Floreo at Teravalis
Master Plat Narrative
for
Development Unit 2
North of the NWC of the Sun Valley Parkway and
Teravalis Parkway alignment
City of Buckeye, Arizona
Prepared for:
Trillium Land Company, LLC
4150 N. Drinkwater Blvd., Ste. 100
Scottsdale, Arizona 85251
Telephone: 602.834.9115
Contact: Stuart Barney
Prepared by:
HILGARTWILSON, LLC
4742 N 24th Street, Suite 270
Phoenix, AZ 85016
Telephone: 602.490.0535
Contact: Josh Robinson, PE
Date: August 6, 2025
PROJECT OVERVIEW
Floreo at Teravalis (formerly known as Trillium) is a 3,029-acre master planned community located
in the northern area of the City of Buckeye, adjacent and west of the Sun Valley Parkway, east of
the Hassayampa River, and adjacent to the proposed Teravalis Parkway. Refer to Aerial Vicinity
Map for Project location.
A Community Master Plan (CMP) amendment was approved by the Buckeye City Council on
November 1, 2016. In the approved CMP, Floreo is organized into villages with each village
containing multiple pods. Each of the pods may be further split into smaller development parcels.
Refer to Land Use Master Plan for Village and Pod areas.
Since approval of the CMP, the Floreo naming convention of Villages, PODS, & Parcels has
changed. These changes have been approved by the City of Buckeye (CMP Amendment #2 PLZZ
21-00024 Approval 9/1/21). Refer to the Land Use Master Plan Exhibit 8 and the Parcel Exhibit
for a summary of these changes. These exhibits are located at the back of this narrative.
DESCRIPTION OF REQUEST
The Master Plat for Floreo at Teravalis Development Unit 2, consisting of Parcels 1 through 14,
will define internal boundaries and dedicate public right-of-way and associated public utility
easements (PUE) for major roadways within the Project. Sun Valley Parkway is an existing
roadway located on the Project’s eastern boundary and provides existing right-of-way (150 feet
wide and within MCDOT jurisdiction).
Parcels 1 through 14 will be defined by this Master Plat.
The following are the roadways that will have full or partial right-of-way dedicated to the City of
Buckeye by this Master Plat.
a) Sun Valley Parkway – The west half of the roadway provides an existing right-of-way width
of 75 feet (MCDOT Jurisdiction). An additional 25 feet of right-of-way (Buckeye
Jurisdiction) will be dedicated with this Master Plat, providing a total right-of-way width of
100 feet (west half of the roadway).
b) Indigo Way – a collector with 80 ft right-of-way and major collector with 110 ft right-of-way
(for portion located east of 296th Avenue)
c) 296th Avenue – a collector with 80 ft right-of-way
d) 301st Avenue – a major local with 60 ft right-of-way
CURRENT SITE CONDITIONS
The Floreo property is vacant desert situated within a prominent growth area in the City of Buckeye.
Floreo is located west of the Sun Valley Parkway and adjacent to the proposed Teravalis Parkway.
The White Tank Mountains are to the east and the Hassayampa River is to the west of the Floreo
property. Although the surrounding area is still primarily vacant desert, several large master
planned communities are approved for development.
The Project and surrounding area General Plan designations, Zoning Districts, and land uses are
outlined in the table below.
SITE AND SURROUNDING PROPERTIES
General Plan
Zoning
Land Use
Site (Development Unit 2)
Master Planned
Community (MPC)
Planned Community (PC)
Teravalis CMP Overlay
Vacant Desert Floreo
Unit 2
North
Master Planned
Community (MPC)
Planned Community (PC)
Teravalis CMP Overlay
Vacant Desert Future
Floreo Unit 1
East
Master Planned
Community (MPC)
Planned Community (PC)
Vacant Desert
South
Master Planned
Community (MPC)
Planned Community (PC)
Teravalis CMP Overlay
Vacant Desert Floreo
Unit 3
West
Master Planned
Community (MPC)
Planned Community (PC)
Teravalis CMP Overlay
Vacant Desert Future
Floreo Unit 4
This site is currently undeveloped desert, except for Village 3, just South of Development Unit 2,
which has recorded final plats, is mass graded, and is currently in various stages of construction.
Village 3 will ultimately be developed into single family homes, community center, and
commercial/office uses.
PROJECT USES AND AREAS
UNIT 2
1
MDR (3-4.5 du/ac)
45.28
2
MDR (3-4.5 du/ac)
54.57
3-14
MDR (3-4.5 du/ac)
233.92
Total
333.77
Note:
(1)
Gross
Area
(Acres) (1)
All acreage is approximate. Subtotals and totals may
not exactly add up due to rounding errors.
Land Use Category
Parcel #
Parcel #
Gross Area
(Ac)
Gross Density
(DU/Ac)
3
72
21.21
3.39
4
74
15.22
4.86
5
68
14.22
4.78
6
46
12.48
3.69
7
71
17.58
4.04
8
68
13.57
5.01
9
81
16.50
4.91
10
61
22.06
2.77
11
97
21.77
4.46
12
87
24.37
3.57
13
41
26.26
1.56
14
48
28.68
1.67
TOTAL
814
233.92
3.48
Proposed
Units
Single Family Residential
AREA
AC
PARCELS
333.77
ROW
21.72
TOTAL
355.49
STREET NAME
AREA (AC)
296TH AVENUE
4.29
301ST DRIVE
2.17
INDIGO WAY NORTH
13.84
SUN VALLEY PARKWAY
1.42
TOTAL
21.72
RIGHT OF WAY TABLE
ZONING
The City’s current zoning for the Project is Planned Community (PC) and the conceptual land plan
is in conformance with its requirements.
DEVELOPMENT SEQUENCE
Floreo Development Unit 2, consisting of 14 single-family residential parcels, local and collector
roadways, a parkway, and higher density residential parcels will be mass graded at one time.
Construction will begin with Mass grading followed by Phase 1 Offsite Infrastructure and Phase 2
Offsites Infrastructure. Followed by Phase 1 Parcels 3-14. Followed by Phase 2 Parcels 1 & 2. For
more information see Parcel Exhibit on page 12.
PROPOSED TRAILS
Concrete sidewalks are included with each street within the Project. In addition, concrete and
decomposed granite trails will traverse through the open spaces located throughout Development
Unit 2. The trails will provide linkage between the parcels, as well as provide access to amenities
and parks through the Floreo Community.
VEHICULAR CIRCULATION
The roadways for the Project will be public. Access for the Project will be provided to the existing
Sun Valley Parkway and Village 3 (currently in construction) via 296th Avenue and Indigo Way.
PUBLIC UTILITIES AND SERVICES
WATER SOURCE
The proposed water system for the Project has been designed to function both as a part of
the larger City of Buckeye system at full build-out of the City’s system and as a stand-alone
system for serving the Floreo at Teravalis community until such time as the City’s system
is fully built-out.
The designs of the wells, well transmission system, and water campus to serve the Project
are being prepared concurrently and will be submitted separately. The Floreo Water
Campus (FWC) will be developed in phases to serve the community as it develops. The FWC
potable water supply, treatment, storage, pumping and distribution facilities must meet the
requirements for the Project as detailed in this Report at all stages of development.
The first phase of the FWC will include raw water storage, sodium hypochlorite disinfection,
initial booster pumps, and one finished water reservoir with approximately 3.67 Mgal of
total storage (3.33 Mgal of usable storage) which will have sufficient capacity to adequately
serve the Project. The booster pumps will be sized to meet the Project’s water demands
with the largest booster pump out of service at all stages of development.
Additional information about the required well supply, storage, treatment, and booster
pumping capacities required to serve the overall Floreo community and the Project area
are discussed in greater detail within the Master Report (HILGARTWILSON, 2016). Once
constructed, the water infrastructure serving Floreo will be owned and operated by the City
of Buckeye.
WASTEWATER MANAGEMENT
Floreo Development Unit 2 will be served by an onsite network of 12-inch to 18-inch gravity
sewer lines that will generally route wastewater flows to the southeast corner of Parcel 13.
From there, proposed offsite 18-inch sewer mains will route wastewater flows from the
Project as well as other offsite flows from the remaining portions of Village 1 to a package
WWTP. The package WWTP will be located within Village 3 Parcel 53 near the intersection
of the Johnson Road and Wintersburg Parkway alignments. Wastewater from the Project
will be treated at a package WWTP on an interim basis. As the package WWTP is brought
online, a permanent WRF will be constructed within Village 5 along the southern boundary
of the Floreo community, to ensure it can treat flows when the package WWTP reaches
capacity. At that time, the package WWTP will be taken offline and all flows will be conveyed
to the permanent WRF. Treated wastewater flow from the Floreo Interim WRF and
Permanent WRF will be pumped to the underground treated effluent storage tanks within
the Village Core in Village 3. Water from the underground tanks will be pumped throughout
Villages 2 and 3 for irrigation purposes per the development agreement that has been
established for this Floreo. Reclaim water will initially be provided by the Interim WRF and
then by the Permanent WRF once it comes online.
The Master Report discusses anticipated sewer alignments and wastewater flows for the
upstream contributing areas, north of the Project. All sewer mains within the Project have
been designed to adequately convey wastewater flows from the Project, and the
contributing upstream areas at build-out while meeting City design requirements. It is
anticipated that the wastewater infrastructure serving Floreo will be owned and operated
by the City of Buckeye.
RECLAIMED WATER
The reclaimed water system will provide water for irrigation use to various parks and
developed open space areas within the Project, including community parks and
neighborhood parks. Other significantly-sized landscaped areas may also be served by the
reclaimed system where deemed appropriate. Depending on size and proximity to the
reclaimed water mains, these may include landscaped areas along arterials and collector
streets, community entrances and trails, and other landscaped tracts.
Ultimately, the reclaimed water system will be supplied by treated effluent generated at the
future Floreo Water Reclamation Facility (WRF), located along Floreo’s southern boundary.
Until such time as the WRF is constructed and produces sufficient effluent to meet the
reclaimed water demands, effluent from a package wastewater treatment plant will be
used. Raw groundwater and/or potable water may also be used on a short-term basis until
sufficient effluent is available from the package wastewater treatment plant.
STORM WATER MANAGEMENT
A storm water management plan will be provided to direct best management practices
during construction. This will address items including but not limited to dust control, silt
and pollutant control, storm drain inlet protection, stabilized construction entrance
location, and washout area designation. An ADEQ Phase 2 Stormwater General Permit will
be obtained to ensure the proposed stormwater management is in compliance with ADEQ
and City requirements.
STREETLIGHT IMPROVEMENT DISTRICT AND MAINTENANCE
IMPROVEMENT DISTRICT
A streetlight improvement district (SLID) will be established for all of Floreo Development
Unit 2 early in the process, if not for the entire development, then an initial SLID will be
established and expanded as necessary to cover future growth of Floreo.
Maintenance improvement district(s) shall be established for the HOA, one MID per HOA,
covering the maintenance responsibilities delegated to the HOA for areas within the rights
of way, retention, and detention areas and other areas as per the requirements within
City Code Chapter 20.
SOLID WASTE
Curbside residential cart service for trash and recycling will be provided by the City of
Buckeye.
FIRE PROTECTION
Buckeye Fire Department will provide service to the community through a temporary fire
station to be located within the Project.
POLICE PROTECTION
Buckeye Police Department will provide service. The nearest police station is located at
100 North Apache Road #D, Buckeye, Arizona 85326.
IMPACT ON LOCAL SCHOOLS
The Project is located within Saddle Mountain Unified School District boundaries for both
elementary and high school students. The developer has been in discussion with Dr. Paul
Tighe, Superintendent for the school district with the last communication occurring on
July 15, 2021. Existing schools within the vicinity of the Project are listed below:
Tartesso Elementary School
29677 W. Indianola Rd.
Buckeye, AZ 85326
623.474.5400
Festival Foothills Elementary School
26252 W Desert Vista Blvd.
Buckeye, AZ 85396
928.501.6000
Tonopah Valley High School
38201 W. Indian School Rd.
Tonopah, AZ 85354
623.474.5200
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
BOB STUMP MEMORIAL HIGHWAY - LOOP 303
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
INTERSTATE 10
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
FLOREO
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
OLIVE AVE
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
YUMA RD
WHITE
TANK
MOUNTAINS
INTERSTATE
ARIZONA
10
HASSAYAMPA RIVER
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
BELL RD
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
SUN VALLEY PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
TERAVALIS PARKWAY
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
(CACTUS ROAD ALIGNMENT)
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
PEORIA AVENUE
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
WADDELL ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
ACOMA ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
GREENWAY ROAD
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
SUBJECT
AREA
DEVELOPMENT
UNIT2
1
1
1
1
RIGHT OF WAY TABLE
STREET NAME
297TH DRIVE
299TH AVENUE
299TH LANE
300TH DRIVE
VIOLETTA ROAD
VIOLETTA ROAD.
AREA (SQ.FT)
11,327
14,865
11,794
10,151
21,843
42,860
AREA (ACRES)
0.2600
0.3412
0.2707
0.2330
0.5015
0.9839
1
P: 602.490.0535 / F: 602.368.2436
www.hilgartwilson.com
2141 E. HIGHLAND AVE., STE. 250
PHOENIX, AZ 85016