Downtown String Light Pilot Project Presentation.pptx

City of Buckeye — Regular Council Meeting (2026-05-19)

View PDF Meeting page

Extracted text (via pymupdf) 774 characters
Downtown String 
Light Project
Amy Murray, Public Works Director
May 19, 2026
1

Downtown Specific Area Plan (DSAP) 
Goals
Alignment with DSAP Goals
• Enhance visual appeal
• Create a welcoming 
atmosphere
Improved Ambience and Safety
• Enhance ambient light 
levels 
• Enhance nighttime 
visibility
2

New Infrastructure
3
•
Limitations of 
Existing Poles
•
Aesthetic and Safety 
Considerations
•
Clearance Variance 
Approval
•
Structural Integrity

Projected Timeline
Secure engineering firm
May 
2026
Design finalized; materials ordered
August 2026
Product/material delivery
February 2027
Begin installation 
March 2027
Project finalized
June 
2027