Monroe Avenue
Streetscape Project
City Council Meeting
August 26, 2025
Agenda
• DSAP and Monroe Activity Overview
• Monroe Avenue Pilot Striping and Long-Term Phasing Plan
• Proposed Interim Survey, Restripe, and Design Schedule
What is the Downtown Specific Area Plan?
• Extensive and inclusive stakeholder process
• 90-member stakeholder group
• 865 community responses
• 440 attendees between two open houses
• 4,000 subscribers to monthly update newsletter
• The approved document guides land uses, design, public
infrastructure and transportation projects, economic
development strategies, branding, and more
• Includes short-term (1-3 year), mid-term (4-7 year) and long-
term (8+ year) projects to implement the community vision
DSAP Vision for Monroe Avenue
• Lane reduction
• Parallel
parking and/or
parklet lanes
• Wide sidewalks and
amenity zones
• Enhanced landscape
and shade ideas
• Discourages through
truck traffic
Stages of Monroe Reconstruction
STAGE
PROJECT
Status
Dates
Stage 1
Monroe Demonstration Restriping Project
Completed
FY23-24
Stage 1
City Hall East Parking Lot
Completed
FY24
Stage 2
Landscape Demonstration: Downtown Enhancement Program
Completed
FY25-26
Stage 3
Interim Landscaping: Downtown Enhancement Program
In Progress
FY26-27
Stage 4a
Design Concept Review: Monroe Reconstruction and Utility Plan
Pending
FY26-27
Stage 4b
Storm Drain and Fiber: Downtown Storm Drain Project
Pending
FY27+
Stage 4c
Utility Installation: Downtown Improvement Program - Utilities
Pending
~FY30+
Stage 5
A New Cityscape: Downtown Improvement Program - Streetscape
Pending
~FY30+
Stage 1: Monroe Restriping
Complete
• Remove layer of asphalt and pavement
marking and seal cracks
• New designated truck route established
• Speed limit reduced
• Seal coat street
• Repaint pavement markings
• Restriping of Monroe Ave. to two lane road
• Additional parallel parking added
• Designated driveway access striped
• Painting of Parklet zones
• Crosswalk reconstruction
Stage 2: Landscape Demonstration
Demonstration Project: 5th St. to 6th St.
•
Box trees installed on north and south sides
•
Tree boxes framed & wrapped
•
Pedestals to support drainage
•
Planter Boxes Installed along the block
•
Smaller boxes focused on chicanes
•
Larger boxes staged between trees
•
Chicanes were cleaned and enhanced
•
Sample parklet installed and furnished
Stage 3: Interim Landscape and Streetscape
Design Phase - Design Concept Review evaluates options & challenges of reconstruction
•
Limits of construction
•
Existing underground utilities and their locations
•
Capacity and utility needs for future build out
Stormwater Management, Fiber, and City Utilities
• Utility: Forecast and design utility improvement to support anticipated development along Monroe
(Utilities considered: water, sewer, natural gas, power, and fiber)
Construction Phasing and Coordination
•
Ongoing phasing efforts with storm drain, hardscape, & future utility planning for efficient use of
resources and minimal impact to Monroe
Stage 4: Design Concept and Utility Work
Stage 5: Final Streetscape Installation
Scenario 3: Modified 3-Lane w/Center Turn
Scenario 3: Modified 3-Lane w/Center Turn
Interim Restriping Phasing and Schedule
Phase
Timeframe
1. Kickoff & Scope Confirmation
July 2025
2. Survey & Base Mapping
July – August 2025
3. Design Development & Outreach
September – December 2025
4. Potholing & Utility Verification
March – April 2026
5. Final Design Submittal
January – March 2026
6. Surface Prep/Remove striping
Late May 2026
7. Surface Treatment
June 2026
8. Restripe Monroe Avenue
June – August 2026
9. Project Closeout
August 2026
Other Considerations
• Demonstration parklet and planters to be removed in preparation for DCR and
repaving
• Crosswalks to be returned to high-visibility white crossing stripes
• Lane widths to approximate final lane widths of approximately 12 feet
• Parallel parking to be preserved, temporary parking buffer to approximate width of
future widened sidewalk
• Restripe budgeted within Downtown Enhancement CIP project
• Additional enhancements can occur after the 2026 restripe (e.g. plaza string lights,
street furniture, etc.)
Recommended Action Items
1. Consider and vote to approve the a 3-lane section as the long-term lane
configuration for Monroe through downtown
2. Consider and vote to approve restriping the interim configuration to a 3-lane
section within the next 9 months
Questions?