4.I
CITY OF BUCKEYE
Regular Council Meeting
COUNCIL ACTION REPORT
MEETING DATE: 02/03/26
AGENDA ITEM: 4.I. PMO - CIP No.
109290 Gateway Enhancement Program
- Miller/Watson - Job Order Contract
Delivery Order #2 Brycon Corporation
DATE PREPARED: 02/03/26
DISTRICT NO.: 1 & 2
STAFF LIAISON: Rodrigo Nemi, Project Manager, rnemi@buckeyeaz.gov, (623)
204-8442
DEPARTMENT: Program Management
Office
AGENDA ITEM TYPE: Consent Agenda
Items / New Business
ACTION/MOTION: (This language identifies the formal motion to be made by the Council) 
Council to take action on Delivery Order No. 2 to Job Order Contract (JOC) No. 2025088 between the
City of Buckeye, an Arizona municipal corporation, and Brycon Corporation, a New Mexico corporation,
related to the construction services for Capital Improvement Program (CIP) Project No. 109290 Gateway
Enhancement Program - Miller/Watson; and authorize the City Manager to execute and deliver said
Delivery Order on behalf of the City of Buckeye.
SUMMARY
PROJECT DESCRIPTION:
This approval will allow the City Manager to authorize the necessary agreement to complete the
construction of Phase 2 of the landscape improvements, which includes all irrigation components,
plantings, water meters, and related work. 
Phase 1 of this project, not included in this request, was accomplished with Miller Road Expansion -
Durango to Lower Buckeye Road by installing the conduit in line with the ultimate design. Phase 3 will
complete Gateway Enhancement Standards.
BENEFITS:
The completion of Phase 2 of the landscape improvements will provide multiple benefits to the
community and the overall corridor. Bringing the Miller Road corridor closer to the City’s Gateway
Enhancement Standards will significantly improve aesthetics, create a cohesive and welcoming entry
experience, and support long-term community branding efforts. 
FUTURE ACTION:
Following completion of Phase 2, the City will proceed with soliciting and awarding any remaining
landscape or corridor enhancement work needed to fully build out the Gateway Enhancement vision for
both the Miller Road and Watson Road corridors. This may include additional planting, hardscape, or
aesthetic elements to complete the final design intent and ensure long-term corridor continuity.
FINANCIAL IMPACT STATEMENT:
The project is programmed in the CIP in Fiscal Year (FY2026). The total cost to complete the Work
under this Delivery Order shall not exceed $400,000.00, which is inclusive of the Proposal amount of
$388,050.07 and an Owner’s Allowance of $11,949.93.
Future costs for Phase 3 will be programmed for Construction in FY2027.

CURRENT FISCAL YEAR TOTAL COST:
The project is programmed in the CIP in Fiscal Year (FY2026). The total cost to complete the Work
under this Delivery Order shall not exceed $400,000.00, which is inclusive of the Proposal amount of
$388,050.07 and an Owner’s Allowance of $11,949.93.
Future cost for Phase 3 will be programmed for Construction in FY2027.
BUDGETED:
Yes
FISCAL YEAR:
FY2026
FUND/DEPARTMENT:
50213170-543254
Items related to a project or facility location must include an attached vicinity map for Council
Review.
ATTACHMENTS:
Vicinity Map
Contract No. 2025088 DO#2.pdf