May 20 2025 Council Workshop - Monroeb.pdf
Extracted text (via pymupdf)
5214 characters
Monroe Avenue
Streetscape Project
City Council Workshop
May 20, 2025
Agenda
• DSAP Overview
• Monroe Avenue Pilot Striping and Long-Term Phasing Plan
• Public Safety, Financial, and Driver Convenience Impacts
• Overview of Lane Configuration Scenarios
• Downtown Stakeholder Survey Results
What is the Downtown Specific Area Plan?
• Extensive and inclusive stakeholder process
• 90-member stakeholder group
• 865 community responses
• 440 attendees between two open houses
• 4,000 subscribers to monthly update newsletter
• The approved document guides land uses, design, public
infrastructure and transportation projects, economic
development strategies, branding, and more
• Includes short-term (1-3 year), mid-term (4-7 year) and long-
term (8+ year) projects to implement the community vision
DSAP Vision for Monroe Avenue
• Lane reduction
• Parallel
parking and/or
parklet lanes
• Wide sidewalks and
amenity zones
• Enhanced landscape
and shade ideas
• Discourages through
truck traffic
Stages of Monroe Reconstruction
STAGE
PROJECT
Status
Dates
Stage 1
Monroe Demonstration Restriping Project
Completed
FY23-24
Stage 1
City Hall East Parking Lot
Completed
FY24
Stage 2
Landscape Demonstration: Downtown Enhancement Program
Completed
FY25-26
Stage 3
Interim Landscaping: Downtown Enhancement Program
In Progress
FY26-27
Stage 4a
Design Concept Review: Monroe Reconstruction and Utility Plan
Pending
FY26-27
Stage 4b
Storm Drain and Fiber: Downtown Storm Drain Project
Pending
FY27+
Stage 4c
Utility Installation: Downtown Improvement Program - Utilities
Pending
~FY30+
Stage 5
A New Cityscape: Downtown Improvement Program - Streetscape
Pending
~FY30+
Stage 1: Monroe Restriping
Complete
• Remove layer of asphalt and pavement
marking and seal cracks
• New designated truck route established
• Speed limit reduced
• Seal coat street
• Repaint pavement markings
• Restriping of Monroe Ave. to two lane road
• Additional parallel parking added
• Designated driveway access striped
• Painting of Parklet zones
• Crosswalk reconstruction
Stage 2: Landscape Demonstration
Demonstration Project: 5th St. to 6th St.
•
Box trees installed on north and south sides
•
Tree boxes framed & wrapped
•
Pedestals to support drainage
•
Planter Boxes Installed along the block
•
Smaller boxes focused on chicanes
•
Larger boxes staged between trees
•
Chicanes were cleaned and enhanced
•
Sample parklet installed and furnished
Stage 3: Interim Landscape and Streetscape
Design Phase - Design Concept Review evaluates options & challenges of reconstruction
•
Limits of construction
•
Existing underground utilities and their locations
•
Capacity and utility needs for future build out
Stormwater Management, Fiber, and City Utilities
• Utility: Forecast and design utility improvement to support anticipated development along Monroe
(Utilities considered: water, sewer, natural gas, power, and fiber)
Construction Phasing and Coordination
•
Ongoing phasing efforts with storm drain, hardscape, & future utility planning for efficient use of
resources and minimal impact to Monroe
Stage 4: Design Concept and Utility Work
Stage 5: Final Streetscape Installation
Mill Avenue 1950s and Today
Historic Main Street (circa 1950)
DSAP Vision for Monroe Avenue
Buckeye Police Department
• The Buckeye Police Department compared
data along Monroe Ave. through
downtown before and after restriping
• Studying the impact to public safety,
specifically:
• Speeding citations
• Accidents
• Response times
Buckeye Police Department
Decrease in speeding from FY24 (14) to FY25 (11)
(for the first nine months)
Decrease in accidents from FY24 (30) to FY25 (18)
(for the first nine months)
*FY25 represents first nine months only
*
*
Buckeye Police Department
• Six months of corridor data collected
before and after the downtown restriping
project
• Determined the restriping did not have a
negative effect on police response times
in downtown
Downtown Business Revenue
Businesses along Monroe Ave
• 1st Street to Narramore/Apache
• One block North to Roosevelt
• One block South to Jackson
Revenue continues to increase in downtown
Travel Time Effects
2025
2024
55s
15s
12am 2am 4am 6am 8am 10am 12pm 2pm 4pm
6pm 8pm 10pm
15s
9th Street Pedestrian Crossing
• Safety is top priority & frequently
expressed community concern
• Study focused on students and
pedestrians crossing Monroe Ave. at 9th
• Findings support installation of a HAWK
Signal for enhanced safety
• Installed shoulder signals immediately
• Full overhead system on order for
installation in the coming year
Scenario 1: Original 4-Lane Highway
Scenario 2: Existing 2-Lane Configuration
Scenario 2: Existing 2-Lane Configuration
Scenario 3: Modified 3-Lane w/Center Turn
Scenario 3: Modified 3-Lane w/Center Turn
Online and Community Meeting Survey Results
Business Survey Results & Related Stakeholders
•
Value and appreciate slower speeds
•
On-street parking is a priority for customers, but is confusing right now
•
No significant change in business volume, but still monitoring