Downtown String Light Pilot Project Presentation.pptx
Extracted text (via pymupdf)
774 characters
Downtown String Light Project Amy Murray, Public Works Director May 19, 2026 1 Downtown Specific Area Plan (DSAP) Goals Alignment with DSAP Goals • Enhance visual appeal • Create a welcoming atmosphere Improved Ambience and Safety • Enhance ambient light levels • Enhance nighttime visibility 2 New Infrastructure 3 • Limitations of Existing Poles • Aesthetic and Safety Considerations • Clearance Variance Approval • Structural Integrity Projected Timeline Secure engineering firm May 2026 Design finalized; materials ordered August 2026 Product/material delivery February 2027 Begin installation March 2027 Project finalized June 2027 4 Summary and Recommendation Recommend approval of budget alignment and design of the downtown string light project 5