Contract 2025273 CO#2 Granite Constructions CO.pdf

City of Buckeye — Regular Council Meeting (2025-07-01)

View PDF Meeting page

Extracted text (via pymupdf) 4912 characters
(REV. 12.9.2024) 
CONSTRUCTION CONTRACT 
BETWEEN
THE CITY OF BUCKEYE
AND
GRANITE CONSTRUCTION COMPANY
CONTRACT NO. 2025273 
CHANGE ORDER #2 
THIS CHANGE ORDER #2 (this “Change Order”) is entered into as of 
, between 
the City of Buckeye, an Arizona municipal corporation (the “City”) and Granite Construction 
Company, a California corporation (the “Contractor”). This Change Order modifies certain 
sections of Contract No. 2025273 (the “Contract”), with those sections not expressly 
modified remaining in full effect pursuant to their terms.  
CONTRACT CHANGES: 
1.
Section 3
Contract Price is amended by increasing the not-to-exceed
amount by $101,041.07  from $657,729.00 to $758,770.07. 
2.
Exhibit B – Contractor Proposal, is amended by incorporating the revisions to
the Work as set forth in Exhibit 1 to Change Order #2 
RECITALS: 
The City and Contractor entered into Contract No. 2025273 dated March 4, 2025. Pursuant 
to which Contractor was to provide construction services to complete the BXK Taxiway H & 
Hangar Taxi lanes Rehabilitation project with Substantial Completion achieved within Fifty-
One (51) calendar days from the effective date of the Notice to Proceed and a not-to-exceed 
amount of $650,154.00. 
Thereafter, Change Order #1 to change the not-to-exceed amount by $7,575.00_from 
$650,154.00 to $657,729.00. was entered into as of April 23,2025. 
ADDITIONAL PROVISIONS: 
Except as amended herein, all provisions of the Contract remain in full force and 
effect. 
In the event of any conflict or discrepancy between the terms of this Change Order, 
the Contract, and any other contract documents, the documents shall govern in that order.  
Airport Runway Markings 
Contract 2025273 CO#2 
Granite Construction Company
1

(REV. 12.9.2024) 
This Change Order may be canceled pursuant to the provisions of A.R.S. § 38-511. 
IN WITNESS WHEREOF, the parties hereto have executed this Change Order as of the date 
first set forth above. 
CITY: 
CONTRACTOR: 
THE CITY OF BUCKEYE,
GRANITE CONSTRUCTION COMPANY, 
an Arizona municipal corporation
a California corporation
By: 
David B. Roderique, Interim City Manager
   Its:____________________________________ 
ATTEST:
Lucinda Aja, City Clerk 
RECOMMENDED:
William Kauppi, Chief Financial Officer
APPROVED AS TO FORM: 
K. Scott McCoy, City Attorney
Airport Runway Markings 
Contract 2025273 CO#2 
Granite Construction Company
2

(REV. 12.9.2024) 
Exhibit 
(Proposal)
Airport Runway Markings 
Contract 2025273 CO#2 
Granite Construction Company
3

May 8, 2025
Buckeye Municipal Airport 
City of Buckeye 
3000 S. Palo Verde Rd. 
Buckeye, AZ 85326 
Attn: Scott W. Lowe, PE, CEM, PWLF 
 Airport Assets Director 
RE: 
Proposal for Non-Precision Approaches Marking and Lighting Modifications 
Granite Construction Company respectfully submits the below pricing for the requested additional striping and 
electrical work included in in the drawings and specifications 
-35 Non-Precision Approaches Marking 
and Lighting Modifications.  
Work includes: 
 
Notes: 
1.
No additional mobilization for stripers included.  Will be added if required.
2.
No utility location anticipated or included.
3.
No Granite sweeping prior to seal coating in striping obliteration area.  Assume striper will leave clean
enough for seal coat.
4.
Dump site for waterblasting (striping obliteration) will be provided on-site by owner.
5.
Sweeping of blast pad prior to seal coat included if this option is selected.
6.
No additional mobilization for crack seal blast pad included.  Assumed to happen concurrent with run-up
area crack seal work.  Will be added if needed.
7.
Granite includes 6 hours (2 daysx3 hrs/day) of fuel truck service to fuel any Granite equipment and
runway x s.
8.
No power broom support or final cleanup crew included.  Assuming when work is complete, it will be
acceptable.
9.
The price included in item 400 includes 750 gallons of seal coat material.  The stripe obliteration area is
only estimated to need 250 gallons, however a minimum of 600 gallons must be loaded into the truck to
allow proper heating and circulation and the material comes in 250 gallon totes.  The remaining 500
gallons could be applied elsewhere on the airport at no additional cost as long as the work takes place at
the same time as the seal coating of the obliterated markings.

May 8, 2025
2 | P a g e
10. New threshold light installation does not include any excavation beyond that needed to install the new
light can.  If trenching/patching is required to tie into conduit, it will be tracked for separate payment.
11. Blast pad crack seal/seal coat work would cost $28,000 if added to the scope based on 2100 lf of crack
seal and 3294 sy of seal coat, assuming the seal coat material was previously purchased per item 1.
Please contact Jim Merrigan at (520) 260-4385 if you have questions or need additional information. 
Sincerely, 
Jim Merrigan
Area Manager