WT Recovery Well Schedule - prelim 20250415.pdf
Extracted text (via pymupdf)
3054 characters
ID Task Name Duration Start Finish Notes 1 White Tank Recovery Well 688 days Fri 12/27/24 Tue 8/17/27 2 IGA Executed 0 days Fri 12/27/24 Fri 12/27/24 3 Draft ARPA Grant Application 25 days Fri 2/21/25 Thu 3/27/25 4 Establish CIP Project 28 days Fri 3/28/25 Tue 5/6/25 5 Finalize Project SOW and Budget 10 days Fri 3/28/25 Thu 4/10/25 6 Draft CAR to Establish Project 18 days Fri 4/11/25 Tue 5/6/25 7 Council Meeting/Approval 0 days Tue 5/6/25 Tue 5/6/25 8 Preconstruction 255 days Wed 5/7/25 Tue 4/28/26 9 Design Solicitation 55 days Wed 5/7/25 Tue 7/22/25 10 Draft Design Solicitation 5 days Wed 5/7/25 Tue 5/13/25 11 Procurement Review 10 days Wed 5/14/25 Tue 5/27/25 12 Solicitation 10 days Wed 5/28/25 Tue 6/10/25 13 RFQ review 10 days Wed 6/11/25 Tue 6/24/25 14 Interviews 5 days Wed 6/25/25 Tue 7/1/25 15 Contract Negotiations 5 days Wed 7/2/25 Tue 7/8/25 16 Procurement/Legal Review/CM Sign 10 days Wed 7/9/25 Tue 7/22/25 17 Execute contract 0 days Tue 7/22/25 Tue 7/22/25 18 Design 120 days Wed 7/23/25 Tue 1/6/26 19 Permitting 60 days Wed 1/7/26 Tue 3/31/26 20 Site Acquisition 160 days Wed 9/17/25 Tue 4/28/26 21 Establish ROW/Easements 100 days Wed 10/15/25 Tue 3/3/26 22 Construction 550 days Wed 7/9/25 Tue 8/17/27 23 CM@R Solicitation 60 days Wed 7/9/25 Tue 9/30/25 24 Draft CMAR Solicitation 10 days Wed 7/9/25 Tue 7/22/25 25 Procurement Review 10 days Wed 7/23/25 Tue 8/5/25 26 Solicitation 15 days Wed 8/6/25 Tue 8/26/25 27 RFQ review 10 days Wed 8/27/25 Tue 9/9/25 28 Interviews 5 days Wed 9/10/25 Tue 9/16/25 29 Procurement/Legal Review/CM Sign 10 days Wed 9/17/25 Tue 9/30/25 30 Execute Contract 0 days Tue 9/30/25 Tue 9/30/25 31 Preconstruction Services 110 days Wed 10/1/25 Tue 3/3/26 32 Order Long Lead Items 240 days Wed 11/12/25 Tue 10/13/26 33 Construction 340 days Wed 4/29/26 Tue 8/17/27 34 Mobilization 20 days Wed 4/29/26 Tue 5/26/26 35 Clear Site 20 days Wed 5/27/26 Tue 6/23/26 36 Drilling 120 days Wed 6/24/26 Tue 12/8/26 Bore/Test/Final 37 Offsites (Transmission Line/Power) 80 days Wed 5/27/26 Tue 9/15/26 38 Wellsite Underground 60 days Wed 12/9/26 Tue 3/2/27 39 Secure Site 40 days Wed 3/3/27 Tue 4/27/27 Perimeter Enclosure 40 Equipment Placement/Energize 80 days Wed 3/3/27 Tue 6/22/27 41 Closeout 40 days Wed 6/23/27 Tue 8/17/27 Punchlist, Training 42 Project Complete 0 days Tue 8/17/27 Tue 8/17/27 12/27 5/6 7/22 9/30 8/17 Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Q Task Split Milestone Summary Project Summary Group By Summary Rolled Up Task Rolled Up Critical Task Rolled Up Milestone Rolled Up Progress External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Task Progress Page 1 Project: WT Recovery Well Sche Date: Tue 4/15/25