REPORT OF PLANNING HEARING OFFICER ACTION  
Byron Easton, Planner III, Hearing Officer  
Teresa Garcia, Planner I, Assisting  
 
February 21, 2024 
 
ITEM NO: 4 
 
 
DISTRICT NO. 6 
SUBJECT: 
 
 
 
Application #: 
PHO-2-24--Z-127-96-6 
Location: 
Southeast corner of 48th Street and Thistle Landing Drive 
Zoning:  
CP/GCP 
Acreage:  
40.36 
Request: 
1) Request to modify Stipulation 1 regarding general 
conformance with the site plan dated October 15, 1997. 
2) Request to delete Stipulation 2 regarding a 
Comprehensive Sign Plan. 
3) Technical Correction to Stipulation 3. 
4) Request to modify Stipulation 7 regarding building height. 
5) Request to delete Stipulation 8 regarding a landscaped 
entryway. 
6) Request to delete Stipulation 9 regarding landscaped 
pedestrian walkways. 
Applicant: 
Thistle Income Partners LLC 
Owner: 
 
Thistle Income Partners LLC 
Representative: Thistle Income Partners LLC 
 
ACTIONS: 
 
Planning Hearing Officer Recommendation: The Planning Hearing Officer 
recommended denial as filed, approval with modifications and additional 
stipulations. 
 
Village Planning Committee (VPC) Recommendation: The Ahwatukee Foothills 
Village Planning Committee heard this request on January 22, 2024 and 
recommended approval with additional stipulations by a vote of 8-0. 
 
DISCUSSION: 
 
Nick Wood, representative of Snell & Wilmer LLC, gave an overview of the site 
and modification requests. He stated the one of the primary concerns voiced by 
surrounding neighbors was building setbacks. He stated that even though the 
applicant is allowed up to 80-feet in height by the Zoning District, the buildings 
will be 56 feet tall with a minimum 126-foot setback. He stated the size of the

Planning Hearing Officer Summary of February 21, 2024 
Application PHO-2-24--Z-127-96-6 
Page 2 
 
 
streets provides a greater distance from surrounding homes. He stated the 
substation will be 770 feet away from the nearest single-family home. He stated 
the park will be publicly accessible from 6:00AM-10:00PM and have substantial 
security 24/7. He stated in the event the project is phased; the park will be built 
when the final certificate of occupancy is issued. 
 
Nikki Micale, 14817 South 46th Place, stated the applicant’s public outreach map 
showed minimal dots for the southwest corner of 48th Street and Thistle Landing 
Drive. She stated that the before mentioned area is where her two properties are 
located and that she has video footage showing no one approached her homes 
for public outreach. She clarified that her neighbors attended the meeting 
because it was a work night. She stated that if the developer was interested in 
building a park, it would be located closer to 48th Street. She stated she is 
concerned with the heat, noise and traffic generated for the proposed site. 
 
Byron Easton, Planning Hearing Officer, asked Mr. Wood if he can provide data 
regarding daily trips generated for the proposed site. 
 
Mr. Wood stated the existing site would produce 226 daily a.m. arrival trips and 
59 daily a.m. departure trips during peak morning times at full capacity; the 
proposed project would produce 65 daily a.m. arrival trips and 51 departing. He 
stated the existing site would produce 56 arrivals and 160 departing during peak 
evening times; the proposed project would produce 28 arrivals and 65 departing. 
 
Mr. Easton asked how the park will be fenced. 
 
Mr. Wood stated the conceptual plan may not indicate the actual shape of the 
park. He stated when the geometry is determined, the fence and gates will be 
designed to go around the perimeter of the park. 
 
Mr. Easton recommended denial as filed, approval with modifications and 
additional stipulations. 
 
FINDINGS: 
 
1) The request to modify Stipulation 1 regarding general conformance with 
the site plan dated October 15, 1997 is recommended to approved with a 
modification to replace the general conformance stipulation with targeted, 
specific stipulations that ensure the site plan adheres to goals that were 
agreed upon by the developer and surrounding neighborhoods.  The first 
stipulation ensures that the developer will maintain a minimum 126’ 
perimeter building setback as depicted on the proposed site plan. The 
second stipulation ensures that the substation will be located away from 
the single-family residential neighborhoods adjacent to the site as shown 
on the proposed site plan.  The third stipulation ensures that the park will

Planning Hearing Officer Summary of February 21, 2024 
Application PHO-2-24--Z-127-96-6 
Page 3 
 
 
be constructed to the size and location as shown on the proposed site 
plan and will operate at the hours listed by the fourth stipulation. 
 
The original stipulated site plan consisted of four (4), L-shaped buildings 
that were designed for a call center use, higher employee 
numbers/parking and more traffic.  The proposed use will produce lower 
impacts to the community, will provide more dense landscaping and will 
provide 24 hour security to the area. 
 
2) The request to delete Stipulation 2 regarding a Comprehensive Sign Plan 
is approved.  There is no need for a CSP with one, unified user. 
 
3) The request for a technical correction to Stipulation is approved. 
 
4) The request to modify Stipulation 7 regarding building height is 
recommended for approval to match the proposed design of the data 
center, which require additional interior height for operational uses. As 
such, in order to accommodate this Project, this application requests to 
modify this stipulation so that the maximum permitted building height is in 
conformance with the Zoning Ordinance’s baseline standards for the 
CP/GCP zoning district (which is the Property’s underlying zoning).  
 
5) The request to delete Stipulation 8 regarding a landscaped entryway 
feature is recommended for approval.  Since the Project is no longer a 
commercial center, an entryway feature is no longer required. 
 
6) The request to delete Stipulation 9 regarding landscaped walkways is 
recommended denial as filed.  Workers on site will still need walkways to 
connect to the other buildings and adjacent right of ways for public transit 
access. 
 
7) The new stipulation is added to provide clarity for City Staff regarding the 
timing of the of the construction of the publicly accessible open space 
(park) and how that it now tied to the certificate of occupancy for the final 
building on the site. This stipulation allows for the buildings that are build 
in earlier phases be completed an occupied while allowing the installation 
and completion of the park to be timed by the contractor to avoid conflicts 
with construction equipment.  It is noted by the Planning Hearing Officer 
and agreed upon by the applicant that the Phasing Plan referenced by the 
stipulation be submitted to the Development Division for Director approval 
at the time of preliminary site plan review. 
 
8) The applicant did not submit a Proposition 207 waiver of claims prior to 
the Planning Hearing Officer hearing. Submittal of this form is an 
application requirement.  An additional stipulation is recommended to

Planning Hearing Officer Summary of February 21, 2024 
Application PHO-2-24--Z-127-96-6 
Page 4 
 
 
require the applicant to record this form and deliver it to the City to be 
included in the rezoning application file for record. 
 
STIPULATIONS: 
 
1. 
That development be in general conformance with the site plan dated 
October 15, 1997 as may be modified by the following stipulations, and 
the Development Services Department.  
 
THE DEVELOPER SHALL PROVIDE MINIMUM 126’ BUILDING 
SETBACKS FROM ALL PERIMETER PROPERTY LINES, AS 
DEPICTED ON THE SITE PLAN DATE STAMPED DECEMBER 11, 
2023, AND AS APPROVED BY THE PLANNING AND DEVELOPMENT 
DEPARTMENT. 
 
 
2. 
THE PROPOSED SUBSTATION SHALL BE LOCATED IN THE 
SOUTHEAST QUARTER OF SITE, AS DEPICTED ON THE SITE PLAN 
DATE STAMPED DECEMBER 11, 2023, AND AS APPROVED OR 
MODIFIED BY THE PLANNING AND DEVELOPMENT DEPARTMENT. 
 
 
3. 
THE DEVELOPER SHALL PROVIDE AN APPROXIMATELY 2 ACRE 
PUBLICLY ACCESSIBLE OPEN SPACE AREA IN THE NORTHEAST 
QUARTER OF THE SITE, AS DEPICTED ON THE SITE PLAN DATE 
STAMPED DECEMBER 11, 2023, AND AS APPROVED OR MODIFIED 
BY THE PLANNING AND DEVELOPMENT DEPARTMENT. 
 
 
4. 
THE PUBLICLY ACCESSIBLE OPEN SPACE SHALL BE OPEN TO THE 
PUBLIC FROM 6AM-10PM. 
 
 
2. 
That the property be subject to a Comprehensive Sign Plan per Section 
705.JJJ of the Zoning Ordinance. The sign plan shall convey a sese of 
continuity between the buildings and the property as a whole.  
 
 
5. 
3. 
That all buildings within the project shall be harmonious with each other 
and each building elevation shall be consistent and continuous in design 
and materials around the building, as approved by the PLANNING AND 
Development Services Department. 
 
 
6. 
4. 
That the following right-of-way dedications be provided: 
 
 
 
a. 
A 55-foot half street and landscape/sidewalk for 48th Street. 
 
 
 
b. 
A 33-foot half street and a 10-foot landscape/sidewalk easement for

Planning Hearing Officer Summary of February 21, 2024 
Application PHO-2-24--Z-127-96-6 
Page 5 
 
 
Thistle Landing Drive; and 
 
 
 
c. 
A 35-foot half street and a 10-foot landscape/sidewalk easement for 
50th Street; 
 
 
 
d. 
An 18-foot by 18-foot triangle at 48th Street and Thistle Landing Drive.
 
 
7. 
5. 
Additional right-of-way dedications may be required upon review of the 
final approved Traffic Impact Study by the Street Transportation 
Department. 
 
 
8. 
6. 
The Developer shall construct all streets within and adjacent to the 
development with paving, curb, gutter, sidewalk, streetlights, median 
islands, landscaping and other incidentals as per plans approved by the 
City. 
 
 
9. 
7. 
That no buildings shall exceed 56-FEET one story in height. 
 
 
8. 
That a landscape entryway feature be provided at the northwest corner of 
the site approved by the Development Services Department. 
 
 
10.
9. 
That landscaped pedestrian walkways be proved throughout the site 
connecting buildings and adjacent rights-of-way as approved by the 
Development Services Department.  
 
 
11. 
IN THE EVENT THE PROJECT IS PHASED, THE PUBLICLY 
ACCESSIBLE OPEN SPACE WILL NOT BE REQUIRED TO BE 
COMPLETED UNTIL PRIOR TO THE ISSUANCE OF THE FINAL 
CERTIFICATE OF OCCUPANCY FOR THE LAST BUILDING OF THE 
PROJECT, AS PER A PHASING PLAN FOR THE OVERALL PROJECT, 
AS APPROVED BY THE PLANNING AND DEVELOPMENT 
DEPARTMENT. 
 
 
12. 
PRIOR TO PRELIMINARY SITE PLAN APPROVAL, THE LANDOWNER 
SHALL EXECUTE A PROPOSITION 207 WAIVER OF CLAIMS IN A 
FORM APPROVED BY THE CITY ATTORNEY'S OFFICE.  THE WAIVER 
SHALL BE RECORDED WITH THE MARICOPA COUNTY RECORDER'S 
OFFICE AND DELIVERED TO THE CITY TO BE INCLUDED IN THE 
REZONING APPLICATION FILE FOR RECORD. 
 
 
 
Upon request, this publication will be made available within a reasonable length 
of time through appropriate auxiliary aids or services to accommodate an

Planning Hearing Officer Summary of February 21, 2024 
Application PHO-2-24--Z-127-96-6 
Page 6 
 
 
individual with a disability. This publication may be made available through the 
following auxiliary aids or services: large print, Braille, audiotape or computer 
diskette. To request a reasonable accommodation, please contact Teleia Galaviz 
at teleia.galaviz@phoenix.gov or (602) 291-2559 or TTY: 7-1-1.