Attachment B - CAPEX Budget
City of Phoenix — Transportation, Infrastructure, and Planning Subcommittee (2021-10-20)
Extracted text (via pymupdf)
624 characters
Attachment B Estimated Design and Pre-construction Activities Budget Activity Estimated Budget Notes Preliminary Engineering (PE) $5,400,000 Preliminary engineering including 15% and 30% designs, and community outreach during the PE and EA phases. Environmental Assessment (EA) $1,800,000 N/A Final Design $23,300,000 Includes design up to 100% with community outreach during this phase. Pre-Construction $10,600,000 Constructability, third party utility design and real estate support Contingency $4,200,000 Contingency at 10% of PE, EA, Final Design and Pre-construction total. TOTAL $45,300,000