JOB ORDER CONTRACT DELIVERY ORDER
BETWEEN
THE CITY OF BUCKEYE
AND
SCHOFIELD CIVIL CONSTRUCTION LLC
JOB ORDER CONTRACT NO. 2025109
DELIVERY ORDER #1
TARTESSO WRF ARSENIC AND FLUORIDE TREATMENT UPGRADES
THIS DELIVERY ORDER #1
is entered into as of ______________________,
between the CITY OF BUCKEYE
City , and Schofield Civil
Construction LLC, an Arizona limited liability company
This Delivery Order is
subject to and governed by the terms and conditions of Job Order Contract No. 2025109 between
the City and Contractor, dated September 3, 2024
.
ARTICLE 1
SCOPE OF WORK
The Contractor shall furnish all labor, materials, and equipment, as more fully set forth in the
Proposal, which is attached hereto as Exhibit A and incorporated as if fully set forth herein (the
, to complete the Tartesso WRF Arsenic and Fluoride Treatment Upgrades (the
.
ARTICLE 2
SCHEDULE OF COMPLETION OF WORK
The Contractor shall commence work within ten (10) days from issuance by the City of a Notice
to Proceed, and shall complete the Work on or before December 31, 2025. In view of the
difficulty or impossibility of determining the City's damages from delay, should the Contractor
fail to achieve Substantial Completion with the above number of calendar days, as may be
extended by any City-approved Change Orders, the Contractor agrees to pay and will pay to the
City, in addition to all other sums owed pursuant to the Contract, the sum of Seven Hundred Ten
Dollars and Zero Cents ($710.00) for each calendar day of delay as liquidated damages for such
delay and not as a penalty. This sum may be withheld from the balance of the contract price as
it becomes due. Should liquidated damages exceed the contract price due or to become due,
then the Contractor shall pay the City the difference within three (3) days of receipt of written
demand.
ARTICLE 3
COST OF CONSTRUCTION
The total cost to complete the Work under this Delivery Order shall not exceed One Million Six
Hundred Fifty-Three Thousand Two Hundred Fifteen Dollars and Zero Cents ($1,653,215.00).
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
1
ARTICLE 4
INSURANCE & BONDS
In accordance with Article 19 of the Contract, the Contractor agrees to issue the required
insurance ACORD form(s). Payment and Performance Bonds are required for this project, and
will be provided by the Contractor prior to the start of the Work.
ARTICLE 5
ADDITIONAL TERMS
This Delivery Order is subject to the terms and conditions of the Contract and may be canceled
pursuant to the provisions of A.R.S. § 38-511.
To the extent applicable under A.R.S. § 35-394, the Contractor certifies that it does not, and will
not for the duration of the Contract, use the forced labor, any goods or services produced by the
forced labor, or any contractors, subcontractors, or suppliers that use the forced labor or any
China.
In the event of any conflict or discrepancy between the terms of this Delivery Order, the Contract,
and Exhibit A to this Delivery Order, the documents shall govern in that order.
ARTICLE 6
EXHIBITS
This Delivery Order includes and incorporates the following Exhibits:
Exhibit A Proposal
[SIGNATURE PAGE TO FOLLOW]
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
2
IN WITNESS WHEREOF, the parties hereto have executed this Delivery Order as of the date first
set forth above.
CITY:
CONTRACTOR:
THE CITY OF BUCKEYE, SCHOFIELD CIVIL CONSTRUCTION LLC,
an Arizona municipal corporation
an Arizona limited liability company
______________________________
David B. Roderique, Interim City Manager
Eddie Hawley, Secretary
ATTEST:
Lucinda Aja, City Clerk
RECOMMENDED:
William Kauppi, Chief Financial Officer
APPROVED AS TO FORM:
K. Scott McCoy, City Attorney
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
3
EXHIBIT A
TO
DELIVERY ORDER #1
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
4
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
5
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
6
AMON BUILDERS LLC
General Building Contractor
37615 N 16th Street
Phoenix, AZ 85086
(928) 970-0715
amonbuildersllc@gmail.com
Contractors Lic. No. ROC KB-1 328395
We are pleased to have the opportunity to submit our proposal/estimate to furnish tools, equipment,
labor, material and supervision for th
x17 Pre-Engineered Metal
building per your drawings.
INCLUDES:
Structural design sealed by licensed structural engineer
Pre-Engineered Metal building.
IBC 2018,
Roof panel- 26 gauge PBR profile w/ 4:12 pitch
Wall panel- 26 gauge PBR profile with standard color finish
(1
personnel doors with mortise lever lock sets
(1) 12 x14 canister roll-up over head door w/ jamb wrap and manual operation
(1) 16 x11 canister roll-up over head door w/ jamb wrap and manual operation
R-19 Roof and R-13 wall insulation
12 x32 -2 x14 Lean to
Freight to Phoenix, AZ including unloading of building materials.
Please see attached exhibit A
Building Erection
Concrete Foundation based on standard 4 3,000 PSI Concrete
STAR Metal Building Price: $111,710.66
Building Erection: $36,000.00
Building Foundation and Slab: $42,660.00
Excludes
Taxes, permit fees, impact fees, soils report, survey, grading & drainage plans, testing or special
inspections, Termite pre treat.
Gutters, downspouts, Garage Doors, Man Doors, finish painting of red iron, or exterior concrete.
fire suppression, associated engineering/drawings
Due to erratic price increases in building materials our proposal/contract must be subject to increased
amounts we may be required to pay for subject to price fluctuations over the prices quoted as of the date
of this proposal. 50% Deposit is due upon execution of this contract. We will provide you proof of any
increase. This proposal in its entirety is to be incorporated into and shall become part of any contract
agreement entered into by Amon Builders LLC for this project.
For your convenience, we submit this proposal in the form of a contractual agreement. If it meets with
your approval you need only to sign and return it to our office. Return of this signed proposal shall
constitute a contract.
Respectfully Submitted,
Levi Amon, President
PROPOSAL/ESTIMATE
February 10, 2025
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
7
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
8
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
9
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
10
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
11
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
12
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
13
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
14
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
15
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
16
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
17
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
18
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
19
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
20
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
21
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
22
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
23
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
24
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
25
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
26
Tartesso WRF Arsenic and Fluoride Treatment Upgrades
Contract No. 2025109, Delivery Order #1
Schofield Civil Construction LLC
27