PROFESSIONAL SERVICES AGREEMENT
BETWEEN
THE CITY OF BUCKEYE
AND
LJA ENGINEERING, INC.
CONTRACT NO. 32500002
CHANGE ORDER #2
THIS CHANGE ORDER #2
is entered into as of ________________,
between the City of Buckeye, an Arizona municipal corporation
LJA Engineering,
Inc., a Texas corporation (the
). This Change Order modifies certain sections of
Contract No. 32500002
Agreement , with those sections not expressly modified remaining
in full effect pursuant to their terms.
RECITALS:
The City and Consultant entered into Contract No. 32500002 dated June 17, 2025. Pursuant to
which Consultant was to provide Program and Project Management Services with an expiration
date of June 30, 2026, and a not-to-exceed amount of $875,480.00.
Thereafter, Change Order #1 to Contract No. 32500002 increased the total not-to-exceed amount
by $74,500.00, from $875,480.00 to $949,980.00, and incorporated additional services into the
Scope of Work and Proposal, which was entered into as of February 25, 2026.
CONTRACT CHANGES:
1.
Section 2 Scope of Work and Exhibit A of the Original Agreement Proposal,
are amended to incorporate the additional services set forth in Exhibit 1 of Change Order #2.
2.
Section 3 Compensation, is amended by increasing the total not-to-exceed
amount by $87,500.00, from $949,980.00 to $1,037,480.00.
ADDITIONAL PROVISIONS:
Except as amended herein, all provisions of the Agreement remain in full force and effect.
In the event of any conflict or discrepancy between the terms of this Change Order, the
Agreement, and any other contract documents, the documents shall govern in that order.
This Change Order may be canceled pursuant to the provisions of A.R.S. § 38-511.
[SIGNATURE PAGE TO FOLLOW]
Program and Project Management Services
Contract No. 32500002, Change Order #2
LJA Engineering, Inc.
1
(REV. 6.23.25)
IN WITNESS WHEREOF, the parties hereto have executed this Change Order as of the date
first set forth above.
CITY:
CONSULTANT:
THE CITY OF BUCKEYE,
LJA ENGINEERING, INC.,
an Arizona municipal corporation
a Texas corporation
By:
Doug Sandstrom, City Manager
Its:
ATTEST:
Lucinda Aja, City Clerk
RECOMMENDED:
Rob Roach, Grant Program and
Procurement Manager
APPROVED AS TO FORM:
Tosca Henry, City Attorney
Program and Project Management Services
Contract No. 32500002, Change Order #2
LJA Engineering, Inc.
2
(REV. 6.23.25)
Exhibit 1
Program and Project Management Services
Contract No. 32500002, Change Order #2
LJA Engineering, Inc.
3
(REV. 6.23.25)
October 20, 2025
CHANGE ORDER 1
Mr. Jim Shano, PE
Program Management Office Director
City of Buckeye
945 N. 215th St. Suite 137
Buckeye, Arizona 85326
Re:
CIP Development, Durango Street Miller Road to Yuma Roadway Improvements
City of Buckeye
LJA Project No. AZ3450-1207CO01
LJA Proposal No. 25-44637CO01
Professional Services Agreement: 32500002, June 17, 2025
Dear Mr. Shano,
LJA Engineering, Inc. (LJA) is pleased to submit this Scope of Work (SOW) for a Change Order to the
Capital Improvement Program (CIP) Program and Project Management Services. This includes
providing a Project Manager with Construction Management expertise. Our proposed services and
corresponding fees align in accordance with the Professional Services Agreement (PSA) between the
City of Buckeye and LJA Engineering, Inc., dated June 17, 2025.
Our proposed team is comprised of highly experienced professionals with diverse expertise in
construction management, project leadership, and technical oversight. Each member brings a proven
track record of successfully delivering complex infrastructure and development projects on time and
within budget. Together, they provide a comprehensive blend of strategic vision, hands-on
management, and technical proficiency to ensure the successful execution of the City of Buckeye’s
Capital Improvement Program.
KEY PERSONNEL
Anthony Sumner, MBA, Vice President | 25 Years’ Experience
Mr. Sumner, a founding member of Sandbox Development Consultants (now part of LJA), brings over
25 years of experience in construction management and project leadership for large-scale
infrastructure and residential developments. He excels in managing complex projects involving
coordination with multiple stakeholders, development agreements, and utility coordination to ensure
smooth project execution. Notably, Mr. Sumner led entitlement and construction coordination efforts
on the 1,172-lot Tortosa South master-planned community, successfully managing joint development
agreements and extensive utility restorations. His expertise also includes overseeing multi-party joint
development agreements and managing public bidding processes for major infrastructure projects
throughout the Phoenix metropolitan area. With deep knowledge of budgeting, scheduling, and
feasibility, Mr. Sumner leverages strong industry relationships to ensure projects stay on schedule and
within budget.
Program and Project Management Services
Contract No. 32500002, Change Order #2
LJA Engineering, Inc.
4
(REV. 6.23.25)
Art Nehf, Director | 35 Years’ Experience
Art Nehf brings over 35 years of extensive experience in construction management and development
oversight for large-scale residential and commercial projects. He has successfully led planning,
engineering, permitting, and construction efforts for major master-planned communities including
Verrado, Kukuiula, DC Ranch, and Pebble Creek. Art’s expertise includes managing construction
schedules, coordinating subcontractors, ensuring regulatory compliance, and facilitating timely
infrastructure delivery to keep complex developments on track. His leadership and strategic approach
have been instrumental in the successful execution of multiple high-profile projects in Arizona and
Hawaii.
Rod Luker, Senior Project Manager | 28 Years’ Experience
Rod is highly skilled in managing comprehensive project documentation, including RFIs, submittals,
inspection reports, daily logs, and closeout records. He excels at coordinating contractors, utilities,
inspectors, and public stakeholders to optimize logistics, sequencing, and communication throughout
all project phases. Rod provides precise technical guidance to project managers, ensuring rigorous
quality assurance, regulatory compliance, and seamless integration of as-built data into GIS systems.
Known for his strong field presence and deep technical expertise, Rod anticipates challenges
proactively while maintaining alignment with the overall project objectives. His consistent track record
includes delivering projects on time and within budget. Rod holds a bachelor’s degree in business
management and possesses a General Engineering license in Arizona, as well as General
Commercial and Residential licenses in Arizona, New Mexico, and Utah.
Ryan Muncey, Project Manager | 10 Years’ Experience
Ryan brings valuable prior experience from Meritage Homes and GTIS, a build-to-rent developer,
where he successfully managed numerous projects at both vertical and horizontal stages. He is well-
versed in working within active municipal environments, including projects in the City of Buckeye such
as Floreo at Teravalis. Ryan applies strong construction management expertise through hands-on
oversight of contractor coordination, site logistics, and project sequencing to maintain efficient and
orderly workflows.
He is proficient in reviewing contractor pay applications by conducting thorough field verification of
installed quantities and providing well-informed recommendations to the Program Manager.
Maintaining a consistent daily field presence, Ryan monitors quality, compliance, and contractor
performance to ensure all work meets contract requirements. His capabilities extend to effective
contractor schedule management, risk identification, and providing guidance to keep projects on track.
Ryan also manages critical project documentation—including RFIs, submittals, change orders, and
closeout records—submitting these for Program Manager approval while maintaining accurate logs.
He coordinates closely with utilities, inspectors, municipal departments, and public communications to
support smooth project execution.
Furthermore, Ryan ensures that as-built drawings are accurate and integrated into GIS, updates
project schedules and budgets for Program Manager concurrence, and systematically uploads all
inspection and project documentation into project management platforms such as Sensei and
OneDrive. His thorough approach and technical acumen significantly contribute to the successful
delivery of projects on time and within budget.
Program and Project Management Services
Contract No. 32500002, Change Order #2
LJA Engineering, Inc.
5
(REV. 6.23.25)
SCOPE OF WORK
715 – Municipality Consultation
Durango Street/ Miller to Yuma
Plans prepared by Kimley Horn Engineers
Unapproved Plans dated 06/05/25 prepared by Joel Varner, P.E.
Project Management:
LJA proposes to provide Project Management consultation with Construction Management expertise
to support the City of Buckeye’s CIP. Services include:
Task
Project Manager (PM)
Construction Manager
(CM)
City Inspector
Budget Authority / Pay
Applications
Retains control of budgets,
invoices, and POs
Reviews and monitors
budget and change
requests. Makes
recommendations to PM on
budget related items
Complies daily quantities in
logs
Contract Administration
Manages
consultant/contractor
contracts at owner level
Oversees contractor
coordination and site
logistics
Verifies contractor
compliance with specs and
standards
Schedule Management
Approves master project
schedule and changes
Tracks contractor
schedules; reviews monthly
updates to CPM; Reviews
weekly 3 week look ahead
schedule. flags risks
Policy & Compliance
Ensures City procurement,
CIP, and reporting
compliance
Ensures field activities meet
codes and safety standards
Decision-Making
Final authority on scope,
schedule, and budget
Provides technical
recommendations for PM
decisions
Provides field observations
to inform CM/PM
Reporting
Provides updates to City
leadership and council
Prepares documentation
and submittal logs, ; RFI’s,
RFP’s, Allowance Tracking,
Submittals
Provides daily inspection
reports to CM
On-Site Oversight
Weekly field presence
Field presence 3 site visits
per week
Daily field presence
Contractor Coordination
Approves GC macro-level
sequencing, logistics, and
communication as required
Manages GC for
sequencing, logistics, and
communication
Confirms work follows
plans/specs
Program and Project Management Services
Contract No. 32500002, Change Order #2
LJA Engineering, Inc.
6
(REV. 6.23.25)
Task
Project Manager (PM)
Construction Manager
(CM)
City Inspector
Quality Assurance
Provides final acceptance of
project
Monitors compliance with
specifications and project
documentation, verifies
with engineer of record for
any clarifications.
Verifies workmanship and
material testing
Change Order Review
Approves or rejects
Reviews scope, schedule
and budget requests;
provides PM
documentation and
recommendation
Provides field input on
validity of claims
Issue Resolution
Approves resolution
Manages RFIs, submittals,
and conflicts, coordinates
with engineer of record and
all applicable parties to
each issue. Reviews issues,
investigates and collects all
pertinent data, and makes a
recommendation for
resolution to the PM
Identifies field issues and
communicates to CM
Documentation
Approves project
documents
Maintains logs, reports,
submittal logs, RFIs, change
orders, closeout records;
submits for PM approval in
Sensei
Provides daily inspection
logs/photos; final city field
acceptance
Weekly Construction
Meetings
Attend meeting, provide
update from Agency
Lead weekly meetings,
prepare agenda and
meeting minutes
Attend meeting provide
update from field
Stakeholder Coordination
High-level coordination
with
leadership/stakeholders
Coordinates utilities,
inspectors, departments,
public response
Coordinates with utilities
and contractors as required
As-Built Coordination
Reviews final acceptance
Ensures contractor as-builts
are accurate and integrated
into GIS
Documents field changes
and reviews changes to
contractor field red lines
Sensei Tracking
Oversees reporting
database
Inputs schedule and budget
updates for PM
concurrence; uploads
inspection, logs, RFIs,
submittals, closeout and
other documentation to
OneDrive
Provides inspection data to
CM
Program and Project Management Services
Contract No. 32500002, Change Order #2
LJA Engineering, Inc.
7
(REV. 6.23.25)
Municipal Consulting Fee is a Fixed Fee (FF) for a Seven (7) month duration at $81,000
Mileage reimbursement will be billed on a Fixed Fee (FF) basis as authorized by the Client, $6,500
for the seven (7) month period.
COMPENSATION SUMMARY
LJA proposes to provide the scope of work described above on a Fixed Fee (FF) basis for 7 months.
Phase
Description
Fee Basis
Fee
715
Municipal Consulting
FF
81,000
Z99
Reimbursable Expenses
FF
$6,500
TOTAL
$87,500
SCHEDULE
This Scope of Work will be performed from January 15, 2026, through August 15, 2026. Monthly
billing is anticipated at approximately $12,500 per month.
We appreciate the opportunity to submit this proposal and look forward to the possibility of working
with you on this project. If you have any questions or need further information, please feel free to
contact Riley Quinlan at (650) 704-0541 or Anthony Sumner at (480) 703-8784.
Sincerely,
Proposal Accepted By:
LJA ENGINEERING, INC.
CITY OF BUCKEYE
Riley Quinlan, PE
By:
Senior Project Manager
Name:
Title:
Anthony Sumner
Vice President
Date:
RQ/AS/jc
Program and Project Management Services
Contract No. 32500002, Change Order #2
LJA Engineering, Inc.
8