T2050 FY 2021-22 Annual Progress Report

City of Phoenix — Transportation, Infrastructure, and Planning Subcommittee (2022-11-16)

View PDF Meeting page

Extracted text (via pymupdf) 77467 characters
MOVING PHOENIX 
FORWARD
ANNUAL
PROGRESS 
REPORT
FISCAL YEAR 2022
JULY 1, 2021 THROUGH JUNE 30, 2022
Attachment A

2
A MESSAGE FROM LEADERSHIP
Mayor Kate Gallego
Councilmember Debra Stark  
Chair, Transportation, Infrastructure 
and Planning Subcommittee
Commissioner Jennifer Mellor 
Chair, Citizens Transportation 
Commission
“Transportation 2050 is an unprecedented 
investment in our community, our 
economy, and our future,” said Mayor 
Kate Gallego. “Our voters made one of 
the largest investments in transit and 
transportation infrastructure of its kind in 
the country, and now we are seeing those 
investments starting to pay off. More 
Phoenix residents are finding that mass 
transit is the way to go, especially as gas 
prices remain higher. T2050 is expanding 
our transportation service, helping us 
prepare for the future, and positioning 
Phoenix for decades of economic growth.”
“When voters approved T2050, they 
approved expanded investment in 
Phoenix’s infrastructure for the next 
35 years,” said Councilmember Stark. 
“Street improvements, expanded 
bus service, improved Dial-a-Ride 
and light rail expansion are all 
priorities in the plan that residents 
overwhelmingly supported. As we 
continue to improve transportation in 
Phoenix, our residents, and everyone 
who visits our city, will benefit from 
the vision our voters had when they 
approved this plan.”
“The T2050 plan continues to improve 
transportation in Phoenix with an 
expanding transit system and new 
paving projects on our city’s busiest 
arterial streets. The future is bright 
for transportation in Phoenix with 
new light rail projects underway, 
new asphalt smoothing the ride on 
even busier city streets, and our bus 
system providing multiple alternatives 
for residents looking for greener, 
more affordable ways to get to and 
from home, work, entertainment, and 
the community.”
OVERVIEW
BUS/DAR
HCT
STREETS
APPENDIX

3
1.0	 Program Overview
2.0	 Bus and Dial-a-Ride
3.0	 High Capacity Transit
4.0	 Street Maintenance and Improvements
5.0	 Appendix
Annual Progress Report — Fiscal Year 2021  
Interactive features may be found throughout the document in orange.
TABLE OF CONTENTS
►
►
►
►
►
OVERVIEW
BUS/DAR
HCT
STREETS
APPENDIX

1.0
Program Overview
4
BUS/DAR
HCT
STREETS
APPENDIX
OVERVIEW

5
PROGRAM OVERVIEW
Transportation 2050 (T2050) is 
Phoenix’s 35-year plan dedicated 
to improving multiple modes 
of transportation in Phoenix, 
including bus, light rail,  
Dial-a-Ride (DAR), streets, bikes lanes,  
and active transportation. Phoenix voters 
made T2050 possible when they approved  
Proposition 104 on August 25, 2015. The 
measure, which replaced the previous 0.4% 
sales tax with a 0.7% sales tax, became 
effective Jan. 1, 2016, and allocates 70 cents 
of each $100 spent to the city’s transportation 
needs. Approximately 86% of funds support 
public transit and 14% supplement street 
maintenance and improvement funds.
T2050 revenues supplement other sources 
of transportation funding, allowing the city to 
accomplish more. This report summarizes 
T2050 accomplishments for July 1, 2021, to 
June 30, 2022 (FY 2022). In addition, the report 
identifies cumulative 
progress, since the start 
of the program, and 
provides an overview of 
improvements planned for 
the next five years.
T2050 is dedicated to improving multiple modes 
of transportation in Phoenix, including bus, light 
rail, Dial-a-Ride (DAR), streets, bikes lanes, and 
active transportation.
$100
100
70¢
(0.7%)
BUS/DAR
HCT
STREETS
APPENDIX
OVERVIEW

T2050 
FUNDS
FEDERAL 
FUNDS
REGIONAL 
FUNDS
FINANCING
$
$
OTHER 
TRANSIT 
REVENUES
TRANSIT 
FARE 
REVENUES
Figure 1.1 Sources of Funds
Total estimated 
revenues for 
35-year program
$31.5B
  
$16.8B
T2050
Sales
Tax
$2.9B
State/
Regional
$3.9B
Federal
$5.1B
Transit
Fares
$1.7B
 Financing
 (bonds/
 loans)
$1.1B
 Other
6
Lifecycle Revenues
Over the course of 35 years, Phoenix expects 
sales tax revenue to generate more than half 
of the estimated $31.5 billion in overall T2050 
funding. The remaining funds will be provided by 
federal, state, regional and local funding sources. 
 shows funding sources as established 
at the start of the program. 
In addition to these funds, Public Transit and 
Street Transportation Department staff will 
pursue any opportunities to reduce costs through 
innovation and efficient project delivery methods. 
More information on program assumptions can 
be found in the appendix, with projected and 
actual sales tax revenue shown in Table A.1. 
For additional information on regional and federal 
funding, visit phoenix.gov/T2050/Funding.
T2050 FUNDING
T2050 PROGRAM AREAS
Figure 1.1
NEW AND  
EXPANDED BUS 
AND  
DIAL-A-RIDE
TRANSIT 
INFRASTRUCTURE
MOBILITY  
AND 
ACCESSIBILITY
TECHNOLOGY 
ENHANCEMENTS
PAVEMENT 
MAINTENANCE 
NEW AND 
EXPANDED 
MAJOR STREETS
HIGH CAPACITY 
TRANSIT
BUS/DAR
HCT
STREETS
APPENDIX
OVERVIEW

$2.3B
Debt 
service and 
reserve
$2.3B
Streets, 
pavement, 
mobility and 
technology
$268M
Transit
infrastructure
$6.7B
New light
rail transit
$670M
Bus rapid 
transit
$1.9B
New bus 
service in
unserved 
areas
$878M
Bus 
frequency
for a peak 
period and 
weekend
service
$1.8B
Expanded 
bus and 
Dial-a-Ride 
hours
$14.7B
Existing bus,
Dial-a-Ride
and light rail
transit
 
Total estimated 
costs
$31.5B
7
Lifecycle Expenditures
At times, revenue projections for T2050 will 
exceed projected expenditures for a given 
year. This helps to ensure that the plan has 
available funds in future years for large 
capital projects such as light rail construction, 
park-and-ride facilities, and to ensure a fund 
balance is maintained whenever possible 
during the life of the plan. 
 shows 
planned uses of funds as established at the 
launch of the program.
Figure 1.2 Planned Uses of Funds
As COVID-19 cases are declining ridership is 
slowly returning to pre-pandemic levels.
Impact of COVID-19
The COVID-19 virus resulted in a global 
pandemic beginning in 2020 and significantly 
shifted consumer demands. Ridership numbers 
steeply declined because social distancing 
requirements changed travel patterns and 
work practices in various industries continue 
to evolve. Ridership has been progressively 
increasing since the initial decline. However, it 
still remains below pre-pandemic levels. This 
report notes the effects of changes due to the 
pandemic within each program area.
FY 2022 Financial Summary 
and Projection 
The total operating and capital budgets for 
FY 2022 are $865,738,551. Table A.2 in the 
appendix details budgeted and actual revenues 
and expenditures. 
 provides projected 
and actual sales tax revenue, as well as short-
term projected revenue figures. Table A.3 in the 
appendix outlines the FY 2022–2027 five-year 
financial plan. 
Figure 1.3 T2050 Sales Tax Revenue Summary
Figure 1.2
Figure 1.3
BUS/DAR
HCT
STREETS
APPENDIX
OVERVIEW

8
Public Outreach
To understand residents’ transportation 
needs, staff regularly engages with the 
public at open houses and public meetings. 
They also attend community events, 
providing information and gathering input 
on a variety of topics, including increasing 
transit access; planning bus routes 
and extensions, future light rail station 
locations, potential bus rapid transit routes; 
building and improving roads; and creating 
and improving bike lanes.
Due to the pandemic, staff members 
utilized a mixture of in-person and virtual 
meeting platforms to conduct outreach 
and receive community input throughout 
the year. Staff members hosted virtual 
public meetings, accessible by phone 
or computer. Virtual meetings included 
presentations, a variety of speakers, and 
public question-and-answer segments. As 
COVID rates continue to decline across 
the Greater Phoenix area, in-person 
public meetings will once again be a 
consideration. 
Formal Oversight
The Citizens Transportation Commission (CTC) 
was established in 2015 by the mayor and 
Phoenix City Council to provide oversight of 
the T2050 program. The Phoenix City Council 
appoints a total of 15 commission members 
to address street and transit needs, provide 
oversight on the expenditure of funds, and 
make recommendations on plan elements. 
Transportation, Infrastructure and Planning 
Subcommittee Members: (top row, left–right):  
Councilmember Debra Stark, Chair; Vice 
Mayor Laura Pastor; (second row, left–right): 
Councilmember Betty Guardado; Councilmember 
Ann O’Brien.
CTC members represent various facets of 
the community. As of June 30, 2022, CTC 
members include: 
	
●Chair Jennifer Mellor
	
● Vice Chair Rick Naimark
	
●Jess Bristow
	
●Carolyn Chatman
	
●Michael Infanzon
	
●Gail Knight
	
●Gabriel Loyola
	
●David Martin
	
●Christina Panaitescu
	
●David Moody
	
●Brookelynn Nisenbaum
	
●Phil Pangrazio
	
●Joan Berry
	
●Shannon McBride
	
●(Vacant Position)
The Phoenix City Council’s Transportation, 
Infrastructure and Planning subcommittee 
provides policy guidance on issues related 
to infrastructure, transportation, transit, 
streets, aviation/airport, water, technology, 
smart cities, innovation, and sustainability. 
The Phoenix City Council provides 
additional oversight, and its meetings also 
provide opportunities for the public to offer 
input on the program. 
35-Year Goals Established at the Onset of T2050 
The voter-approved 35-year sales tax became effective on January 1, 2016. The following dashboard provides an overview of 
T2050 progress. City leaders established these goals based on the Proposition 104 ballot language, with the expectation that goals 
may evolve as the program progresses. Use the interactive links included throughout this report to access additional information.
T2050 
Goals 
Dashboard 
on next 
page
BUS/DAR
HCT
STREETS
APPENDIX
OVERVIEW

35 
YEARS
15 MIN
 
RAPID
 
BRT
NEW
50th
 
Approaching expected target
Below expected target
 At or above expected target
9
This dashboard represents progress from Jan. 1, 2016, through June 30, 2022. 
T2050 GOALS ESTABLISHED AT PROGRAM ONSET
CONTINUE local bus, RAPID commuter bus, neighborhood circulator and Dial-a-Ride service FOR 35 YEARS
PROVIDE 15-MINUTE FREQUENCY on half of all bus routes
EXTEND & ADD new RAPID service
PURCHASE NEW buses and Dial-a-Ride vehicles
EXTEND bus and Dial-a-Ride service hours TO MATCH LIGHT RAIL HOURS
EXTEND & ADD BUS SERVICE to unserved major streets
ADD NEW circulator service
BUILD NEW park-and-ride lots
BUILD additional bus bays
CONTINUE 17 MILES of light rail service
PROVIDE 75 MILES of new bus rapid transit service
ADD 42 MILES of new light rail in Phoenix
BUILD NEW light rail station at 50th Street (completed April 25, 2019, and operational since then)
680 MILES of new overlays on arterial/major streets
	2,000 new streetlights
	$240 MILLION for new roads and upgraded bridges
1,080 MILES of new bike lanes
	135 MILES of new sidewalks
ENHANCE technology
All goals expected to be at or above the progress target at 6.5 years.
EXPECTED PROGRESS  
AT 6.5 YEARS
STREETS
HIGH CAPACITY  
TRANSIT
BUS AND DIAL-A-RIDE
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
►
STREETS
HIGH CAPACITY  
TRANSIT
BUS AND DIAL-A-RIDE
BUS/DAR
HCT
STREETS
APPENDIX
OVERVIEW

10
2.0
Bus and Dial-a-Ride
OVERVIEW
HCT
STREETS
APPENDIX
BUS/DAR

RAPID
DAR
DAR
11
BUS AND DIAL-A-RIDE
CUMULATIVE PROGRESS Jan. 1, 2016–June 30, 2022
EXTENDED SERVICE HOURS
for bus and Dial-a-Ride to MATCH LIGHT RAIL HOURS (FY 2017)
INCREASED FREQUENCY*
off-peak to 15 MIN on five routes:
41
Indian School 
Road
(FY 2019)
19
19th
Avenue
(FY 2018)
3
Van Buren
Street
(FY 2018)
50
Camelback
Road
(FY 2018)
29
Thomas  
Road
(FY 2018)
Weekday service levels  
on five holidays reinstated  
(previously on a Sunday schedule)
RAPID service  
frequency increases
Weekdays and weekends 
to 30 MIN or better
EXTENDED BUS ROUTES
Route 51	 	 MARY Neighborhood Circulator Extended on 59th Avenue to service neighborhoods 
	
	 near Sunridge Park. (FY 2022)
Route 51	 51st Avenue Lower Buckeye Road to Baseline Road (FY 2017)
Route 60	 16th Street Bethany Home Road & 16th Street to Camelback Road & 24th Street (FY 2018)
Route 19	 23rd Avenue Happy Valley Road to Pinnacle Peak Road (FY 2018)
Route 39	 Shea Boulevard Dreamy Draw Park-and-Ride to 40th Street (FY 2017)
Route 122	 Cactus Road ASU West Campus to 19th Avenue/Dunlap Avenue Light Rail (FY 2017)
ORDERED 
443
Local Buses;
44
Rapid Buses;
147
Dial-a-Ride Vehicles;
9
Circulator Buses
INSTALLED 
7
Bus Bays;
52
Bus Stops
445
Bus Shelter Shade Structures.
ADDED BUS ROUTES 
Route32	 32nd Street Camelback Road to Baseline Road & 
Priest Drive (FY 2017)
Route140	 Ray Road 48th Street to Gilbert Road (FY 2018)
R* On May 4, 2020, service was temporarily reduced due to the COVID-19 pandemic and its impact on transit demand.
51
60
19
39
122
32
140
MARY
 FY16 - FY21
 FY16 - FY21
 FY16 - FY21
 FY16 - FY21
FY22
FY22
FY22
& FY22
443
443
44
44
403
403
44
44
122
122
6
147
147
9
OVERVIEW
HCT
STREETS
APPENDIX
BUS/DAR
►
►
►
►

>> <<
DAR
12
BUS AND DIAL-A-RIDE
CUMULATIVE PROGRESS Jan. 1, 2016–June 30, 2022
OTHER IMPROVEMENTS COMPLETED
$431
MILLION RECEIVED
in Federal Transit Administration (FTA) formula grants for 
Phoenix transit (6.5-year total)
$22
MILLION RECEIVED in competitive grant funding to 
purchase buses (6.5-year total)
LIQUEFIED NATURAL GAS  
contract saves $2 million in fuel costs each year (FY 2018)
WEST TRANSIT FACILITY
awarded contract (FY 2019)
NORTH AND SOUTH FACILITIES 
awarded contract (FY 2020)
ALTERNATIVE TRANSPORTATION SERVICES 
technology enhancements include: ADA Ride, Senior Ride 
and Senior Center Shuttle, Employment Transportation  
and Medical Trip (FY 2019)
PTD IT is working on passenger notifications  
for passengers who use DAR (FY 2022) 
TRIPSPARK 
customer web portal for Dial-a-Ride reservations (FY 2018)
SECURITY
K-9 Security Unit Grant (FY 2017)
REGIONAL DIAL-A-RIDE IMPLEMENTED
eliminating transfers (FY 2017)
SOUTH TRANSIT FACILITY
refurbished (FY 2019)
COMPUTER-AIDED DISPATCH/AUTOMATED  
VEHICLE LOCATION upgrades installed (FY 2020)
AUDIO ON DIGITAL BUS SIGNS (FY 2018)
FARE COLLECTION SYSTEM awarded contract (FY 2020)
OPERATIONS CONTROL CENTER
awarded contract (FY 2020)
OVERVIEW
HCT
STREETS
APPENDIX
BUS/DAR
►
►
►
►
►
►

13
BUS AND DIAL-A-RIDE
The Phoenix Public Transit 
Department (PTD) focuses 
on operating transportation 
services that allow riders to have 
a safe ride while knowing there 
is much value in physically connecting our 
communities. With the available services, riders 
are able to get to schools, health facilities, jobs, 
grocery stores, pharmacies and many other 
critical connections. The department works 
in partnership with Valley Metro, the regional 
public transportation agency that provides 
coordinated transit services to riders in the 
metro area. 
Phoenix residents have access to a wide range 
of public transportation options, including fixed 
route bus and light rail service, neighborhood 
circulators, express commuter buses and 
alternative transportation services such as 
Dial a Ride (DAR) for people who are unable 
to utilize local routes due to a disability. This 
implies local bus/LRT and not just “bus service 
For additional transit information, visit  
phoenix.gov/publictransit.
Funding and Budget
Bus and DAR receive T2050 sales tax 
revenues and funding from federal grants. 
Funding is also generated from fare revenues, 
transit advertising, and the Regional Public 
Transportation Fund.
Employing all those resources, PTD used 
$235.5 million in FY 2022 to support ongoing 
operations and system improvements, 
which included greater bus frequency, 
additional and extended bus routes, new 
vehicles, shaded bus stops and security and 
technology enhancements. Phoenix plans 
to use $2.1 billion in the next five years to 
continue bus and DAR operations, make capital 
investments to ensure that the system remains 
in a state of good repair and further expand 
Dial-a-Ride buses provide people with disabilities 
a safe and convenient means of transportation.
OVERVIEW
HCT
STREETS
APPENDIX
BUS/DAR

14
COVID-19 Response
The Transportation Security Administration  
has lifted its federal mask mandate for all 
transportation services. Masks are now 
optional and no longer required for riders or 
employees of the Valley Metro system. The 
Centers for Disease Control continues to 
encourage masks on public transportation. 
PTD regularly updates staff members and 
contractors about health and safety protocols 
as CDC guidelines change. 
Despite the lessening of the impact of the 
COVID-19 pandemic and its effect on ridership 
and fare revenue, PTD is still operating at a 
reduced service level. The morning service 
span is restored to pre-pandemic levels, while 
evening service currently ends at 11 p.m. daily.  
We have continued to extend bus and Dial-a-
Ride service hours to match light rail hours. 
However, the pandemic’s continuing impact to 
ridership and labor force have so far prevented 
PTD from fully resuming pre-pandemic levels of 
In FY 2022, a total of 20,998,943 bus boardings
occurred in Phoenix, which is about half the
pre-pandemic level.
Local Fixed Route
The foundation of the public transportation 
network is local fixed route bus service. 
Riders can easily make their way to desired 
locations across the Valley using the grid 
system on which buses operate. Bus services 
were available nearly 24 hours per day prior to 
reductions in service due to the pandemic.
In FY 2022, a total of 20,998,943 bus boardings 
occurred in Phoenix, which is about half the 
pre-pandemic level. Throughout the pandemic, 
riders continued to use public transit for 
essential trips. PTD communicated with 
passengers about safety measures put in 
place throughout the transit environment.
Dial-a-Ride and Alternative 
Transportation Services 
Phoenix provides a variety of alternative 
transportation options including DAR, ADA 
Cab, Senior Cab and Senior Center Shuttle, 
Employment Trips and Medical Trips. 
DAR provides federally required paratransit 
service to individuals unable to ride the bus 
or light rail. This service complements fixed 
route bus service by operating during the same 
service hours. DAR passengers can schedule 
a ride by phone or TripSpark, an online 
reservation tool launched in 2018. 
MARY (Maryvale Area Ride for You) is one of four
circulator bus routes connecting key 
neighborhood destinations, like libraries and 
grocery stores.
Circulator Service
Four circulator routes connect local area 
residents with key neighborhood destinations, 
including libraries, grocery stores and 
community centers. Phoenix’s routes are ALEX 
(Ahwatukee Local Explorer), DASH (Downtown 
Area Shuttle), MARY (Maryvale Area Ride for 
You) and SMART (Sunnyslope Multi-Access 
Residential Transit).
PTD began conducting the Neighborhood 
Transit Study in FY22. The study will use 
public outreach meetings and surveys to 
review Phoenix’s current circulators. The 
study outcomes may include different fixed 
routing proposed by the public, frequency 
improvements, or different service delivery 
type such as flexible route. PTD began the 
study with a focus on the downtown DASH 
route and expects a report to be completed in 
FY 2023.
OVERVIEW
HCT
STREETS
APPENDIX
BUS/DAR

15
Residents in suburban areas have six RAPID route
options that provide a fast, stress free alternative 
to driving into downtown Phoenix.
RAPID Commuter
Six RAPID routes provide residents in 
suburban areas with an alternative to driving to 
downtown Phoenix.  
Park-and-Ride 
PTD maintains and operates nine park-and-
ride facilities, including the Sunnyslope, 
Metrocenter and Desert Sky transit centers, 
which provide free parking for transit users. 
In addition, Valley Metro manages five light 
rail park-and-ride locations along the Phoenix 
portion of the light rail alignment. A new park-
and-ride facility is anticipated to open in Laveen 
near Baseline Road and the South Mountain 
Freeway in 2024.
Bus Stops and Shelters 
PTD added 96 shade structures to existing 
bus stops during the past fiscal year. Over the 
next five fiscal years, Phoenix plans to install at 
least 80 additional shade structures at existing 
bus stops each year, totaling 400 new shade 
structures by FY 2027.
Over the next five fiscal years, Phoenix plans 
to install at least 400 new shade structures at 
existing bus stops across the city.
Table 2.1 T2050 Bus and Dial-a-Ride
Completed FY 2022 (July 1, 2021–June 30, 2022)
Fund existing bus, RAPID commuter bus, neighborhood 
circulator and Dial-a-Ride service for 35 years
	•
Continued to provide safe and reliable services.
	•
Maintained bus and DAR service hours to match light 
rail hours. 
Improve bus frequency
	•
Implemented Route 7 frequency improvement 
between Dobbins Road and Van Buren Street (October 
2021).
	•
Partially restored transit services that had been cut 
due to the COVID-19 pandemic and its impact on 
transit demand and the transit workforce. 
New buses and Dial-a-Ride vehicles
	•
Ordered 40 CNG buses, three circulator buses and 25 
DAR vehicles.
Extend and add bus service to unserved major streets
	•
Implemented Route 8  extension to Baseline Road and 
Central Avenue to connect with Route 0A (October 
2021).
	•
Implemented MARY Circulator extension along 
59th Avenue to Estrella Village via Fillmore St. and 
Roosevelt St. (April 2022).
	•
Completed outreach on proposed service change 
extending Route 43 on 43rd Avenue to Lower Buckeye 
Road, connecting to Route 28.
Bus bays 
	•
One bus bay was constructed at the intersection of 
75th Ave and Van Buren. The improvements at this 
intersection also included upgrading the adjacent 
signal with ADA compliant ramps and APS push 
buttons to help facilitate the safe movement of 
vehicles and pedestrians through the intersection.
Bus stops 
	•
Installed 96 new shade structures at existing bus 
stops. 
Incorporate technology
	•
The regional fare collection system modernization 
project continues into its 2nd year.  
	•
A limited feature trip planner and real-time 
information mobile application was launched in July 
2021.
	•
Mobile ticketing application will be launched in early 
2023.
	•
Reloadable smartcards and a new retail network for 
the new Valley Metro Card will be incorporated into 
the new fare collection system in early 2024.
Increase security
	•
Modified security hours at transit centers due to the 
pandemic and related decreased bus service hours.
OVERVIEW
HCT
STREETS
APPENDIX
BUS/DAR

16
Technology
Phoenix finalized the conversion of its regional 
transit fleet to the new Computer-Aided 
Dispatch/Automated Vehicle Location (CAD/
AVL) system supplied by Clever Devices. 
The conversion helped in updating the bus 
system technology and added new features to 
optimize transit system operations, dispatching 
and asset tracking.
The Regional Fare Collection System (FCS) 
Improvement Project is moving forward.  
Design has been completed and bus and light 
rail platform validators will be delivered from 
the manufacturer in the first quarter of FY23. 
All validators will be installed by mid-November 
2022.  A Mobile Ticketing pilot launch will 
begin in December 2022, with fares able to 
be purchased via the mobile app. Phase 2 will 
see a new public-facing website, reloadable 
smartcards, fare capping, and new Ticket 
Vending Machines (TVMs) across light rail.
Operations and Maintenance
Phoenix uses three facilities for bus 
maintenance, fueling and cleaning: the West, 
North and South Transit Facilities. First Transit,  
began providing transit services from the West 
Facility under a new agreement beginning 
July 1, 2018. Transdev began providing transit 
services from the North and South facilities 
under a new agreement beginning July 1, 
2020. Transdev also began providing services 
at the Operations Control Center on July 1, 
2020, adding three new controllers to provide 
increased system support and oversight.
Table 2.2 T2050 Bus and Dial-a-Ride
Planned for FY 2023
Fund existing bus, RAPID commuter bus, neighborhood 
circulator and Dial-a-Ride service for 35 years
	•
Continue to provide safe and reliable services.
	•
Maintain bus and DAR service hours to match light rail 
hours.
Improve bus frequency
	•
Restore transit services that had been cut due to the 
COVID-19 pandemic.
New buses and Dial-a-Ride vehicles
	•
Order 40 buses, three circulator buses and 25 DAR 
vehicles. RFP issued for Zero Emission buses. 
Extend and add bus service to unserved major streets
	•
Implement service change that would extend Route 43 
to Lower Buckeye Road.
	•
Conduct outreach on service change that would 
extend Route 28 to 99th Avenue.
	•
Conduct outreach on service change that would 
extend bus service north of Happy Valley Road on 
Norterra Pkwy.
Bus stops 
	•
Install 100 new shade structures at existing bus stops. 
ARPA funding allocated by the City Council provided 
for additional shade structure funding for 20 additional 
new shade structures for next two years.
Increase security
	•
Increase security as service expands.
Incorporate technology
	•
Continue work on the future launch of FCS mobile 
application.
	•
Implement a passenger notification system for DAR 
passengers which will produce automated message 
reminders when a trip is scheduled and when a driver 
is on its way to pick up a passenger.
Table 2.3 T2050 Bus and Dial-a-Ride
Planned for FY 2024–2027
Fund existing bus, RAPID commuter bus, neighborhood 
circulator and Dial-a-Ride service for 35 years
	•
Continue to provide safe and reliable services.
	•
Maintain bus and DAR service hours to match light rail 
hours.
New buses and Dial-a-Ride vehicles
	•
Order buses: 40 (FY 2023), 40 (FY 2024), 60 (FY 2025), 
60 (FY 2026), 40 (FY 2027).
	•
Order circulator buses: 3 (FY 2023), 3 (FY 2024), 3 (FY 
2025), 3 (FY 2026), 3 (FY 2027).
	•
Order 25 DAR vehicles each fiscal year. 
Extend and add bus service to unserved major streets
	•
FY2024: Add peak hour frequency on at least three 
local routes.
Circulator Service 
	•
Modify service pending outcomes of Neighborhood 
Transit Study.
	•
FY 2024: Improve MARY and ALEX service to every 30 
minutes. 	
Bus stops 
	•
Install 400 new shade structures at existing bus stops.
Increase security
	•
Increase security as service expands. 
Incorporate technology
	•
FY 2024: Launchable smart cards and reduced fare 
registration program. 
	•
The regional fare collection system modernization 
project continues into its 2nd year.  
	•
A limited feature trip planner and real-time information 
mobile application was launched in July 2021.
	•
Mobile ticketing application will be launched in early 
2023.
	•
Reloadable smartcards and a new retail network for 
the new Valley Metro Card will be incorporated into the 
new fare collection system in early 2024.
OVERVIEW
HCT
STREETS
APPENDIX
BUS/DAR

17
3.0
High Capacity 
Transit
OVERVIEW
BUS/DAR
STREETS
APPENDIX
HCT

18
HIGH CAPACITY TRANSIT
CUMULATIVE PROGRESS Jan. 1, 2016–June 30, 2022
LRT Ongoing Projects - Construction
NORTHWEST EXTENSION PHASE II
• Began construction in August 2020.
• Awarded three allocations for the FTA Capital Investment Grants 
program ($50.6 million in August 2020, $49.4 million in December 2020 
and $58 million in May 2021).
• Awarded $1 million for Transit Oriented Development (TOD) Planning 
Pilot Grant from the FTA.
• Began track and electrical installation work.
• In March 2022, completed the “Bridging East to West” milestone which 
completed the bridge girder installation crossing Interstate 17.
• In May 2022, $58.1 million allocation to complete the FTA CIG project 
cost share.
• In May 2022 began Metrocenter elevated station platform construction.
• Transit Oriented Development (TOD) Land Use Planning and Equitable 
Housing Project consultant procurement in planning stages.
SOUTH CENTRAL EXTENSION/DOWNTOWN HUB
• In February 2022, City Council approved the extension of Small Business 
Financial Assistance Program (SBFAP) to increase the number of 
businesses access to the funding.     
 - Eligibility criteria Increased the business annual revenue threshold 
$500,000 to $750,000.
 - Requirement for businesses to have been open not less than one year 
prior to construction is removed.
• Continue utility relocation work along the South-Central area of the 
alignment.
• From May 2021 to July 2022, installed new track configuration in 
Downtown Hub and Single tracking of LRT system for special track work 
for downtown hub.
• In May 2022, $232.1 million was allocated to complete the FTA CIG 
project cost share.
• Completed Salt River Bridge reinforcement in June.
LRT Ongoing Projects - Planning
Capitol Extension
West Phoenix Transit Corridor Study
I-10 West Extension
Light Rail Transit (LRT) Completed Projects
50th Street Station 
Northwest Extension Phase I
LRT Deferred Projects
Northeast Extension
35th Ave/Van Buren
Glendale
Peoria
Paradise 
Valley
Scottsdale
Tempe
Phoenix
Phoenix
9
2
1
5
8
6
3
7
EXISTING LIGHT RAIL 
PRIOR TO T2050 
4
PORTION OF THE WEST 
PHOENIX TRANSIT 
CORRIDOR STUDY
2
1
5
3
4
6
7
8
►BRT Service 
9
OVERVIEW
BUS/DAR
STREETS
APPENDIX
HCT

19
HIGH CAPACITY TRANSIT
CUMULATIVE PROGRESS Jan. 1, 2016–June 30, 2022
LRT Ongoing Projects - Construction
Northwest Extension Phase II
South Central Extension/Downtown Hub
LRT Ongoing Projects - Planning
CAPITOL EXTENSION
• In May 2022, reached 15% Preliminary Engineering, which identifies station 
locations under review.
• Capitol Extension and I-10 West Extension Transit Oriented Development 
(TOD) Land Use Planning and Equitable Housing Project consultant 
procurement process underway.
WEST PHOENIX TRANSIT CORRIDOR STUDY
• Approved to move forward by City Council, and for staff to apply for grant 
funds. (2022).
• In June, FTA awards $514,045 American Rescue Plan Route Planning 
Restoration Program grant to conduct a West Phoenix High-Capacity Transit 
(HCT) study.
• Consultant procurement process is currently underway.
I-10 WEST EXTENSION
• Preliminary planning and corridor evaluation continued.
• In April 2022, completed Traffic Analysis Report.
• Capitol Extension and I-10 West Extension Transit Oriented Development 
(TOD) Land Use Planning and Equitable Housing Project consultant 
procurement process underway.
Light Rail Transit (LRT) Completed Projects
50TH STREET STATION 
• Opened April 25, 2019.
• Received Sustainable 
Infrastructure Award from Arizona 
State University’s Metis Center.
NORTHWEST EXTENSION 
PHASE I
• Service began March 19, 2016.
LRT Deferred Projects
NORTHEAST EXTENSION
• Deferred to end of T2050 program by Phoenix 
City Council (2018).
35TH AVENUE/VAN BUREN STREET 
•	In April 2022, City Council approved further transit 
analysis, public outreach, alternatives analysis and 15% 
preliminary engineering for the initial BRT corridor of 35th 
Avenue/Van Buren Street.
Glendale
Peoria
Paradise 
Valley
Scottsdale
Tempe
Phoenix
Phoenix
9
2
1
5
8
6
3
EXISTING LIGHT RAIL 
PRIOR TO T2050 
7
4
PORTION OF THE WEST 
PHOENIX TRANSIT 
CORRIDOR STUDY
OVERVIEW
BUS/DAR
STREETS
APPENDIX
HCT
7
8
6
►Bus Rapid Transit (BRT) Ongoing Projects
5
3
4
1
2
9

20
HIGH CAPACITY TRANSIT
High-capacity transit (HCT) is 
able to serve more customers 
than traditional bus service 
because it uses larger-capacity 
vehicles. HCT also offers faster 
travel because it bypasses vehicular traffic.
For example, Phoenix’s light rail service can 
operate at faster travel speeds because it runs 
in an exclusive guideway with prioritized traffic 
signaling. The 16.5 miles of light rail service 
within the city of Phoenix is a substantial 
portion of the existing 28.2-mile Valley Metro 
Rail light rail system. Residents use the system 
to connect between the downtown areas of 
Phoenix, Tempe and Mesa, as well as Sky 
Harbor Airport and many other key destinations 
in between. 
In addition to light rail, bus rapid transit (BRT) 
is a key component of continuing to expand 
the city’s HCT network. The BRT program had 
previously completed an 11-month public 
education and community outreach campaign, 
which ran from February to December in 2020. 
The information gathered from this outreach 
effort, in addition to the transit analysis, was 
used to identify the recommended initial BRT 
corridor of 35th Ave and Van Buren Street. 
BRT focuses on improved speed, reliability, 
convenience, and the overall transit experience. 
There are common recurring elements found 
in successful BRT systems including enhanced 
stations, advanced fare collection, custom 
buses, unique branding, dedicated lanes, and 
transit spot improvements such as transit 
signal priority and queue jump lanes.
Northwest Extension Phase II: bridge construction
over I-17.
OVERVIEW
BUS/DAR
STREETS
APPENDIX
HCT

21
Phoenix Public Transit Department (PTD)
Despite the remaining challenges brought by COVID-19, the PTD saw significant progress in 
FY22:
	• On September 15, 2021, the Transportation, 
Infrastructure, and Planning Subcommittee 
recommended City Council approval of the 
initial Bus Rapid Transit (BRT) corridor of 
35th Avenue/Van Buren Street.                                     
	• On October 6, 2021, Phoenix City Council 
approved the initial BRT corridor of 35th 
Avenue/Van Buren Street. 
	• In October 2021, Route 0A frequency was 
modified in response to rail construction 
along the route. Route 7 frequency 
improved. Select RAPID trips were also 
restored that were reduced as result of the 
pandemic. 
	• On November 3, 2021, the Phoenix BRT 
hosted a Funding Workshop with Public 
Transit Department staff to discuss funding 
and finance strategies for the initial BRT 
Corridor of 35th Ave/Van Buren Street.
	• In November 2021, PTD performed 
outreach on the proposal to extend the 
MARY circulator further south on 59th 
Avenue. 
	• In April 2022, City Council approved 
further transit analysis, public outreach, 
alternatives analysis and 15% preliminary 
engineering for the initial BRT corridor of 
35th Avenue/Van Buren Street.
	• In May 2022, PTD conducted outreach on 
the proposal to extend Route 43 one mile 
south on 43rd Avenue from Buckeye Road 
to Lower Buckeye Road. The extension was 
subsequently approved and will become 
effective in October 2022.
The BRT webpage, Phoenix.gov/BRT, provides information about the program, including 
frequently asked questions.
Funding and Budget
The cities of Phoenix, Tempe and Mesa share 
funding obligations for the ongoing operations 
and maintenance of the light rail system. 
Expenses include vehicle operations, security 
and fare collection, and vehicle and system 
maintenance and administration.
Phoenix allocated $290.2 million in FY 2022 
to support ongoing light rail operations and 
expansion. T2050 includes an investment of 
more than $2 billion to expand and improve 
the city’s HCT network over the next five years. 
The plan includes light rail improvements and 
expansion and development of BRT. In addition 
to revenues generated by the city’s T2050 
sales tax, other funding sources include federal 
grants, the Regional Public Transportation 
Fund, fares and advertising. 
COVID-19 Response
In FY 2020, Valley Metro modified light rail hours 
in response to the COVID-19 pandemic, and 
these modifications remained largely in place 
through FY 2022. The first full trip on light rail 
began at approximately 4:45 a.m. with the last 
trip starting at 11 p.m. Adjustments included a 
15-minute frequency from 5 a.m.–6 p.m. with no 
late-night service on Friday or Saturday. Sunday 
service remained the same. As public works 
construction is considered an essential service, 
construction activities on HCT projects, such as 
the extension of light rail down Central Avenue 
(South Central Extension/Downtown Hub), and 
the extension of light rail toward the Metrocenter 
transit center (Northwest Extension Phase II) 
were able to progress as planned.
In March of this year construction crews 
completed bridge girder installation crossing 
over Interstate 17 for the Northwest Extension, 
Phase II.
“Bridging East to West” Cranes set the final girders
for the Northwest Extension, Phase II over I-17.
OVERVIEW
BUS/DAR
STREETS
APPENDIX
HCT

22
Table 3.1 T2050 High Capacity Transit
Completed FY 2021 (July 1, 2021–June 30, 2022) 
Increase light rail in Phoenix 
Northwest Extension Phase II
	•
Began track and electrical installation work.
	•
In March, completed the “Bridging East to West” 
milestone which completed the bridge girder 
installation crossing the Interstate 17. 
	•
In May, $58.1 million allocation to complete the FTA 
CIG project cost share.
	•
In May, began Metrocenter elevated station platform 
construction.
	•
Transit Oriented Development (TOD) Land Use 
Planning and Equitable Housing Project consultant 
procurement in planning stages. 
South Central Extension/Downtown Hub
	•
In February, City Council approved the extension of 
Small Business Financial Assistance Program (SBFAP) 
to increase the number of businesses access to the 
funding:
	- Eligibility criteria Increased the business annual 
revenue threshold $500,000 to $750,000.
	- Requirement for businesses to have been open 
not less than one year prior to construction 
removed.
	•
Continued utility relocation work along South-Central 
area of the alignment.
	•
In May, began installation of new track configuration in 
Downtown Hub.
	•
In June, began single tracking of LRT system for 
special track work for downtown hub.
	•
In May, $232.1 million allocation to complete the FTA 
CIG project cost share.
	•
In June, completed Salt River Bridge reinforcement.
Capitol Extension
	•
In May, reached 15% Preliminary Engineering.
	•
Capitol Extension and I-10 West Extension Transit 
Oriented Development (TOD) Land Use Planning and 
Equitable Housing Project consultant procurement 
process underway.
I-10 West Extension
	•
In April 2022, City Council approved further transit 
analysis, public outreach, alternatives analysis and 
15% preliminary engineering for the initial BRT corridor 
of 35th Avenue/Van Buren Street.
	•
Preliminary planning and corridor evaluation 
continued.
	•
In April, completed Traffic Analysis Report.
	•
Capitol Extension and I-10 West Extension Transit 
Oriented Development (TOD) Land Use Planning and 
Equitable Housing Project consultant procurement 
process underway.
Construction is well underway on the elevated
station for the Northwest Extension Phase II
Light Rail Service
Northwest Extension Phase II 
	• Phase II of the Northwest Extension will 
bring light rail almost to Metrocenter. The 
extension will run west on Dunlap Avenue 
from 19th Avenue, north on 25th Avenue 
and west on Mountain View across I-17, 
terminating near Metrocenter. 
	• Construction began in August 2020 and the 
extension is currently scheduled to open 
in 2024, which is three years earlier than 
originally anticipated. 
	• In FY22, track and electrical installation 
work began on this section and completed 
the “Bridging East to West’ in March. This 
milestone completed the bridge girder 
installation crossing Interstate 17.
	• In November 2021, the Full Funding Grant 
Agreement between Phoenix and the 
Federal Transit Administration (FTA) was 
executed.
	• The consultant procurement is in the 
planning stages for Transit Oriented 
Development (TOD) Land Use Planning and 
Equitable Housing Project. 
OVERVIEW
BUS/DAR
STREETS
APPENDIX
HCT

23
South Central Extension/Downtown Hub 
	• This extension adds 5.5 miles to the light 
rail system and connects South Phoenix 
residents to downtown Phoenix and the 
light rail network. The project includes a 
hub in downtown Phoenix, two park-and-
rides and public art.
	• Construction began on the South-Central 
Extension in October 2019 and the new line 
is expected to be operational by 2024.
	• During the last half of 2021 we completed 
crossover track work at 5th Street (Between 
Jefferson and Washington) and McKinley 
(Between 1st Ave and Central). We also 
continue utility relocation work along entire 
alignment. 
	• In February 2022, City Council approved the 
extension of the Small Business Financial 
Assistance Program (SBFAP) to increase 
the number of businesses eligible for 
funding:
	• Eligibility criteria Increased the business 
annual revenue threshold from  
$500,000 to $750,000. A requirement  
for businesses to have been open not less 
than one year prior to construction was 
removed.
	• We continued utility relocation work along 
South-Central area of the alignment, and 
in May, began installation of new track 
configuration in the Downtown Hub. Also 
in May, we allocated $290.2 million to 
complete the FTA CIG project cost share.
	• In June, we completed Salt River Bridge 
reinforcement and began single tracking of 
the downtown LRT system for special track 
work. 
Capitol Extension
	• The 1.4-mile Capitol Extension, originally 
known as Capitol/I-10 West Phase I, will 
connect the existing light rail system in 
downtown Phoenix to the Arizona state 
capitol.
	• During the first half of FY 22 we continued 
preparing for the federally required 
Environmental Assessment and began 
preliminary design.
	• In December, City Council approved the 
completed analysis of the route alignment 
(LPA), and in May 2022, we reached 15% 
Preliminary Engineering. 
	• The consultant procurement process 
is currently underway for the Capitol 
Extension and I-10 West Extension Transit 
Oriented Development (TOD) Land Use 
Planning and Equitable Housing Project.
	• The project is currently scheduled to be 
completed in 2026.
Table 3.2 T2050 High Capacity Transit
Planned for FY 2023
Increase light rail in Phoenix 
Northwest Extension Phase II
	• Continue utility relocation and rail construction.
South Central Extension/Downtown Hub
	• Continue utility relocation and rail construction.
Capitol Extension
	• Develop loop options and receive public input.
I-10 West Extension
	• Continue evaluating portions to expedite the project. 
Begin Bus Rapid Transit program
	• Begin the Alternatives Analysis process for the BRT 
Corridor of 35th Avenue and Van Buren Street.
I-10 West Extension
	• The I-10 West light rail extension will 
connect downtown Phoenix and the state 
capitol to the 79th Avenue Park-and-Ride 
in Maryvale. The project is expected to be 
completed in 2030. 
	• Preliminary planning and corridor 
evaluation continued in FY 22, while in April, 
we completed the project Traffic Analysis 
Report. 
	• The project analysis, which began in 2020, 
includes an analysis of transit types and 
funding opportunities, and an evaluation of 
extending the line to the Desert Sky Transit 
Center.
Table 3.3 T2050 High Capacity Transit
Planned for FY 2024–27
Increase light rail in Phoenix 
Northwest Extension Phase II
	• Complete construction, with anticipated opening in 
2024.
South Central Extension/Downtown Hub
	• Complete construction, with anticipated opening in 
2024. 
Begin Bus Rapid Transit program
	• Planning, design and construction of one or more  
BRT corridors. Timing and schedule to be determined 
by the CTC and Phoenix City Council.
OVERVIEW
BUS/DAR
STREETS
APPENDIX
HCT

24
Bus Rapid Transit
Phoenix will develop the BRT program based 
on where current and future transit riders need 
service most. The BRT outreach effort began 
with an 11-month community information 
campaign and solicited input on six potential 
BRT corridors and four potential network 
scenarios. The outreach team held 26 in-
person or virtual meetings, connected with 
more than 1,200 people and fielded/answered 
nearly 600 questions and comments. 
	• As a result, on May 27, 2021, the Citizens 
Transportation Commission (CTC) 
recommended Phoenix City Council 
approval of the initial BRT corridor of 35th 
Avenue/Van Buren Street.
	• On September 15, 2021, the Transportation, 
Infrastructure, and Planning Subcommittee 
recommended City Council approval of the 
initial Bus Rapid Transit (BRT) corridor of 
35th Avenue/Van Buren Street.
	• On October 6, 2021, Phoenix City Council 
approved the initial BRT corridor of 35th 
Avenue/Van Buren Street.
	• On November 3, 2021, the Phoenix BRT 
hosted a Funding Workshop with Public 
Transit Department staff to discuss funding 
and finance strategies for the initial BRT 
Corridor of 35th Ave/Van Buren Street.
	• On Feb. 24, 2022, the Citizens 
Transportation Commission recommended 
City Council approval to execute an 
amendment to the Phoenix Bus Rapid 
Transit (BRT) Program with AECOM 
to extend the term of the contract for 
24-months and provide further project 
management, public outreach and 
stakeholder engagement, alternative 
analysis, design concepts, and 15% design 
plans for the initial BRT corridor of 35th 
Avenue/Van Buren Street. 
	• On April 20, 2022, City Council approved 
an amendment to the Phoenix Bus Rapid 
Transit (BRT) Program with AECOM 
to extend the term of the contract for 
24-months and provide further project 
management, public outreach and 
stakeholder engagement, alternative 
analysis, design concepts, and 15% design 
plans for the initial BRT corridor of 35th 
Avenue/Van Buren Street.
In May, the Citizens Transportation Commission 
(CTC) recommended Council approval of the 
initial BRT corridor of 35th Avenue and Van 
Buren Street.
Approved BRT Corridor   
35th Ave/Van Buren
OVERVIEW
BUS/DAR
STREETS
APPENDIX
HCT

25
4.0
Street Maintenance 
and Improvements
OVERVIEW
BUS/DAR
HCT
APPENDIX
STREETS

IMPROVED/INSTALLED
22,338
ADA RAMPS
26
STREET MAINTENANCE AND IMPROVEMENTS
CUMULATIVE PROGRESS Jan. 1, 2016–June 30, 2022
* Cumulative number updated due to 
previous administrative errors, per staff 
update to the Citizens Transportation 
Commission in April 2022.
69 MILES OF NEW SIDEWALKS
26
OVERVIEW
BUS/DAR
HCT
APPENDIX
STREETS
ILLUMINATED 
STREET SIGNS
3,567
REPLACED
NEW STREETLIGHTS
3,369
INSTALLED
LEFT-TURN ARROWS
261
INSTALLED
INTERSECTIONS
1,040
PAINTED SIGNAL POLES at
►
►
►
►
STOP 
ON  
RED
INSTALLED
76
HAWKS
(High-intensity Activated 
crossWalKs)
►
STOP 
ON  
RED
INSTALLED
222.2*
MILES OF NEW  
BICYCLE LANES
►
Miles of 
new  
pavement
Miles of 
pavement 
treatments
ARTERIAL/MAJOR 
COLLECTORS
282
718
MINOR COLLECTORS/ 
LOCAL
592 2,354
►
►
39 POTENTIAL STUDY AREAS
►
 SELECTED 
12 MOBILITY STUDY LOCATIONS from
COMPLETED 12 STUDIES

27
STREET MAINTENANCE  
AND IMPROVEMENTS
The Street Transportation 
Department works to provide 
a safe and sustainable 
transportation network for 
everyone, including pedestrians, 
bicyclists and motorists. 
To ensure that people and goods move 
efficiently through the transportation network, 
the department’s work includes the pavement 
preservation program, asphalt and pothole 
repair and installation of street signs, traffic 
signals, streetlights, bikeways and Americans 
with Disabilities Act (ADA)-compliant ramps 
and sidewalks. 
Due to a well-defined scope, the Street 
Maintenance Division plans and executes 
many street improvement projects such as 
resurfacing and striping changes. However, 
larger-scale, more complex projects require a 
project assessment phase prior to design and 
construction. Examples of these more complex 
projects include turn lane improvements, lane 
additions and drainage studies.
The Street Transportation Department also 
conducts plan reviews for private development 
projects, construction inspections, materials 
testing and implementation of technology 
enhancements such as Geographic 
Information Systems (GIS). Visit phoenix.gov/
streets for additional information.
Asphalt paving at 19th Avenue and Camelback 
Road.
OVERVIEW
BUS/DAR
HCT
APPENDIX
STREETS

28
Funding and Budget
Phoenix streets receive funding from a variety 
of sources, including 13.8% of T2050 sales 
tax, the state-collected motor fuel tax, city’s 
general fund, regional/Maricopa Association 
of Governments (MAG) funds, federal funds, 
grants and impact fees. 
shows 
the overall T2050 program distribution of 
T2050 funds within the Street Transportation 
Department. 
In FY 2022, Phoenix budgeted approximately 
$44 million in T2050 funding for street 
construction and maintenance projects. 
Phoenix’s T2050 plan for FY22 and the next 
five years includes nearly $285 million to 
improve transportation system infrastructure, 
make ADA improvements, assess and address 
mobility needs and continue maintenance of 
city streets.
Figure 4.1 Overall T2050 Program Distribution 
for Street Improvements
 
5%
Technology 
enhancements
15%
Mobility
improvements
50%
Street 
maintenance
30%
 New and 
expanded 
streets
COVID-19 Response
During Covid-19 restrictions, street paving and 
patching, pothole repair sign replacement, 
lane striping, traffic signal servicing and 
installation and streetlight repair were not 
significantly affected as they are considered 
essential city services. As Covid-19 impacts 
are further reduced Street Maintenance and 
Improvements will continue.
Throughout this fiscal year, planning and 
design continued with community engagement 
occurring on virtual platforms. The shift to 
virtual engagement has resulted in high levels 
of engagement and valuable input for the 
project teams. 
Updates about health and safety protocols 
were regularly distributed to project teams and 
road crews, allowing schedules to be updated 
accordingly. Health and safety remain a top 
priority for the department.
Accelerated Pavement 
Maintenance Program
In 2018, the Phoenix City Council created 
the Accelerated Pavement Maintenance 
Program (APMP) and allocated $200 million of 
additional funding over five years. 
In June 2022, APMP had already reached 
its goal of 630 miles of mill and overlay 
treatments in just four years, a year sooner 
than its original goal. In FY 2022, under the 
APMP program the department performed 
mill and overlay treatment on 104 miles of 
streets, pavement preservation on 200 miles 
and crack seal on 360 miles in preparation for 
future work. Additionally, 3,411 ADA sidewalk 
ramps were installed. The 2023 paving season 
currently has 59 miles of overlay planned.
The annual Pavement Condition Report details 
the paving assessment process, pavement 
treatments and current conditions. The reports 
are available on the city’s website.
Street Pavement and Overlays
In FY 2022, the T2050 program financed a 
substantial amount of pavement maintenance 
and replacement across the city. A total of 18.7 
miles of new asphalt pavement was placed 
on major city streets, totaling 225.6 miles of 
new paving since the program began. Another 
120.6 miles of crack and fog sealing (pavement 
preservation that maintains the roadway until it 
requires replacement) was performed on major 
streets, with a cumulative total of 669.5 miles. 
Local (residential) streets saw 38.3 miles of 
new paving in FY22, for a total of 427 miles 
from the start of the program. Local streets 
also saw significant crack and fog sealing, with 
297.2 miles included, totaling 2,063.4 miles 
completed since the program began. 
Figure 4.1
OVERVIEW
BUS/DAR
HCT
APPENDIX
STREETS

29
Active Transportation Program 
The Active Transportation Program (ATP) 
strives to connect, improve and expand 
the city’s pedestrian and bicycle network. 
Active transportation and transit are highly 
interconnected because users depend on active 
transportation to access light rail, BRT and bus 
routes. 
As the Street Transportation Department repaves 
streets, the ATP identifies opportunities to update 
striping plans to add or widen bike lanes, add 
buffers to existing bike lanes and add markings 
in the intersections on major bikeways. Buffered 
bike lanes and protected bike lanes create more 
space between sidewalks and vehicle travel 
lanes, improving the walking experience.
The ATP also coordinates with other teams to 
support multi-use paths and street crossings. 
Projects along canals and other off-street trails 
strengthen the active transportation network and 
create a better quality of life for everyone. 
The Active Transportation Plan, which includes 
a Bicycle Master Plan update, launched its 
public outreach process in fall 2021 to find out 
residents’ priorities for enhancing the active 
transportation network.
With that in mind, FY22 saw extensive increases 
to the city’s bike network, adding 35.4 miles of 
new bike lanes, which is 4.5 miles more than 
the target goal of 30.9 miles. In addition, the 
ATP made a number of safety improvements to 
the existing bike lanes, adding either buffers or 
vertical protection:  
	• Protected bike lanes – 2.2 miles  
(A protected bike lane has a vertical 
element added to it, such as flexible lane 
delineators or a concrete curb, sometimes 
with a painted buffer.) 
A protected bike lane reduces conflicts 
between bicycles and vehicles by providing 
physical separation between people biking and 
people driving. 
	- 1 mile of protection was added to existing 
bike lanes.
	- 1.2 miles of protection was added to new 
bike lanes.
	• Buffers – 49.5 miles (A buffered bike lane 
has striping added to the pavement that 
alerts drivers and riders to the bike lane 
boundaries.)
	- 26.5 miles of buffers added to existing 
bike lanes.
	- 23 miles of buffers added to new bike 
lanes.
While updating the bikeway data structure, staff 
discovered an administrative error that resulted in 
an overcount of 26.9 bike lane miles. Despite the 
counting issues, Street Transportation remains 
ahead of the target of 30.9 bike lane miles per 
year. Staff verified all bikeway data using aerial 
photography and Google Streetview. Results 
were presented to the CTC in April 2022, along 
with a plan to install an additional 26.9 bike lane 
miles over the next three years
Mobility Studies
The Street Transportation Department 
conducts mobility studies to identify barriers 
for pedestrians and bicyclists as they travel to 
neighborhood destinations. Phoenix identified 
39 locations for study at the inception of T2050 
and has completed 12 studies so far.
To improve safety, convenience and quality 
of life, the studies’ recommendations have 
included opportunities for constructing new 
sidewalks, installing or improving ADA curb 
ramps and installing streetlights, bicycle 
facilities, traffic signals, shade trees and 
connections to transit stops. 
In FY22 we installed 54 Mobility ramps in 
partnership with the Neighborhood Services 
Department and their Community Development 
Block Grant (CDBG) funding.
In FY 2023, the Street Transportation 
Department will again partner with the 
Neighborhood Services Department to use 
Phoenix’s federal Community Development 
Block Grant to install at least 305 ADA mobility 
ramps recommended by the mobility studies.
Construction crews are installing hundreds of 
ADA curb ramps throughout the city, eliminating 
barriers to mobility for people with disabilities.
OVERVIEW
BUS/DAR
HCT
APPENDIX
STREETS

30
Table 4.1  
T2050 Street Maintenance and Improvements
Completed FY 2022 (July 1, 2021–June 30, 2022)
Street projects
	•
4 major street projects in design.
	•
3 major street projects in construction.
Street pavement and overlays
	•
Continued the Accelerated Pavement Maintenance 
Program, for which the Phoenix City Council authorized 
an additional $200 million to fast-track pavement 
maintenance through FY 2024.
	•
18.7 miles of new asphalt pavement on major streets.
	•
120.6 miles of other pavement treatments, such as 
crack and fog sealing, on major streets.
	•
38.6 miles of local street paving.
	•
297.2 miles of other pavement treatments on local 
streets.
Bicycle lanes
	•
Installed 35.4 miles of new bike lanes.
	•
Upgraded 1 mile of existing bike lane miles to 
protected bike lanes.
	•
Added 1.2 miles of protection to new bike lanes.
	•
Upgraded 26.5 miles of existing bike lanes to buffered 
bike lanes.
	•
Added 23 miles of buffering to new bike lanes.
Streetlights
	•
Installed 52 new streetlights.
Sidewalks
	•
Constructed 3 miles of sidewalks.
Intersection technology enhancements
	•
Replaced six street signs at major intersections with 
illuminated signs.
	•
Repainted all signal poles at 528 major intersections to 
extend their lifecycles.
	•
Installed 21 new left-turn arrows at warranted 
intersections.
	•
Installed nine pedestrian High-intensity Activated 
crossWalKs (HAWKs).
Intersection and Technology 
Enhancements
Phoenix uses a variety of technology 
enhancements, ranging from rapid flashing 
beacons and enhanced illumination to 
installing High-intensity Activated crosswalks 
(HAWKs). Other T2050 technology 
enhancements include improving and 
maintaining traffic control equipment, adding 
left-turn arrows at warranted intersections, 
replacing street name signs with retroreflective 
signs that feature light-emitting diode (LED) 
lighting and installing updated signals, signage, 
detection equipment and traffic management 
and monitoring systems.
The City, as part of a continuing transportation 
management program, is expanding the 
communication fiber backbone system to 
allow for remote monitoring, control and 
traffic signal optimization. The FY 2022 Indian 
School Road fiber enhancement project 
installed 12.5 miles of fiber optic infrastructure 
and cable to the western limits of the City of 
Phoenix and through a portion of the City of 
Glendale. The project provided connections 
between the Maricopa County Department of 
Transportation, the City of Glendale and the 
City of Phoenix. The FY 2023 Baseline Road 
fiber optic cable and equipment project will 
also install 13 miles of fiber optic infrastructure 
and cable along Baseline Road from South 
Mountain freeway (loop 202 ) to Interstate 10. 
This project will provide connections between 
the Arizona Department of Transportation, 
the City of Tempe and the City of Phoenix for 
remote monitoring, control and traffic signal 
optimization along the corridor.
Traffic Management Center (TMC) can better 
monitor traffic with cameras that send full 
streaming video back to the TMC. In addition, 
intelligent devices installed at intersections 
transmit traffic performance metrics to the 
TMC, allowing the TMC to adjust traffic signal 
timing to improve traffic flow and better 
serve the public. Similarly, the expanded fiber 
backbone provides for improved, integrated 
connections between stations for emergency 
responders such as fire and police.
Integration of new fiber optic lines to assist
traffic safety and operations.
Sensors installed at intersections transmit traffic 
performance metrics, allowing the TMC to adjust 
traffic signals and reduce congestion.
OVERVIEW
BUS/DAR
HCT
APPENDIX
STREETS

31
Information Technology and GIS
The Street Transportation Department 
digitizes, validates and reports on assets. The 
department uses GIS technology to catalogue 
location data and maintenance records on 
bikeways, pavement, lighted street signs and 
ADA curb ramps. Ultimately, the data allow for 
more efficient planning, analysis and reporting. 
Recent improvements in these processes have 
included: 
	• Creating field staff applications for 
reporting condition and improvement 
needs related to assets such as traffic 
signals, pavement, curb ramps, sidewalks 
and streetlights.
	• Improving the accuracy, usefulness and 
availability of existing traffic signal data for 
the entire department.
	• Leveraging pavement condition data, with 
underlying soil condition data, to provide 
engineers with a broader understanding of 
problematic areas.
	• Using data sources from the city, county 
and Arizona State University to identify and 
map tree and shade prioritization areas.
	• Updating bikeways, Key Corridors Master 
Plan and Mobility Studies data to give 
the ATP team accurate information for 
planning and implementing improvements. 
	• Researching and editing thousands of 
ADA ramp records to build and update the 
database.
Internal and external applications allow staff 
and, in many cases, residents to access 
map services and applications with this GIS 
information. Some of these include a live active 
HAWK traffic signal web map, the pavement 
maintenance dashboard, bikeways map 
services and e-scooter facilities mapping. 
As staff members in the field make live 
updates, the accumulated data and analysis 
tools provide for a more efficient workflow and 
near-real-time analysis and reporting.
Public facing interactive pavement maintenance 
dashboard provides mapping, information and 
schedules for planned pavement treatments 
across the City.
Table 4.2  
T2050 Street Maintenance and Improvements
Planned for FY 2023
Street projects
	•
Design 10 major street projects. 
	•
Continue construction on 24 major street projects.
Street pavement and overlays
	•
Pave 19 miles on major streets.
Bicycle lanes
	•
Install 31 miles of bike lanes and low-stress bikeways.
Streetlights
	•
Install 100 new streetlights. 
Sidewalks
	•
Construct 4 miles of new sidewalks.
Mobility studies
	•
Install 305 ADA ramps based on mobility studies. 
Intersection technology enhancements
	•
Replace 240 street signs at major intersections with 
illuminated signs.
	•
Repaint all signal poles at 80 major intersections to 
extend their lifecycles.
	•
Install 15 pedestrian HAWKs.
Table 4.3  
T2050 Street Maintenance and Improvements
Planned for FY 2024–2027
Street projects
	•
Conduct one major street project assessment. 
	•
Design 11 major street projects. 
	•
Continue construction on 20 major street projects.
Street pavement and overlays
	•
Pave at least 77 miles of new pavement on major 
streets.
Bicycle lanes
	•
Install 124 miles of bike lanes and low-stress 
bikeways.
Streetlights
	•
Install 400 new streetlights. 
Sidewalks
	•
Construct 15 miles of new sidewalks.
Intersection technology enhancements
	•
Replace 960 street signs at major intersections with 
illuminated signs.
	•
Repaint all signal poles at 320 major intersections to 
extend their lifecycles.
	•
Install 25 pedestrian HAWKs.
OVERVIEW
BUS/DAR
HCT
APPENDIX
STREETS

32
5.0
Appendix
OVERVIEW
BUS/DAR
HCT
STREETS
APPENDIX

33
APPENDIX
Lifecycle Programming Assumptions 
As with any long-term plan, preparation of the financial model for the T2050 program required 
many assumptions for estimated costs, revenues and timing of projects and new services. Key 
assumptions of the T2050 program include: 
	• The implementation of projects and new 
services is projected to occur over the 
course of the 35-year plan as funding 
allows and service demand dictates. 
	• Capital and operating costs are estimated 
to grow at average inflation rates of 3–4% 
annually over the life of the plan. These 
inflation rates are somewhat higher than 
the typical annual increases the city has 
experienced in the large transit contracts, 
and provide for more conservative cost 
estimates.
	• T2050 sales tax revenues are estimated to 
grow at an average annual rate of 4.75%, 
which is slightly lower than the 5.2% 
average annual growth rate in the Arizona 
Department of Transportation’s most 
recent forecast prepared in September 
2020 for the Proposition 400 Maricopa 
County Transportation Excise Tax. 
	• The existing 0.5% Proposition 400 regional 
tax, currently in place through Dec. 31, 
2025, is assumed to be extended for at 
least 20 years. 
	• Federal transit formula funds are assumed 
to continue through the life of the plan, with 
very modest increases over time, and are 
consistent with MAG’s long-term Regional 
Transportation Plan.
	• The financial model is consistent with 
Valley Metro assumptions, ranging from 
0% to 39%, for the funding level from 
discretionary federal Capital Investment 
Grants for light rail capital costs. 
Discretionary federal Capital Investment 
Grants, on average, fund more than 40% of 
total project costs for current rail projects 
across the country. 
	• Transit fares are assumed to continue to 
be lower than the regional fare policy goal 
of 25% recovery of direct transit operations 
costs, reflecting the current fare recovery 
rate. Decreased fare revenues due to 
the COVID-19 pandemic are assumed to 
recover very slowly over 20 years.
	• Some capital funding is assumed to be 
provided through financing, as needed, 
with the corresponding costs estimated 
using typical municipal bond offerings. 
Less expensive and more flexible types 
of financing will be explored to minimize 
financing costs. 
	• Other revenues, such as transit advertising 
and interest earnings on fund balance, are 
forecasted using very low growth rates. 
	• An operating reserve equivalent to 15% 
of annual public transit operating costs is 
assumed to be maintained throughout the 
life of the plan.
As rates of Covid-19 infections declined fare 
revenues began to recover, though are still below 
2019 levels.
Impact of COVID-19
Phoenix had expected that the global 
pandemic, which began in 2020 as a result of 
the contagious COVID-19 virus, would reduce 
revenue projections for the coming years 
because ridership numbers fell significantly 
in 2020. However, there were some economic 
drivers that had a positive impact on revenue 
projection, which city leaders continue to 
monitor.
This report notes the changes experienced due 
to the pandemic within each program area.
OVERVIEW
BUS/DAR
HCT
STREETS
APPENDIX

34
T2050 Sales Tax Projected Revenue Stream
The following table includes the projected sales tax revenue for each year of the T2050 plan. Additionally, the table shows the anticipated 
allocation to the Public Transit and Street Transportation departments. 
Table A.1 T2050 Sales Tax Projected Revenue Stream
Fiscal Year
Overall T2050  
(2015 Forecast)
Actual Overall
Forecasted Public Transit 
(86.2%)
Actual Public Transit
Forecasted Street  
Transportation (13.8%)
Actual Street  
Transportation
2016
$89,125,000
$98,593,240
$76,826,000
$85,095,392
$12,299,000
$13,497,848
2017
$204,006,000
$203,352,480
$175,853,000
$175,430,201
$28,153,000
$27,922,279
2018
$213,696,000
$215,805,685
$184,206,000
$185,998,894
$29,490,000
$29,806,791
2019
$224,401,000
$239,179,006
$193,434,000
$206,200,341
$30,967,000
$32,978,665
2020
$235,642,000
$247,592,555
$203,123,000
$213,437,765
$32,519,000
$34,154,790
2021
$246,835,000
$279,348,428
$212,772,000
$240,800,097
$34,063,000
$38,548,331
2022
$258,559,000
$335,608,608
$222,878,000
$289,313,016
$35,681,000
$46,295,592
2023
$270,841,000
blank
$233,465,000
blank
$37,376,000
blank
2024
$283,706,000
blank
$244,555,000
blank
$39,151,000
blank
2025
$297,182,000
blank
$256,171,000
blank
$41,011,000
blank
2026
$311,298,000
blank
$268,339,000
blank
$42,959,000
blank
2027
$326,085,000
blank
$281,085,000
blank
$45,000,000
blank
2028
$341,574,000
blank
$294,437,000
blank
$47,137,000
blank
2029
$357,799,000
blank
$308,423,000
blank
$49,377,000
blank
2030
$374,794,000
blank
$323,072,000
blank
$51,722,000
blank
2031
$392,597,000
blank
$338,419,000
blank
$54,178,000
blank
2032
$411,245,000
blank
$354,493,000
blank
$56,752,000
blank
2033
$430,779,000
blank
$371,331,000
blank
$59,448,000
blank
2034
$451,241,000
blank
$388,970,000
blank
$62,271,000
blank
2035
$472,675,000
blank
$407,446,000
blank
$65,229,000
blank
2036
$495,127,000
blank
$426,799,000
blank
$68,328,000
blank
2037
$518,646,000
blank
$447,073,000
blank
$71,573,000
blank
2038
$543,281,000
blank
$468,308,000
blank
$74,973,000
blank
2039
$569,087,000
blank
$490,553,000
blank
$78,534,000
blank
2040
$596,119,000
blank
$513,855,000
blank
$82,264,000
blank
2041
$624,435,000
blank
$538,263,000
blank
$86,172,000
blank
2042
$654,095,000
blank
$563,830,000
blank
$90,265,000
blank
2043
$685,165,000
blank
$590,612,000
blank
$94,553,000
blank
2044
$717,710,000
blank
$618,666,000
blank
$99,044,000
blank
2045
$751,801,000
blank
$648,052,000
blank
$103,749,000
blank
2046
$787,512,000
blank
$678,835,000
blank
$108,677,000
blank
2047
$824,919,000
blank
$711,080,000
blank
$113,839,000
blank
2048
$864,102,000
blank
$744,856,000
blank
$119,246,000
blank
2049
$905,147,000
blank
$780,237,000
$124,910,000
2050
$948,142,000
blank
$817,299,000
blank
$130,844,000
blank
Total
$16,679,368,000
blank
$14,377,615,000
blank
$2,301,753,000
blank
OVERVIEW
BUS/DAR
HCT
STREETS
APPENDIX

35
FY 2022 Financial Overview
The FY 2022 Financial Overview table summarizes the budgeted and actual revenue and expenditures during FY 2022.
Table A.2 FY 2022 Financial Overview (July 1, 2021 - June 30, 2022)
Source of Funds
Budget
Actuals
Amount Over/(Under Budget)
Percent Over/Under Budget
Footnotes
Dedicated Sales Tax - T2050
274,395,000
335,608,608
61,213,608
22.3%
1
Local Transportation Assistance
 4,300,000 
4,052,686
 (247,314)
-5.8%
Bus Fare Revenue
17,708,957
12,142,592
 (5,566,365)
-31.4%
2
DAR Fare Revenue
889,066
502,968
 (386,098)
-43.4%
3
Rail Fare Revenue
4,797,716
3,355,396
 (1,439,321)
-30.0%
4
Federal Transit Funds
518,867,287
236,632,263
 (282,235,024)
-54.4%
5
Regional Transportation Tax
64,266,816
3,857,201
 (60,409,615)
-94.0%
6
Debt Proceeds
-
 - 
-
-
7
Other Revenue
8,202,649
25,480,764
17,278,115
210.6%
8
Fund Balance
(27,685,940)
 (96,279,778)
 (68,593,837)
247.8%
9
 Total Revenues
 $865,738,551 
 $525,352,700 
 $(340,385,851)
-39.9%
Use of Funds in Transit Operations
Budget
Actuals
Amount Over/(Under Budget)
Percent Over/Under Budget
 Local Fixed Route Bus
 $1501,471,083 
 $147,342,304 
 $(3,128,779)
-2.1%
 RAPID Commuter Bus
2,444,566
2,757,611
313,045
12.8%
10
 Neighborhood Circulator
3,748,622
3,831,294
82,672
2.2%
 Bus Rapid Transit
 - 
 - 
 - 
N/A
11
 DAR Operations
21,231,800
19,005,919
 (2,225,881)
-10.5%
12
 Light Rail Operations
42,484,798
19,954,485
 (22,530,313)
-53.0%
 Security
13,060,602
12,121,303
 (939,299)
-7.2%
13
 Administration & Support
27,180,000
24,780,245
 (2,399,755)
-8.8%
14
Total Operations
 $260,621,472 
 $229,793,162
 $(30,828,310)
-11.8%
Debt Service
 $21,124,625 
 $1,522,947
 $(19,601,678)
-92.8%
15
Use of Funds in Capital Projects
Budget
Actuals
Amount Over/(Under Budget)
Percent Over/Under Budget
 Bus and DAR Vehicles
46,712,943
25,507,308
 $(21,205,635)
-45.4%
16
 Bus Passenger Facilities
14,182,195
2,777,896
 (11,404,299)
-80.4%
17
 Bus O & M Facilities
28,246,735
2,043,494
 (26,203,241)
-92.8%
18
 Bus and DAR Technology
39,712,074
1,044,562
 (38,667,512)
-97.4%
19
 Other Bus Capital
12,056,676
1,579,530
 (10,477,146)
-86.9%
20
 South Central LRT
266,474,00
130,145,160
 (136,328,840)
-51.2%
21
 Northwest Phase II LRT
103,849,00
74,344,591
 (29,504,409)
-28.4%
22
9,970,000
43,825
 (9,926,175)
-99.6%
23
 LRT Other
 1,841,457 
3,986
 (2,028,014)
-99.8%
24
 Bus Rapid Transit
2,032,000
4,617
 (5,999,665)
0.0%
25
 Streets – Major Maintenance
17,053,000
39,105,848
 22,052,848
-129.3%
 Streets – Major Transportation Projects
21,510,252
9,795,126
 (11,715,126)
-54.5%
 Streets – Mobility Projects
9,308,797
2,776,937
 (6,531,861)
-70.2%
 Streets – Other
2,639,500
913,021
(1,726,479)
-65.4%
 Streets – Technology
4,241,000
3,950,689
 (290,311)
-6.8%
Total Capital Projects
 $583,992,454 
 $294,036,592 
 $(289,955,863)
-49.7%
Total Expenditures
 $865,738,551 
 $525,352,700 
 $(340,385,851)
-39.3%
Transit Operations
Source of Funds
Capital Projects
 Capitol Light Rail Extension
OVERVIEW
BUS/DAR
HCT
STREETS
APPENDIX

36
Footnotes detailing the FY 2022 Financial Overview table found on the preceding page include: 
1.	 Better than expected local economic 
activity resulted in higher sales tax 
revenues.
2.	
Front door boarding and use of 
fareboxes resumed 10/11/21.
3.	
Front door boarding and use of 
fareboxes resumed 10/11/21.
4.	
Front door boarding and use of 
fareboxes resumed 10/11/21.
5.	
Decrease due to Capital Project delays.
6.	
Decrease due to Capital Project delays.
7.	
Transit did not need to finance due to 
federal pandemic relief funds received from 
FTA and higher than expected sales tax 
revenues.
8.	
$13M Streets CIP Expense Recovery, $6.5M 
PTD Expense Recovery, $2M Higher than 
expected transit advertising revenues.
9.	
Fund balance increased due to federal 
pandemic relief funds received from 
FTA and higher than expected sales tax 
revenues.
10.	 20% increase in scheduled revenue miles 
over prior estimate.
11.	 Reduction in revenue hours due to 
pandemic.
12.	 Reduction in payments to Valley Metro 
Rail due to lower service levels and federal 
pandemic relief funds received from FTA.
13.	 New Security Contract less than initially 
budgeted.
14.	 Personal Services and Technology less than 
budgeted.
15.	 Transit did not need to finance due to 
federal pandemic relief funds received from 
FTA and higher than expected sales tax 
revenues.
16.	 Fleet manufacturers’ production delays.
17.	 Laveen Park n Ride delayed.
18.	 Projects delayed.
19.	 Projects delayed.
20.	 Unused contingency.
21.	 Delay in funding needed from Phoenix for 
the project.
22.	 Delay in funding needed from Phoenix for 
the project.
23.	 Project delays.
24.	 Over programed budget for disposal of 
remnant properties, Business Assistance 
Program, McDowell & Central and City Core 
Staff - West Phx/Central Glendale.
25.	 Longer than expected public/stakeholder 
involvement process.
OVERVIEW
BUS/DAR
HCT
STREETS
APPENDIX

37
Five-Year Implementation Plan
The Five-Year Implementation Plan table summarizes the projected distribution of funds collected over the next five years. The table does not include 
actual collections. Note: BRT capital and operations expenditures are planned to be incurred during this five-year plan, and the amounts reflected are 
preliminary, pending the results of the BRT study.
Table A.3 Five-Year Implementation Plan (FY 2023–2027) 
Use of Funds for Transit Operations
FY 2021-2022
FY 2022-2023
FY 2023-2024
FY 2024-2025
 FY 2025-2026
Local Fixed Route Bus
 $159,711,621 
 $165,868,932 
 $172,700,668 
 $178,117,442 
 $190,926,738 
RAPID Commuter Bus
3,851,573
3,940,495
4,103,141
4,216,325
 4,343,769
Neighborhood Circulator
3,911,960
7,178,144
7,481,712
7,729,252
 7,994,861 
Bus Rapid Transit
 - 
2,201,056
7,467,096
7,723,664
 7,996,560 
DAR Operations
22,182,792
22,848,276
23,533,724
24,239,736
 24,966,928
Light Rail Operations
44,978,980
46,727,002
63,031,083
62,498,075
71,570,298
Security
13,468,302
13,872,351
14,288,522
14,717,177
15,158,693
Administration & Support
27,995,400
28,835,262
29,700,320
30,591,329
31,509,069
Total Operations
 $276,100,627 
 $291,471,519 
 $322,306,265 
 $323,833,001 
 $354,466,916 
Debt Service
 $2,501,000 
 $10,000,000 
 $12,352,250 
 $29,119,938 
 $30,294,500 
Use of Funds for Capital Projects
FY 2021-2022
FY 2022-2023
FY 2023-2024
FY 2024-2025
 FY 2025-2026
Bus and DAR Vehicles
 $53,557,503 
 $49,290,645 
 $50,027,783 
 $62,687,005 
 $63,469,019 
Bus Passenger Facilities
24,082,534
4,330,000
4,330,000
4,430,000
4,430,000
Bus O&M Facilities
24,268,036
2,450,000
2,200,000
2,200,000
2,200,000
Bus and DAR Technology
26,054,178
2,520,000
300,000
20,000
20,000
Other Bus Capital
17,812,366
4,721,058
2,668,086
2,669,915
2,676,861
South Central Light Rail
251,334,000
260,986,000
65,189,000
-
-
Northwest Phase II Light Rail Extension
136,161,000
33,171,000
-
-
 - 
Capitol Light Rail Extension
23,318,000
43,051,000
78,603,000
107,264,000
115,155,000
Capitol/I-10 West Rail Extension
11,940,523
 24,597,477 
266,021,717
391,431,955
403,174,914
Other Light Rail
141,000
 - 
 - 
 - 
 - 
Bus Rapid Transit
40,790,000
50,000,000
160,000,000
55,000,000
160,000,000
Total Public Transit T2050 Capital Projects
 $609,459,140 
 $475,117,180 
 $629,339,586 
 $625,702,875 
 $751,125,794 
Streets – Major Maintenance
 $48,768,578 
 $25,090,000 
 $25,090,000 
 $26,090,000 
 $27,090,000
Streets – Major Transportation Projects
 $12,782,893 
 $2,909,337 
 $14,125,015 
 $11,147,337 
 $1,977,337 
Streets – Mobility Projects
 $11,515,451 
 $12,021,601 
 $671,327 
 $1,161,000 
 $1,066,000 
Streets – Other
 $463,000 
 $463,000 
 $463,000 
 $463,000 
 $463,000 
Streets – Technology
 $10,028,323 
 $2,364,000 
 $2,175,345 
 $1,510,000 
 $860,000 
Total Streets T2050 Capital Projects 
 $83,558,245 
 $42,847,938 
 $42,524,687 
 $40,371,337 
 $31,456,337
Total Capital Projects
 $693,017,385 
 $517,965,118 
671,864,273
 $666,074,212 
 $782,582,131 
Total Expenditures
 $971,619,012 
 $819,436,637 
 $1,006,522,788 
 $1,028,027,151 
 $1,167,343,547 
Year End Fund Balance: Public Transit
 $253,334,554 
 $36,890,037 
 $123,900,193 
 $200,456,592 
 $352,339,531
Year End Fund Balance: Streets
49,246,659
51,499,027
49,116,088
51,502,841
54,282,258
Total Fund Balance
 $302,581,212
 $88,389,064 
 $173,016,281 
$251,959,433
 $406,621,789 
Source of Funds
FY 2022-2023
FY 2023-2024
FY 2024-2025
FY 2025-2026
 FY 2026-2027
Dedicated Sales Tax – T2050
 $326,455,000 
 $344,937,0000 
 $363,346,000 
 $382,305,000 
 $402,433,000 
Local Transportation Assistance
4,100,000
 4,100,000 
4,100,000
 4,100,000 
 4,100,000 
Bus Fare Revenue
18,018,129
 24,945,870 
30,394,321
32,504,044
 33,769,118 
DAR Fare Revenue
711,790
753,660
847,512
941,680
941,680
Rail Fare Revenue
3,852,674
6,485,335
9,953,069
10,052,600
12,010,726
Federal Transit Funds
496,434,040
148,370,708
477,870,024
489,470,033
514,437,012
Regional Transportation Tax
86,721,200
65,953,645
58,103,127
177,605,546
184,173,097
Debt Proceeds
 - 
 - 
136,692,208
-
160,000,000
Other Revenue
9,554,946
9,698,270
9,843,744
9,991,400
10,141,271
Fund Balance
25,771,234
214,192,148
 (84,627,217)
(78,943,152)
 (154,662,356)
 Total Revenues
 $971,619,012 
 $819,436,637 
 $1,006,522,788 
 $1,028,027,151
 $1,167,343,547 
Source of Funds
Use of Funds
Transit Operations
Capital Projects
37
OVERVIEW
BUS/DAR
HCT
STREETS
APPENDIX