 
2025-2030 Public Art Plan. Funding of all projects is subject to City Council approval through 
future plans. 
General Obligation Bond Program 
On November 7, 2023 Phoenix voters passed the City Council approved $500 million General 
Obligation (GO) Bond Program. GO Bond programs help to fund critical infrastructure and 
rehabilitation needs of City facilities such as parks, libraries, fire and police stations, affordable 
housing, streets, and storm drains.  Approved projects are prioritized and allocated over the 
five-year period of fiscal year 2024-2025 to fiscal year 2028-2029 and included in the 
Preliminary Capital Improvement Program (CIP) scheduled approved by City Council on March 
19, 2024.  Each of the four proposition includes a percent-for-art calculation which must be 
spent on projects in each proposition.  A breakdown of proposed public art projects is in the 
next section. 
Artist Initiatives 
On-going temporary installations provide crucial professional development opportunities for 
emerging artists and those new to public art.  Temporary installations can also activate 
underutilized spaces and provide neighborhoods with new ways to engage with artists.  This 
program is guided by the Office of Arts and Culture’s Temporary Art Guidelines. 
Collaborative Neighborhood Projects 
Artists will be selected to work directly with neighborhood and business associations, such as 
theHUB (Hatcher Urban Businesses) and the Bell Road Business Alliance, to enhance parks, 
business corridors, and other community amenities.  These enhancements foster community 
collaboration and external partnerships that expand the reach of the public art program. 
Community Water Facilities Improvements 
Over the years, multiple artists have been contracted to work with the community and the 
Water Services Department to improve the security and appearance of community water 
facilities citywide, including well sites and lift stations.  
Phoenix Sky Harbor International Airport 
Phoenix Sky Harbor International Airport’s new terminal modernizations represent the City's 
most significant opportunity to reach the widest public with integrated public art and design. 
PSHIA handles more than 40 million passengers annually. ACD staff continue to work with 
Aviation staff and its design teams to carry out a comprehensive plan to integrate significant art 
and design to enhance travelers’ experience. Projects will be implemented in step with the 
airport modernization phases. 
FY 2025-2030 Multi-Year Initiatives

Public Works Recycling and Sustainability Initiative 
ACD has worked with the Public Works Department since 1990 to involve artists in the design of 
innovative recycling centers, and in building awareness of the need for recycling and 
sustainable resource management. Artists will be contracted to create artworks that expand 
awareness about recycling and sustainable resource management by introducing new ways to 
reuse materials and bolster City efforts to increase recycling citywide.  
Rio Reimagined 
Rio Reimagined is the Valley’s most impactful green infrastructure project in a century.  Rio 
Salado, or the Salt River, is a historically significant and underutilized natural resource 
reimagined as a unifying public space.  A creative and collective effort is underway to  
integrate priorities of public open space, environmental quality, housing, transportation, 
economic and workforce development, community sustainability, and resilience.  ACD staff 
work with the Planning Department to identify and integrate permanent and temporary public 
art opportunities.  
Shade, Cooling, and Heat Mitigation  
Artists will be contracted to work with the community and various City departments to enhance 
the pedestrian experience by increasing shade options and improving shaded connectivity. The 
enhancements will be coordinated with City efforts to reduce the impact of urban heat and 
improve mobility citywide through initiatives like Cool Corridors.  The initiative also includes 
supporting funds for the Bloomberg Philanthropies Public Art Challenge grant. 
Tres Rios Wetlands 
Adam Kuby has been selected to work with City departments, consultants and the community 
to create significant environmental recreation and education opportunities at Tres Rios 
Wetlands. This project is part of this multi-year effort to improve the seven-mile, 1,500-acre 
wetland at the confluence of the Salt and Gila Rivers in southwestern Phoenix.

FY 2025-2030 Public Art Plan Summary and Map 
 
Public Art Plan Summary 
*General Obligation (GO) Bond Program – tentative public art projects
Number of New Projects 
3 
$350,000 
General Obligation Bond Program* 
4 
$3,761,464 
Number of Continuing Projects 
38 
$20,295,190 
Total Funded Projects 
45 
$24,406,654 
Proposition 1 
Fire Station 7
Fire Station 13
Fire Station 15
Fire Station 51
4
$1,632,629 
Proposition 2 
Estrella Civic Space + Branch Library
Desert View Civic Space + Branch Library
2
$903,853 
Proposition 3 
Latino Cultural Center 
1 
$624,603 
Proposition 4 
Choice Neighborhoods Housing 
Development 
McDowell Senior Center 
2 
$600,649 
Total Funded GO Bond Projects 
9 
$3,761,464