WT Recovery Well Schedule - prelim 20250415.pdf

City of Buckeye — Regular Council Meeting (2025-05-06)

View PDF Meeting page

Extracted text (via pymupdf) 3054 characters
ID
Task Name
Duration
Start
Finish
Notes
1
White Tank Recovery Well
688 days
Fri 12/27/24
Tue 8/17/27
2
IGA Executed
0 days
Fri 12/27/24
Fri 12/27/24
3
Draft ARPA Grant Application
25 days
Fri 2/21/25
Thu 3/27/25
4
Establish CIP Project
28 days
Fri 3/28/25
Tue 5/6/25
5
Finalize Project SOW and Budget
10 days
Fri 3/28/25
Thu 4/10/25
6
Draft CAR to Establish Project
18 days
Fri 4/11/25
Tue 5/6/25
7
Council Meeting/Approval
0 days
Tue 5/6/25
Tue 5/6/25
8
Preconstruction
255 days
Wed 5/7/25
Tue 4/28/26
9
Design Solicitation
55 days
Wed 5/7/25
Tue 7/22/25
10
Draft Design Solicitation
5 days
Wed 5/7/25
Tue 5/13/25
11
Procurement Review
10 days
Wed 5/14/25
Tue 5/27/25
12
Solicitation
10 days
Wed 5/28/25
Tue 6/10/25
13
RFQ review
10 days
Wed 6/11/25
Tue 6/24/25
14
Interviews
5 days
Wed 6/25/25
Tue 7/1/25
15
Contract Negotiations
5 days
Wed 7/2/25
Tue 7/8/25
16
Procurement/Legal Review/CM 
Sign
10 days
Wed 7/9/25
Tue 7/22/25
17
Execute contract
0 days
Tue 7/22/25
Tue 7/22/25
18
Design
120 days
Wed 7/23/25
Tue 1/6/26
19
Permitting
60 days
Wed 1/7/26
Tue 3/31/26
20
Site Acquisition
160 days
Wed 9/17/25
Tue 4/28/26
21
Establish ROW/Easements
100 days
Wed 10/15/25 Tue 3/3/26
22
Construction
550 days
Wed 7/9/25
Tue 8/17/27
23
CM@R Solicitation
60 days
Wed 7/9/25
Tue 9/30/25
24
Draft CMAR Solicitation
10 days
Wed 7/9/25
Tue 7/22/25
25
Procurement Review
10 days
Wed 7/23/25
Tue 8/5/25
26
Solicitation
15 days
Wed 8/6/25
Tue 8/26/25
27
RFQ review
10 days
Wed 8/27/25
Tue 9/9/25
28
Interviews
5 days
Wed 9/10/25
Tue 9/16/25
29
Procurement/Legal Review/CM 
Sign
10 days
Wed 9/17/25
Tue 9/30/25
30
Execute Contract
0 days
Tue 9/30/25
Tue 9/30/25
31
Preconstruction Services
110 days
Wed 10/1/25
Tue 3/3/26
32
Order Long Lead Items
240 days
Wed 11/12/25 Tue 10/13/26
33
Construction
340 days
Wed 4/29/26
Tue 8/17/27
34
Mobilization
20 days
Wed 4/29/26
Tue 5/26/26
35
Clear Site
20 days
Wed 5/27/26
Tue 6/23/26
36
Drilling
120 days
Wed 6/24/26
Tue 12/8/26
Bore/Test/Final
37
Offsites (Transmission Line/Power) 80 days
Wed 5/27/26
Tue 9/15/26
38
Wellsite Underground
60 days
Wed 12/9/26
Tue 3/2/27
39
Secure Site
40 days
Wed 3/3/27
Tue 4/27/27
Perimeter Enclosure
40
Equipment Placement/Energize
80 days
Wed 3/3/27
Tue 6/22/27
41
Closeout
40 days
Wed 6/23/27
Tue 8/17/27
Punchlist, Training
42
Project Complete
0 days
Tue 8/17/27
Tue 8/17/27
12/27
5/6
7/22
9/30
8/17
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Quarter
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Quarter
2nd Quarter
3rd Quarter
4th Q
Task
Split
Milestone
Summary
Project Summary
Group By Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical Task
Progress
Page 1
Project: WT Recovery Well Sche
Date: Tue 4/15/25