JOB ORDER CONTRACT DELIVERY ORDER
BETWEEN
THE CITY OF BUCKEYE
AND
M.R. TANNER DEVELOPMENT AND CONSTRUCTION, LLC
JOB ORDER CONTRACT NO. 2025081
DELIVERY ORDER # 12
ACACIA WAY CHICANES
THIS DELIVERY ORDER #12 (this “Delivery Order”) is entered into as of November 24, 2025,
between the CITY OF BUCKEYE, an Arizona municipal corporation (the “City”) and M.R. Tanner
Development and Construction, LLC, an Arizona limited liability company (the “Contractor”). This
Delivery Order is subject to and governed by the terms and conditions of Job Order Contract No.
2025081 between the City and Contractor, dated September 3, 2024 (the “Contract”).
ARTICLE 1
SCOPE OF WORK
The Contractor shall furnish all labor, materials, and equipment, as more fully set forth in the
Proposal, which is attached hereto as Exhibit A, and incorporated as if fully set forth herein (the
“Work”), to complete the Acacia Way Chicanes project, as more fully set forth in the Plans and
Specifications, which are attached hereto as Exhibit B and incorporated as if fully set forth
herein (the “Project”).
ARTICLE 2
SCHEDULE OF COMPLETION OF WORK
The Contractor shall commence work within ten (10) days from issuance by the City of a Notice
to Proceed, and shall complete the Work by May 1, 2026, unless the Delivery Order or the
Contract is terminated per the terms of the Contract.
ARTICLE 3
COST OF CONSTRUCTION
The total cost to complete the Work under this Delivery Order shall not exceed Three Hundred
Seventy-Two Thousand Five Hundred Fifteen Dollars and Zero Cents ($372,515.00).
Acacia Way Chicanes
Contract No. 2025081 DO#12
M.R.Tanner Development and Construction, LLC
1
ARTICLE 4
INSURANCE
In accordance with Article 18 of the Contract, the Contractor agrees to issue the required
insurance ACORD form(s).
ARTICLE 5
ADDITIONAL TERMS
This Delivery Order is subject to the terms and conditions of the Contract and may be canceled
pursuant to the provisions of A.R.S. § 38-511.
By executing this Delivery Order, the Contractor certifies its compliance with A.R.S. § 35-393.01.
To the extent applicable under A.R.S. § 35-394, the Contractor certifies that it does not, and will
not for the duration of the Contract, use the forced labor, any goods or services produced by the
forced labor, or any contractors, subcontractors, or suppliers that use the forced labor or any
goods or services produced by the forced labor of ethnic Uyghurs in the People’s Republic of
China.
In the event of any conflict or discrepancy between the terms of this Delivery Order, the Contract,
and Exhibit A to this Delivery Order, the documents shall govern in that order.
ARTICLE 6
EXHIBITS
This Delivery Order includes and incorporates the following Exhibits:
Exhibit A – Proposal
Exhibit B – Plans and Specifications
[SIGNATURE PAGE TO FOLLOW]
Acacia Way Chicanes
Contract No. 2025081 DO#12
M.R.Tanner Development and Construction, LLC
2
IN WITNESS WHEREOF, the parties hereto have executed this Delivery Order as of the date first
set forth above.
CITY:
CONTRACTOR:
THE CITY OF BUCKEYE, M.R. TANNER DEVELOPMENT AND
an Arizona municipal corporation
CONSTRUCTION, LLC, an Arizona limited
liability company
______________________________
Doug Sandstrom, City Manager
Chad Montoya, Vice President
ATTEST:
Lucinda Aja, City Clerk
RECOMMENDED:
Rob Roach, Grant Program and Procurement Manager
APPROVED AS TO FORM:
K. Scott McCoy, City Attorney
Acacia Way Chicanes
Contract No. 2025081 DO#12
M.R.Tanner Development and Construction, LLC
3
EXHIBIT A
TO
DELIVERY ORDER #12
PROPOSAL
Acacia Way Chicanes
Contract No. 2025081 DO#12
M.R.Tanner Development and Construction, LLC
4
EXHIBIT B
TO
DELIVERY ORDER #12
PLANS AND SPECIFICATIONS
Acacia Way Chicanes
Contract No. 2025081 DO#12
M.R.Tanner Development and Construction, LLC
5