JOB ORDER CONTRACT DELIVERY ORDER
BETWEEN
THE CITY OF BUCKEYE
AND
BRYCON CORPORATION
JOB ORDER CONTRACT NO. 2025088
DELIVERY ORDER #2
MILLER ROAD LANDSCAPE IMPROVEMENTS:
LOWER BUCKEYE PIMA STREET PHASE I
THIS DELIVERY ORDER #2
is entered into as of __________________,
between the CITY OF BUCKEYE
City , and Brycon
Corporation, a New Mexico corporation
This Delivery Order is subject to and
governed by the terms and conditions of Job Order Contract No. 2025088 between the City and
Contractor, dated September 3, 2024
.
ARTICLE 1
SCOPE OF WORK
The Contractor shall furnish all labor, materials, and equipment, as more fully set forth in the
Proposal, which is attached hereto as Exhibit A and incorporated herein by reference (the
, to complete the Miller Road Landscape Improvements: Lower Buckeye Pima Street
Phase I project
.
ARTICLE 2
SCHEDULE OF COMPLETION OF WORK
The Contractor shall commence work within ten (10) days from issuance by the City of a Notice
to Proceed, and shall complete the Work on or before eight (8) weeks from the effective date of
the Notice to Proceed. In view of the difficulty or impossibility of determining the City's damages
from delay, should the Contractor fail to achieve Substantial Completion with the above number
of calendar days, as may be extended by any City-approved Change Orders, the Contractor agrees
to pay and will pay to the City, in addition to all other sums owed pursuant to the Contract, the
sum of Four Hundred Thirty Dollars and Zero Cents ($430.00) for each calendar day of delay as
liquidated damages for such delay and not as a penalty. This sum may be withheld from the
balance of the contract price as it becomes due. Should liquidated damages exceed the contract
price due or to become due, then the Contractor shall pay the City the difference within three (3)
days of receipt of written demand.
Miller Road Landscape Improvements:
Lower Buckeye - Pima Street Phase I
Contract No. 2025088, Delivery Order #2
1
Brycon Corporation
ARTICLE 3
COST OF CONSTRUCTION
The total cost to complete the Work under this Delivery Order shall not exceed Four Hundred
Thousand Dollars and Zero Cents ($400,000.00), which is inclusive of the Proposal amount of
$388,050.07 and an Owner s Allowance of $11,949.93.
ARTICLE 4
INSURANCE & BONDS
In accordance with Article 19 of the Contract, the Contractor agrees to issue the required
insurance ACORD form(s). Payment and Performance Bonds are required for this project, and
will be provided by the Contractor prior to the start of the Work.
ARTICLE 5
ADDITIONAL TERMS
This Delivery Order is subject to the terms and conditions of the Contract and may be canceled
pursuant to the provisions of A.R.S. § 38-511.
To the extent applicable under A.R.S. § 35-394, the Contractor certifies that it does not, and will
not for the duration of the Contract, use the forced labor, any goods or services produced by the
forced labor, or any contractors, subcontractors, or suppliers that use the forced labor or any
China.
In the event of any conflict or discrepancy between the terms of this Delivery Order, the Contract,
and Exhibit A to this Delivery Order, the documents shall govern in that order.
ARTICLE 6
EXHIBITS
This Delivery Order includes and incorporates the following Exhibits:
Exhibit A Proposal
[SIGNATURE PAGE TO FOLLOW]
Miller Road Landscape Improvements:
Lower Buckeye - Pima Street Phase I
Contract No. 2025088, Delivery Order #2
2
Brycon Corporation
IN WITNESS WHEREOF, the parties hereto have executed this Delivery Order as of the date first
set forth above.
CITY:
CONTRACTOR:
THE CITY OF BUCKEYE, BRYCON CORPORATION,
an Arizona municipal corporation
a New Mexico corporation
______________________________
Doug Sandstrom, City Manager
Kevin Freis, Vice President of Construction
ATTEST:
Lucinda Aja, City Clerk
RECOMMENDED:
Rob Roach, Grant Program and Procurement Manager
APPROVED AS TO FORM:
City Attorney
Miller Road Landscape Improvements:
Lower Buckeye - Pima Street Phase I
Contract No. 2025088, Delivery Order #2
3
Brycon Corporation
EXHIBIT A
TO
DELIVERY ORDER #2
PROPOSAL
Miller Road Landscape Improvements:
Lower Buckeye - Pima Street Phase I
Contract No. 2025088, Delivery Order #2
4
Brycon Corporation
Miller Road Landscape Improvements:
Lower Buckeye - Pima Street Phase I
Contract No. 2025088, Delivery Order #2
5
Brycon Corporation
PROJECT NAME: City of Buckeye Miller Rd Landscape Improvements Lower Buckeye
Rd to Pima Street (Phase 1)
LOCATION: Buckeye, AZ
Date: Nov 18, 2025
Estimate No.: E25-073
Estimator: M.Kupanoff
Revision No.: 1
Brycon appreciates the opportunity to present its bid and qualifications for the above-mentioned
project.
SCOPE OF WORK
INCLUDES:
Plant Establishment Guarantee and Maintenance (excluding water & power) 3
month(s)
- 1" Screened Saddleback Brown 33730 SF
- Median DG removal and replenish 6919 SF
- 5g Shrub / Accent 446 Ea
- 5g Groundcover 376 Ea
- 36" Box Trees 52 Ea
- Tree Emitters 104 Ea
- Shrub Emitters 162 Ea
- Drip Lateral Flush Outlet 10 Ea
- 1" Electric Remote Control Valve and Pressure Regulator Assembly 6 Ea
- Controller Assembly 2 Ea
- Reduced Pressure Backflow Prevention Unit and Cage 2 Ea
- 1-1/2" Gate Valve 1 Ea
- 1" Gate Valve 6 Ea
- 1 1/2" PVC Irrigation Pipe, Schedule 80 940 LF
- 2" Schedule 80 PVC Irrigation Pipe 520 LF
- 3/4" SCH80 PVC Irrigation Pipe 5680 LF
- 1" SCH80 PVC Irrigation Pipe 2340 LF
Water meter revisions:
STA 41+44 1" Irrigation Service Per C.O.B Dtl 31330
1" Backflow Preventer With Enclosure
STA 202+90.5 Remove Existing Fire Hydrant, Riser,90 Bend And 15 LF Of 6" Pipe
6" Restraint Joint Ductile With Poly Wrap
6" Valve, Box And Cover
3'6" Fire Hydrant Per MAG 360-1
Miller Road Landscape Improvements:
Lower Buckeye - Pima Street Phase I
Contract No. 2025088, Delivery Order #2
6
Brycon Corporation
Connect To Existing Waterline
1" Irrigation Service Per C.O.B Dtl 31330
Traffic Control for up to 20 days.
QUALIFICATIONS & CLARIFICATIONS
General Requirements & Assumptions
o Proposal is based on plans & specs by Harrington Planning & Design, dated 7/22/2025
o Project duration is estimated to be 8 weeks
o Insurance and gross receipts tax is included OR this is an MRRA project. If the project
total exceeds $750,000 at any time during the project, gross receipts tax will be added to
the project.
o Payment and performance bonds are included.
o Provide full-time field supervision on site, at all times, during construction activities.
o Provide qualified person responsible for safe performance of work.
o Host weekly progress meetings attended by the project manager and superintendent.
o
Daily and final cleanup of trash and construction debris to Brycon provided dumpsters.
Exclusions
o Off hours or weekend work.
o Hazardous materials testing or abatement.
o Permits, plan reviews, and associated fees.
o Unforeseen conditions.
o Hard Dig.
o Utility Realignments.
o BIM & CAD Documents/As-Builts.
o Geotech Reports.
o Special Inspections.
o Architectural and Engineering design costs and fees.
o Surveying assumes ready
o Rough grading assumes ready
o Steel edge and rip rap in the medians.
o Rip-Rap
o Site furnishings and amenities.
o Gabion baskets, concrete and concrete form-liners, fill materials.
o Artificial turf installation.
o Directional bore sleeving.
o Traffic control.
o Import or export of soil.
o Rough grading or mounding.
Miller Road Landscape Improvements:
Lower Buckeye - Pima Street Phase I
Contract No. 2025088, Delivery Order #2
7
Brycon Corporation
o Concrete and pavement work.
o Electrical work.
o Electric service to irrigation controllers.
o DG in retention basins
o Federal prevailing wages.
Base Bid: $388,050.07
If there are any questions and/or comments, please do not hesitate to call us at 480.785.9911.
Sincerely,
BRYCON CORPORATION
cc: Kevin Freis, Vice President of Construction
Miller Road Landscape Improvements:
Lower Buckeye - Pima Street Phase I
Contract No. 2025088, Delivery Order #2
8
Brycon Corporation