City Council Workshop
Airport Master Plan Recommendations Overview
September 16, 2025

Agenda/Topics
•Airport Master Plan
•Airport Layout Plan (ALP)
•Long-Range Airport Development Plan
•Airport Specific Area Plan
•Next Steps
•Questions

Airport Master Plan
• What is it?
• Federal Aviation Administration required planning document
• Identifies a 20-year capital development plan for an airport
• Determines the extent, type, and timeline of future development
• Development eligible for federal/state grant funding
• Supports the depictions on the Airport Layout Plan
• What it is not
• Visionary or an aspirational concept plan
• Most recent Master Plan was published in 2007

Airport Master Plan Process

Airport Master Plan Process
Planning Advisory Committee (PAC)
• Advise the Airport and Consultant
• Attend PAC meetings
• Provide feedback on deliverables and the process
• Share study progress with community
• Promote public information meetings
Public Involvement
• Open house format with interactive information stations
• Inform the public of a master plan’s goals and objectives
• Engage the public and stakeholders in soliciting their opinions on development

Master Plan Facility Requirements

Recommended Airside Development
• Airspace and Instrument Procedure Analysis
• Significant coordination with Luke AFB to ensure minimum disruption to the mission
• Analysis of runway configurations
• Primary Runway
• Runway 17-35 remains primary runway through planning period
• 1,800-foot Extension of Runway 17 to the North, total Runway 17-35 length 7,300 feet
• Crosswind Runway
• Runway 10-28 (Airspace Study)
• Alignment on the south of the airport
• 6,000-foot length

Recommended Landside Development
• Air Traffic Control Tower
• Conventional hangars, Executive hangars, T-hangars
• Additional apron and tiedowns
• Non-aeronautical development opportunities
• Access roads and taxilanes

Capital Improvement Plan (20 years)
TIMELINE
TOTAL COST
FEDERAL
STATE
LOCAL
OTHER
PAL 1 (2025-2029)
$43.1
$9.4
$2.8
$13.5
$17.4
PAL 2 (2030-2034)
$115.1
$73.1
$3.4
$3.6
$34.9
PAL 3 (2035-2045)
$21.1
$5.6
$0.3
$3.3
$11.9
TOTAL
$179.4
$88.1
$6.7
$20.3
$64.2
* Estimated costs in millions include planning, environmental, engineering, construction and land acquisition.

Long-Range Airport Development Plan
• Framework for long-range vision beyond the 20-year MP horizon
• Identifies opportunities to meet the anticipated demands of the community beyond the 
constraints of a typical MP
• Visioning
• Demand Scenarios
• Facility Requirements
• Alternatives
• Implementation Plan
• Development Plan Set
• LRADP goal is to accommodate prospective:
• Commercial Service
• Air Cargo
• Military
• Corporate/business users
• Urban air mobility and advanced air mobility  
• Non-aeronautical development
• LRADP included in the appendices of the Master Plan

Recommended Long-Range Development
• Runway 10-28 becomes the Primary 
Runway at 8,800 x 100 feet
• Construct Parallel Training Runway 
(ultimately repurposed as a taxiway)
• Runway 10-28 extended to 10,500 feet
• New Runway 10R-28L at 10,500 feet
• Development areas to accommodate 
Commercial Service, Cargo, Military, 
and other aeronautical uses

Airport Specific Area Plan
• City as the Airport sponsor is required to control land uses around 
the airport
• Propose compatible land uses and zoning
• Airport Master Plan and Long-Range Airport Development Plans 
provide details on height and noise contours
• Height and Noise Overlay Zoning Ordinance

Next Steps
Finalize Master Plan Report
Finalize Airport Layout Plan
Council Adoption of Airport Master Plan
FAA Review and Approval of the Airport Layout Plan
Airport Specific Area Plan

Questions