Contract No. 2025088 CO #2.pdf

City of Buckeye โ€” Special (2026-06-02)

View PDF Meeting page

Extracted text (via pymupdf) 7877 characters
JOB ORDER CONTRACT DELIVERY ORDER 
BETWEEN 
THE CITY OF BUCKEYE 
AND 
HITT CONTRACTING, INC. 
CONTRACT NO. 2025088 
DELIVERY ORDER NO. 2 
CHANGE ORDER #1 
THIS CHANGE ORDER #1 
 is entered into as of __________________, 
between the City of Buckeye, an Arizona municipal corporation 
HITT 
Contracting, Inc., a Virginia corporation 
. This Change Order modifies certain 
sections of Delivery Order No. 2 to Contract No. 2025088 
Delivery Order , with those 
sections not expressly modified remaining in full effect pursuant to their terms.  
RECITALS: 
The City and Contractor entered into Delivery Order No. 2 to Contract No. 2025088 dated 
February 3, 2026. Pursuant to which Contractor was to provide construction services for the Miller 
Road Landscape Improvements: Lower Buckeye  Pima Street Phase I project with the completion 
of the Work eight weeks from the issuance from the Notice to Proceed and a not-to-exceed amount 
of $400,000.00. 
DELIVERY ORDER CHANGES: 
1.
Article 1  Scope of Work and Exhibit A of the Original Delivery Order  - Proposal,
are amended to incorporate the additional services set forth in Exhibit 1 of Change Order #1. 
2.
Article 2 
 Schedule of Completion of Work, is amended by revising the
completion date for the Work from eight (8) weeks from the effective date of the Notice to Proceed, 
to ten (10) weeks from the effective date of the Notice to Proceed.  
3.
Article 3  Cost of Construction, is amended by increasing the total not-to-exceed
amount by $139,624.72, from $400,000.00 to $539,624.72. 
ADDITIONAL PROVISIONS: 
Except as amended herein, all provisions of the Delivery Order and Contract remain in full 
force and effect. 
In the event of any conflict or discrepancy between the terms of this Change Order, the 
Delivery Order, the Contract, and any other contract documents, the documents shall govern in 
that order.   
Miller Road Landscape Improvements: 
Lower Buckeye - Pima Street Phase I 
Contract No. 2025088, Delivery Order #2, Change Order #1
1
HITT Contracting, Inc. 
(REV. 6.23.25)

This Change Order may be canceled pursuant to the provisions of A.R.S. ยง 38-511.  
 
IN WITNESS WHEREOF, the parties hereto have executed this Change Order as of the date 
first set forth above. 
 
CITY:  
 
 
 
 
 
CONTRACTOR: 
 
THE CITY OF BUCKEYE,  
 
 
HITT CONTRACTING, INC., 
an Arizona municipal corporation 
 
 
a Virginia corporation 
 
 
 
     
 
 
 
 
 
 
 
 
 
 
 
 
 
By:  
 
 
 
 
 
 
Doug Sandstrom, City Manager 
 
 
 
 
 
 
 
 
 
 
Its:  
 
 
 
 
 
 
 
 
ATTEST: 
 
 
 
 
 
 
 
 
 
 
Lucinda Aja, City Clerk 
 
RECOMMENDED: 
 
 
 
 
 
 
 
 
 
 
Rob Roach, Grant Program and Procurement Manager 
 
APPROVED AS TO FORM: 
 
 
 
 
 
 
 
 
 
 
Tosca Henry, City Attorney 
 
 
Miller Road Landscape Improvements: 
Lower Buckeye - Pima Street Phase I 
Contract No. 2025088, Delivery Order #2, Change Order #1
2
HITT Contracting, Inc. 
(REV. 6.23.25)

Exhibit 1 
 
 
Miller Road Landscape Improvements: 
Lower Buckeye - Pima Street Phase I 
Contract No. 2025088, Delivery Order #2, Change Order #1
3
HITT Contracting, Inc. 
(REV. 6.23.25)

C.O.R. NO.
1
Job: COG Main Library Mason Repairs
Project #: 26-308
Date:
4/15/2026
Change Order Description:
Brycon's Work:
MH
Labor Rate
Labor $
Material
Equipment
Other
Subtotal  
Subcontractors / Vendors:
1
Allowance for APS
2
Electrical - Tekline
3
Additional 2 Weeks Schedule
4
5
6
7
8
9
10
Contractors/Vendors Direct Cost Subtotal
Brycon Construction's Work Direct Cost Subtotal
Remarks:
Net Subtotal
Subcontractor Bond
Subtotal
General Conditions
10.00%
Subtotal
BC Bond
0.90%
Subtotal
BC Ins.
1.09%
Subtotal
Fee
6.38%
Total Change:
$139,624.72
Subtotal
.
Contract time:
10 days
Sales Tax
5.700%
This C.O.R. valid for:
30 Days
Submitted by:
Brycon 
Brycon C.O.R. No.
1
6915 W. Frye Rd. 
Architect  Acceptance
Chandler, AZ 85226
Date
Shannon Ballard, Project Manager
Owner Acceptance
Project Manager Name / Title
Date
Note:  This modification constitutes compensation in full on behalf of the contractor and its subcontractors and suppliers 
for direct costs only which are attributable to the changes ordered herein.  We reserve the rights to time extensions,
time-related costs and any indirect costs that result or flow from the changes ordered herein.
$7,100.83
$139,624.72
Gross Total
Attached is the change order request to provide the electrical panel and electrical connections for the two irrigation controllers.  
This includes the assumption that all underground raceways are existing and clear.  We have included a $75,000 allowance for 
the APS design, once the design is provided it will be priced and submitted for a separate change order.  We are requesting an 
additional 10 days to complete this scope of work.
$1,099.20
$123,232.71
$1,343.24
$124,575.94
$7,947.95
$132,523.89
$111,030.46
$111,030.46
$11,103.05
$122,133.51
$111,030.46
BRYCON
CHANGE ORDER REQUEST
PRICING BREAKDOWN
SUB / VENDOR $
$75,000.00
$27,600.00
$8,430.46
Miller Road Landscape Improvements: 
Lower Buckeye - Pima Street Phase I 
Contract No. 2025088, Delivery Order #2, Change Order #1
4
HITT Contracting, Inc. 
(REV. 6.23.25)

Brycon 
 
Phoenix, AZ  
 
Attn: John Patterson 
 
 
SUBJECT: 
COB Miller road landscape 
 
ELECTRICAL PROPOSAL Revised with expedite adder 
 
We are SBE/DBE/MBE Certified 
 
We are pleased to offer you the following proposal: 
 
Documents 
 Drawings dated: 6/3/2025 
 Specifications on drawings 
 We have seen no addendum  
 
Scope of Work 
 
 Light Fixtures and branch circuiting 
 Lighting control as shown on the drawings 
 Switchgear  
 Devices and branch circuitry, branch underground installed by standard trenching methods 
 Breakouts are for accounting purposes only 
 Per plans and specifications 
 Proposal good for 10 days 
 
Exclusions 
 
 Utility company charges 
 Utility and switchgear feeders not shown and not included 
 Underground boring 
 All sleeves, conduit across roads are by others 
 Not responsible for sleeve or conduit condition across roads or other areas 
 All concrete bases for light fixtures and switchgear equipment are by others  
 Sales Taxes on materials 
 Traffic control, permits & barricades 
 Participation in a LEEDS type program 
 Hoisting or lifting 
 Furnishing or installation of access doors 
 Cutting or patching of concrete, masonry, brick, sheetrock, plaster, etc 
 Placing or forming of concrete  
Miller Road Landscape Improvements: 
Lower Buckeye - Pima Street Phase I 
Contract No. 2025088, Delivery Order #2, Change Order #1
5
HITT Contracting, Inc. 
(REV. 6.23.25)

Painting or priming of any kind 
 Civil engineering and layout of concrete pole bases or concrete pads. 
 Warranty of existing electrical work 
 Payment and performance bond 
 Rock excavation, if encountered 
 Spoil removal from site 
 Overtime charges 
 Telephone, computer, or data cabling 
 Fire alarm system, raceway, or wiring 
 Temperature control and interlock wiring 
 Loose motor starters for equipment furnished by others 
 Patching of concrete for floor boxes 
 Roof Jacks 
 Trash removal from site (however, trash will be deposited in GC's dumpster) 
 
 
Base Bid 
 
 
 
 
 
 
 
            $214,500 
 
(1) Power Pedestal, Conduit, wire for (2) irrigation controller 
 
            $25,600 
Does not include Primary/Secondary conduit, wire for Utility 
Estimated lead time for pedestal is 5-7 weeks 
(1) Power Pedestal expedite fee adder  6-8 weeks                                                    $2,000 
 
 
Thank you for the opportunity to provide a proposal for this project and please do not hesitate to 
call me if you have any questions or concerns. 
 
Sincerely, 
 
 
 
Eric Myers 
Estimator 
541-292-3894 
ericm@teklineservices.com 
 
Miller Road Landscape Improvements: 
Lower Buckeye - Pima Street Phase I 
Contract No. 2025088, Delivery Order #2, Change Order #1
6
HITT Contracting, Inc. 
(REV. 6.23.25)