1 
 
Benefit Cost Analysis Narrative for Capital Construction Grants 
 
The design is 30% or more complete and the budget contains contingencies and scheduling 
considerations. 
 
Please see the “BCA Calculations”  Excel spreadsheet for details and calculations. 
The Watson Road project costs by category are as follows: 
Planning and Design 
$  2,500,000 
Land Acquisition (ROW) 
$ 14,000,000 
Construction 
$ 45,360,000 
Contingency (5%) 
$  3,093,000 
Total Cost 
$ 64,953,000 
 
The project is designated as urban and 100% of the cost of the project and benefits are in 
historically disadvantaged community census tracts 507.01 and 507.02. In all likelihood, a 
project this large would go unfunded and not be constructed without this grant. Regarding cost 
overruns, Buckeye has built in a 5% contingency into the budget. Any cost overruns beyond the 
budget and contingency would require an alternative source of funding. Since the maximum 
BUILD grant is $25,000,000, Buckeye will need to fund $39,953,000 of the budget from the 
General Fund, which Buckeye is prepared to fund if awarded, subject to final Buckeye City 
Council approval. 
 
Buckeye has used the US DOT BCA spreadsheet to calculate the BCR. 
The project is estimated to commence in 2027 and be completed within 36 months, sometime in 
2029 or 2030. The capital cost is planned at $64,953,000, with $25,000,000 funded by federal 
funds and $39,953,000 to be funded by the City of Buckeye. For BCR purposes, the operational 
period is 20 years. Safety is calculated at the value of crashes with possible injury at the 
estimated number of Watson Road accidents based on historical values. Travel times were 
calculated at the All-Purpose value for the estimated number of vehicles of 3,000 over the 
expected 250 trips per year. Vehicle operating cost savings are based on the light-duty vehicle 
value for the 5.6 miles to be reduced by the project for the number of 3,000 vehicles for the 250 
trips incurred. Emissions reduction was calculated at the All-Vehicles rate for 3,000 vehicles at 
250 trips per year for the 5.6 miles reduced. Other avoided externalities include the All Vehicles 
- All Locations value for the 3,000 vehicles for 250 trips per year. Health benefits were 
calculated for cycling for an estimated round trip of 4 miles for 250 trips per annum. 
The final results ended with the benefits outweighing the costs by 5.45 to 1. 
 
Below, please find the following additional information regarding this project. 
Based upon the Arizona Deptartment of Transportation (ADOT) 2023 crash facts, the cost of all 
accidents in Arizona was $21,638,265,446. There were 122,247 accidents, which equates to 
$177,004 per accident. Applying that to Watson Road accidents of 147 in 2023 equates to

2 
 
$26,019,657 cost of accidents ($177,004 per accident x 147 accidents = $26,019,657). Therefore, 
there is a cost benefit to reducing and eliminating accidents, and of course, there is the 
unquantifiable benefit of reducing or eliminating injuries and fatalities. Buckeye aims to 
eliminate fatalities and reduce injuries by 25%, while reducing accidents by 25%, thereby 
reducing the cost of accidents by $6,504,914. Additionally, separating traffic from the railroad 
tracks, by way of the overpass, eliminates train versus vehicle/pedestrian accidents. 
 
North of the railroad tracks and irrigation canal along the west side of Watson Road is a 
Walmart warehouse distribution center with approximately 1,500 employees. Ross Dress for 
Less, a distribution center on the east side of Watson across from the Walmart distribution 
center has an estimated 1,300 new jobs. Additionally, it is expected that potential new 
development will provide at least 1,300 additional new jobs. These 4,100 jobs, at minimum 
wage of $15.15 per hour wage, will provide $128 million annually in economic benefit to this 
area (4100 x 15.15 x 2080).  
 
The existing available route from Watson Road and Southern Avenue to Watson Road and 
Maricopa County Route 85 (MC85) is 3.5 miles because there is no pathway directly down 
Watson Road from Southern Avenue to MC85 due to barriers to connectivity of railroad tracks 
and an irrigation canal. Once the barriers overpass of 0.7 miles is completed, the distance of 
travel will be reduced from 3.5 miles to 0.7 miles. The proposed multi-modal improvements 
make the new roadway accessible to vehicular and non-vehicular traffic. The proposed 
improvements reduce the distance by 2.8 miles and reduce travel distance and travel time, 
thereby reducing greenhouse emissions, decreasing reliance on automobiles, providing direct 
access to employment, and benefiting the disadvantaged community. The average car produces 
348 grams of carbon dioxide (CO2) emissions per mile, and by reducing daily work roundtrips 
by 5.6 miles (2.8 miles each way) will reduce CO2 emissions by 487,200 grams or 1,074 pounds 
(5.6 miles per round trip x 348 grams x 250 round trips per year) in a single year for just one car. 
If the average daily traffic were only 3,000 vehicles, that would reduce CO2 emissions by over 3 
million pounds per year. There are over 4,000 jobs available along this route, therefore, daily 
traffic counts of 3,000 per day are reasonable. The projected daily volumes on Watson Road are 
over 23,000 vehicles for 2040. The construction of the project would reduce the traffic volumes 
on adjacent congested roadways with a potential CO2 reduction of over 20 million pounds per 
year, thus providing a significant health benefit to this disadvantaged community in terms of air 
quality and reduction in greenhouse gas emissions, improving environmental conditions and 
enhancing sustainability. The project will provide high quality choices of lower-carbon 
transportation such as pedestrian walking, rolling, bicycling, scooters, and other modes of travel 
that reduce greenhouse gas emissions and encourage active life activities. The project also 
provides shorter trip distances for access from neighborhoods to retail and business centers. 
According to the Department of Transportation, installing Intelligent Transportation Systems 
(ITS) along Watson Road will help reduce travel time and make travel safer for non-commercial 
and commercial traffic. ITS provides connectivity between traffic signals along Watson Road to 
allow Signal and Traffic Engineering staff the ability to monitor and adjust signal operations as 
necessary for efficiency, reduced travel and wait times, and safety. A secondary benefit to the 
ITS system is that it provides a connection from the City’s Public Works Facility (home of the 
traffic signal staff) to the City’s ever growing traffic signal system and the ability to monitor and 
adjust traffic signal timing as needed during peak hours or incidents to minimize traffic delays, 
ensure safety, and reduce travel times and emissions.

3 
 
This project will provide new multi-modal pathways for vehicular, pedestrian, handicap, and 
bicycle traffic. It will also connect to other pedestrian/bicycle/rolling only pathways along the 
irrigation canal. 
 
The following is a list of the basic scope of work. 
• 
Survey and Identification of utilities within the project corridor and verifying if prior 
rights exist. Topographic survey of project limits. 
• 
Establishment of horizontal and vertical geometry. 
• 
Identification of right-of-way (ROW) needs. 
• 
Further development of 30% conceptual plans for the ultimate cross section of Watson 
Road. 
• 
Development of probable costs for ultimate and interim cross section, including ROW, 
utility, final design and construction administration costs. 
• 
Conceptual structural design. 
• 
Monthly project meetings with the City and other interested parties. 
• 
Prepare traffic impact analysis. 
• 
Environmental assessment and historic cultural review. 
• 
Coordination with Buckeye Irrigation District for an at-grade bridge over the canal. 
• 
Coordination with the Union Pacific Railroad Company for an at-grade bridge over the 
railroad tracks. 
• 
Coordination with APS for the 96” Cooling Line located on the north side of the BID 
Canal. 
• 
Coordination with Maricopa County Department of Transportation (MCDOT) as they 
have jurisdictional control of MC 85. 
• 
Coordination with the adjacent property owners to ensure access is provided. 
• 
Identification of utilities within the project corridor and verifying if prior rights exist. 
• 
Traffic Impact Analysis. 
• 
Environmental clearances. 
 
The project consists of a final design, land purchase for right-of-way, and construction of a 
grade-separated multi-modal structure over an irrigation canal and railroad tracks and establish 
the vertical and horizontal alignment north and south of the canal and railroad tracks on Watson 
Road from Southern Ave. to MC85, Buckeye, Arizona. This includes a 16-inch water line, a 
traffic signal, ITS conduit, pull box and fiber optics, and any other sleeves for utilities. 
 
Environmental Sustainability 
 
ETC Explorer - State Results | USDOT Equitable Transportation Community (ETC) Explorer 
(arcgis.com)

4 
 
The above ETC tool for Census Tracts 507.01 and 507.02 indicates that the disadvantaged 
community is in the 95th percentile for environmental burden. The existing available route from 
Watson Road and Southern Avenue to Watson Road and MC85 is 3.5 miles because there is no 
pathway directly down Watson Road from Southern Avenue to MC85 due to barriers to 
connectivity of railroad tracks and an irrigation canal. Once the barriers overpass of 0.7 miles is 
completed, the distance of travel will be reduced from 3.5 miles to 0.7 miles. The proposed 
multi-modal improvements make the new roadway accessible to vehicular and non-vehicular 
traffic. The proposed improvements reduce the distance by 2.8 miles and reduce travel distance 
and travel time, thereby reducing greenhouse emissions, decreasing reliance on automobiles, 
providing direct access to employment, and benefiting the disadvantaged community. The 
average car produces 348 grams of carbon dioxide (CO2) emissions per mile and by reducing 
daily work roundtrips by 5.6 miles (2.8 miles each way) will reduce CO2 emissions by 487,200 
grams or 1,074 pounds (5.6 miles per round trip x 348 grams x 250 round trips per year) in a 
single year for just one car. If the average daily traffic were only 3,000 vehicles, that would 
reduce CO2 emissions by over 3 million pounds per year. There are over 4,000 jobs available 
along this route, therefore, daily traffic counts of 3,000 per day are reasonable. The projected 
daily volumes on Watson Road are over 23,000 vehicles for 2040. The construction of the 
project would reduce the traffic volumes on adjacent congested roadways with a potential CO2 
reduction of over 20 million pounds per year, thus providing a significant health benefit to this 
disadvantaged community as to air quality and reduction in greenhouse gas emissions, improving 
environmental conditions and enhancing sustainability. The project will provide high quality 
choices of lower-carbon transportation such as pedestrian walking, rolling, bicycling, scooters, 
and other modes of travel that reduce greenhouse gas emissions and encourage active life 
activities. The project also provides shorter trip distances for access from neighborhoods to retail 
and business centers. 
According to the Department of Transportation, installing Intelligent Transportation Systems 
(ITS) along Watson Road will help reduce travel time and make travel safer for non-commercial 
and commercial traffic. ITS provides connectivity between traffic signals along Watson Road to 
allow Signal and Traffic Engineering staff the ability to monitor and adjust signal operations as 
necessary for efficiency, reduced travel and wait times, and safety. A secondary benefit to the 
ITS system is that it provides a connection from the City’s Public Works Facility (home of the 
traffic signal staff) to the City’s ever-growing traffic signal system and the ability to monitor and 
adjust traffic signal timing as needed during peak hours or incidents to minimize traffic delays 
and reduce travel times and emissions. 
As per the below mapping tool, improved health conditions such as asthma and life expectancy 
can be expected when improving the air quality.

5 
 
Land use will include green spaces in the design to provide for nature-based storm water drainage, 
filtering of pollutants, and reduction of surface temperatures. These basins would also function as a park 
and open green space and utilized for sports fields for community sports programs. Native plants are 
incorporated into the planned design. Green space can improve mental health by reducing stress, 
depression, and anxiety, and promoting calm, improved mood, and relaxation. 
The below maps illustrate the ozone percentile for the proposed Watson Road project, which is 
currently within the 81st percentile and the Particulate Matter percentile which is currently within 
the 66th percentile, according to the EPA’s EJScreen.

6 
 
 
 
Quality of Life 
This project will reduce vehicle dependence due to the multi-modal traffic accommodation and is 
located within and serves an underserved community. The new facility improves public health as 
it promotes pedestrian walking, biking, and rolling via the dedicated non-vehicular travel lanes 
and sidewalks (pathways). These non-vehicular pathways also connect to other pedestrian 
pathways which lead to various destinations within the City of Buckeye. The proposed project 
improves access to daily destinations like jobs, healthcare, grocery stores, schools, places of 
worship, recreation, and parks by reducing the miles driven from 3.5 miles to 0.7 miles, thereby 
reducing the roundtrip travel distance by 5.6 miles. Additionally, quality of life and health are 
improved within this historically disadvantaged community by the expected reduction in vehicle 
emissions, as detailed earlier in this Merit Criteria discussion. It is anticipated that CO2 
emissions can be reduced by over 3 million pounds per year. The existing available route from 
Watson Road and Southern Avenue to Watson Road and MC85 is 3.5 miles because there is no 
pathway directly down Watson Road from Southern Avenue to MC 85 due to barriers to 
connectivity of railroad tracks and an irrigation canal. Once the barriers overpass of 0.7 miles is 
completed, the distance of travel will be reduced from 3.5 miles to 0.7 miles. The proposed 
multi-modal improvements make the new roadway accessible to vehicular and non-vehicular 
traffic. The proposed improvements reduce the distance by 2.8 miles and reduce travel distance 
and travel time, thereby reducing greenhouse emissions, decreasing reliance on automobiles, 
providing direct access to employment, and benefiting the disadvantaged community. The 
average car produces 348 grams of carbon dioxide (CO2) emissions per mile and by reducing 
daily work roundtrips by 5.6 miles (2.8 miles each way) will reduce CO2 emissions by 487,200 
grams or 1,074 pounds (5.6 miles per round trip x 348 grams x 250 round trips per year) in a 
single year for just one car. If the average daily traffic were only 3,000 vehicles, that would 
reduce CO2 emissions by over 3 million pounds per year. Thereby improving the neighborhood 
quality of life. 
 
Transportation becomes more affordable due to the ability to use free non-vehicular modes of 
transportation. Also, with the shorter distance and shorter travel time, use of vehicles becomes 
more affordable. Buckeye is installing a new bus stop between this improvement and the 
downtown, providing the community with more affordable transportation and more choices of 
transportation. 
 
Mobility and Community Connectivity 
The project is in coordination with the City Transportation Master Plan to consider 
environmental sustainability and resiliency, stormwater drainage, and flood risk management. 
The completed project will benefit the community by removing access barriers and significantly 
improving connectivity and safety. The project will remove the physical barriers by constructing 
a multi-modal bridge over connectivity barriers, which are an irrigation canal and railroad tracks, 
using community and stakeholder engagement for the benefit of Downtown Buckeye and a 
disadvantaged community. The bridge will be ADA accessible and connect Downtown Buckeye 
and the disadvantaged community to employment and economic prosperity by means of vehicle, 
pedestrian walking, bicycling, and rolling. The mitigation of the burdening transportation facility 
will also improve economic opportunities, air pollution, reduce environmental harm, and 
improve community accessibility and safety. The project will reduce the distance from 3.5 miles

7 
 
to 0.7 miles from Watson Road to MC 85, a major cross-town roadway connecting downtown 
neighborhoods to the employers just north of the existing barriers. These employers currently 
employ over 4,000 people. 
The average car produces 348 grams of carbon dioxide (CO2) emissions per mile and by 
reducing daily work roundtrip distances by 5.6 miles (2.8 miles each way) will reduce CO2 
emissions by 487,200 grams or 1,074 pounds (5.6 miles per round trip x 348 grams x 250 round 
trips per year) in a single year for just one car. If the average daily traffic were only 3,000 
vehicles, that would 
reduce CO2 emissions by over 3 million pounds per year. The new multi-modal direct access 
over the existing barriers will improve job prospects and allow for access to employment by 
means other than vehicular. The reduction in miles traveled, as a result of the overpass 
connection, will decrease vehicle emissions and will equitably distribute the benefits of better air 
quality, improving the neighborhood environmental and health conditions. 
 
Located at a portion of Watson Road are some railroad tracks and an irrigation canal which cuts 
off Watson Road from the southernmost section of Watson Road just north of MC85. These two 
obstacles create a barrier to the surrounding disadvantaged community and precludes direct 
access from MC 85 to Watson Road north of these two barriers. 
 
According to the DOT Grant Project Location Verification mapping tool, this entire project is in 
a rural area that has been designated as an historically disadvantaged community census tracts 
507.01 and 507.02. The railroad tracks and the irrigation canal are an existing barrier in this 
community that cut off residents from freely traveling back and forth between north and south, 
preventing direct access to employment and community services. 
 
North of the railroad tracks and irrigation canal on the west side of Watson Road is a Walmart 
warehouse distribution center (1,500 employees). Ross Dress for Less is building a distribution 
center on the east side of Watson across from the Walmart distribution center. Construction of 
the Ross Dress for Less distribution center is expected to be completed soon and will provide an 
estimated 1,300 new jobs. Additionally, it is expected that potential new development will 
provide at least 1,300 additional new jobs. These 4,100 jobs, at $15.15 per hour wage, will 
provide 
$128 million annually in economic benefit to this area. 
 
The railroad tracks and canal create a barrier to accessing these workplaces, as well as recreation 
areas, schools, banks, post office, social services, community services, health services, and 
shopping. The extra time and distance it takes vehicles to travel around these barriers creates 
higher levels of pollution to accumulate in the area. Non-vehicular travel around these barriers is 
difficult to impossible. Construction of a multi-modal overpass over the railroad tracks and 
irrigation canal, and completion of the road connecting Watson Road from Southern Avenue to 
MC85 will accommodate vehicular traffic, pedestrians, handicaps, and bicyclists. Dedicated 
bicycle paths and sidewalks for pedestrians will provide pathways for non-vehicular mobility and 
community connectivity. 
 
Using the EPA’s EJScreen geospatial tool, the ozone reading at this area is in the 81st percentile 
compared to the United States. The project will reduce the driving distance from 3.5 miles to 0.7 
miles. The goal is to reduce travel times, reduce distance, reduce greenhouse gas emissions, and

8 
 
provide safe pathways for non-vehicular pedestrian traffic. The completed project will benefit 
the community and provide equity by removing access disparities and significantly improving 
connectivity and safety. The new multi-modal direct access over the existing barriers will 
improve job prospects and allow for access to employment by means other than vehicular. The 
reduction in miles traveled, as a result of the overpass connection, will decrease vehicle 
emissions and will equitably distribute the benefits of better air quality, improving the 
neighborhood environmental and health conditions. 
Based upon the two below snippets from the U.S. Department of Transportation’s Equitable 
Transportation Community Tool (outlined in blue), between 3.6% and 8.6% of the downtown 
community households do not own a personal vehicle. The City is beginning the planning 
process of implementing a transit circulator for the portion of Buckeye south of Interstate 10 and 
east of SR 85 (the primary commercial and employment areas of the City, which includes this 
project and the disadvantaged community). Completing Watson Road between Southern Avenue 
and MC 85 and improving the Watson corridor will allow the transit circulator direct access from 
the residential areas of downtown Buckeye to the large employers. Bus stops are planned along 
Watson for the future bus circulator that will pick up non-vehicular travelers for transportation 
around the community. Dedicated bike paths provide mobility and community connectivity for 
non-vehicular pedestrian traffic. The project also provides the employment centers that have 
large shipping warehouses additional routing access for the volume of semi-tractor trucks that 
flow from the warehouses. These warehouses include Walmart, Ross Dress for Less, and 
Cardinal Glass, and others planned to build in the area. 
 
 
Buckeye has incorporated community participation by having several public meetings to discuss

9 
 
improvement plans. The bridge on Watson Road over the railroad tracks and the irrigation canal 
have been a highly desired infrastructure improvement by the community. 
According to the map below from the EPA’s EJScreen, the affected disadvantaged communities 
are currently within the 61st percentile in regards to Transportation Access Burden. Through this 
project, the City of Buckeye seeks to reduce the transportation access burden for the rural and 
disadvantaged downtown Buckeye residents. Vehicular and non-vehicular modes of travel will 
be able to utilize Watson Road, including public transit, thus reducing the transportation access 
burden. 
 
Economic Competitiveness and Opportunity 
The project improves multimodal freight mobility by providing the large warehouse centers that 
are located just north of the connectivity barriers, additional access to routes for the volume of 
semi-tractor trucks that flow from the warehouses. These warehouses ship goods nationwide. 
which include Walmart, Ross Dress for Less, and Cardinal Glass, and others planned to be built 
in the area. 
 
By removing the barriers caused by the railroad tracks and the irrigation canal, the project will 
open new, good paying jobs to the residents of the Buckeye disadvantaged community. These 
jobs include the Walmart distribution center with an estimated 1,500 employees, Cardinal Glass, 
with an estimate 200+ employees next to Walmart, and Ross Dress for Less distribution center, 
across the road from Walmart with an estimated 1,300 new jobs. Walmart provides workforce 
development programs for its employees. Ross provides tuition assistance to vocational, 
undergraduate, and graduate programs for its employees. These programs will further reduce the 
hardships faced by those in the disadvantaged community and improve the quality of life. The 
increased access to employment promotes wealth building for the local residents. The project 
also encourages long-term economic growth by making the area more warehouse friendly by 
providing multiple accessible shipping routes. The shorter distance to travel to access the 
employment center aids in the promotion of local hiring preferences. 
Buckeye is planning to use Project Labor Agreements, when possible, to ensure fair wages will 
be paid to workers and to encourage that underrepresented and local workers will be hired for 
project work. This project will be open for bid to all qualified contractors, including Minority 
Business Enterprises, Minority Owned Businesses, Woman Owned Businesses, and Veteran 
Owned Businesses. The completed project will support equitable commercial and mixed-income

10 
 
residential development. 
 
The image below illustrates the unemployment rate percentile for the affected areas, with much 
of the downtown Buckeye area’s unemployment rate percentile being within the 80th percentile 
or higher. The Watson Road project seeks to reduce the unemployment percentiles by improving 
access to employers. 
 
 
In downtown Buckeye, a new apartment complex is being built 2.4 miles west of Watson Road, 
called Solana Villas, which will have 200 apartments available for rent. According to 
census.gov, the average household is comprised of 3.16 persons, thus these 200 new apartments 
will house approximately 632 people and create a greater need for the connection of Watson 
Road since it is an arterial roadway which will connect to good paying jobs. Additionally, 
approximately 1.5 miles southwest of Watson Road is another townhome-style residential 
development currently being built, called Lanai Living, which will have a total of 444 units 
available for rent. Based on census.gov, the average household is comprised of 3.16 persons, 
thus these 444 new townhomes will house approximately 1,403 people and create a greater need 
for the connection of Watson Road. Many of these new residents of the area will likely traverse 
via Watson Road since it is an arterial roadway connecting users to Interstate-10 which runs east-
west and is approximately 32 west of Phoenix. Additionally, the connection of Watson Road will 
eliminate the current barrier for first responders as they are unable to quickly respond to calls for 
service since Watson Road is not a through street at MC 85. Connecting Watson Road will 
alleviate traffic in Downtown Buckeye and surrounding areas as it will be one of the main 
arterial roadways connecting downtown Buckeye. The only other arterial roadway in Downtown 
Buckeye is Miller Road, which will not have the capacity to accommodate commuters in the near 
future, due to the rapid growth that Buckeye is experiencing. 
State of Good Repair 
Buckeye plans to use climate friendly materials such as cool pavement, adaptive street lighting, 
and low-carbon construction materials. Cool pavement reflects more solar heat and helps to 
mitigate heat island effects. Cool pavement can also reduce stormwater runoff, improve safety by 
reducing water spray from moving vehicles, and improve night visibility by reducing lighting

11 
 
requirements. Adaptive street lighting regulates the light intensity based on sunrise and sunset 
times and weather situations. Low-carbon construction materials improve environmental 
sustainability and potentially extend the life of roadway surface.

12 
 
The proposed project satisfies Complete Streets approach by completing this new infrastructure 
on Watson Road, overpassing the railroad tracks and the irrigation canal, thereby creating new 
infrastructure in this remote community that will be maintained in a state of good repair, fixing 
an existing system vulnerability for this rural and underserved community. The City will be 
responsible for the on-going maintenance and state of good repair of this project post-
completion. 
 
Partnership and Collaboration 
The project will remove physical barriers by constructing a multi-modal bridge over connectivity 
barriers, which are an irrigation canal and railroad tracks, using community and stakeholder 
engagement for the benefit of Downtown Buckeye and a disadvantaged community. From 
December 2022 through 2024, periodic public meetings were held wherein the public reviewed 
various proposals regarding Buckeye revitalization. Present at the meeting were City staff, 
outside planning consultant Olsson Planning, and various community-based organizations, and 
residents of the community. One item that the public consistently requested was the Watson 
Road infrastructure improvements requested in this grant application. Additional community 
engagement will include, but not limited to, news releases, social media releases, further 
meetings with community-based organizations, and messages on the City website to ensure that 
considerations for underserved communities are meaningfully integrated throughout the lifecycle 
of the project. Buckeye is and will be coordinating with other types of projects such as economic 
development, commercial or residential development, power/electric infrastructure projects, and 
broadband and fiber deployment. Buckeye is also participating with a non-DOT Federal 
capacity-building program, Environmental Protection Agency’s Environmental Justice EPA 
Targeted Brownfields Assessment on a 40-acre parcel in an adjacent historically 
disadvantaged community census tract for Brownfields Assessment, to create a public trailhead, 
park, and wildlife riparian restoration in partnership with Arizona Forestry. 
 
Innovation 
Buckeye will be installing Intelligent Transportation Systems (ITS), which according to the 
Department of Transportation, is a national program, using computers and communications to 
make travel safer by providing travel information to give current, multi-modal information on 
travel conditions to guide choices on how, when, and where to travel. It also provides in-vehicle 
maps and automatic notification emergency services regarding serious accidents and their 
location. Intelligent commercial vehicle systems help public agencies improve safety by 
inspecting vehicles that need it most. The ITS system provides a connection from the City’s 
Public Works Facility (home of the traffic signal staff) to the City’s traffic signal system and the 
ability to monitor and adjust traffic signal timing as needed during peak hours or incidents, to 
minimize traffic delays and reduce travel times and emissions. Innovative Technologies will be 
employed to enhance the environment for electric, connected, and automated vehicles to improve 
the detection, mitigation, and documentation of safety risks. Buckeye will also use practices that 
facilitate accelerated project delivery such as single contractor design-build arrangements, 
congestion management, asset management, and long-term operations and maintenance. 
 
Buckeye plans to use climate friendly materials such as cool pavement, adaptive street lighting, 
and low-carbon construction materials. Cool pavement reflects more solar heat and helps to 
mitigate heat island effects. Cool pavement can also reduce stormwater runoff, improve safety by

13 
 
reducing water spray from moving vehicles, and improve night visibility by reducing lighting 
requirements. Adaptive street lighting regulates the light intensity based on sunrise and sunset 
times and weather situations. Low-carbon construction materials improve environmental 
sustainability and potentially extend the life of roadway surface. 
 
Buckeye anticipates that advanced digital construction management systems will be used to help 
manage the project to improve efficiency and safety. Additionally, accelerated bridge 
construction and digital as-builts are expected to be used to plan and design and review 
construction methods to reduce the time and effort.