PLANNING AND ZONING BOARD 
STUDY SESSION MINUTES 
 
May 13, 2026 
 
The Planning and Zoning Board of the City of Mesa met in the Study Session room at City Hall, 20 East 
Main Street, on May 13, 2026, at 3:31 p.m. 
 
BOARD PRESENT 
BOARD ABSENT 
 
STAFF PRESENT 
Benjamin Ayers, Chairperson 
Troy Peterson, Vice Chairperson* 
Jayson Carpenter, Boardmember 
Jeff Pitcher, Boardmember* 
 
Jamie Blakeman, Boardmember 
Chase Farnsworth, Boardmember 
Genessee Montes, Boardmember 
 
 
 
 
 
Evan Balmer 
Kirstin Dvorchak 
Cassidy Welch 
Danika Heying 
 
(*Participated in the meeting through the use of video conference equipment) 
 
 
 
Chairperson Ayers conducted a roll call. 
 
Chairperson Ayers excused Boardmember Farnsworth and Boardmember Montes from the 
entire meeting. 
 
1. 
Staff update. 
 
There were no staff updates.  
 
2. 
Review and discuss items listed on the Public Hearing agenda for May 13, 2026. 
 
Assistant Planning Director, Evan Balmer, reviewed agenda Item 3-a, ZON25-00626. "NTT 
Mesa PH10" 170± acres located at the northeast corner of East Pecos Road and the 
South Crismon Road alignment. Rezone from Light Industrial with a Planned Area 
Development Overlay (LI-PAD) to Light Industrial with a new Planned Area Development 
Overlay (LI-PAD), Council Use Permit and Major Site Plan Modification. This request will 
allow for an approximately 2,257,581± square foot Data Center development. (District 6) 
on the Planning and Zoning Board Public Hearing agenda and displayed a PowerPoint 
presentation. (See Attachment 1) 
 
Mr. Balmer presented the case on behalf of Senior Planner, Joshua Grandlienard, providing an 
overview of the three requests for the NTT Mesa PH 10 project. He provided historical context, 
noting that a data center was previously approved on the site in 2024 with a CUP for a separate 
substation (major utility), which has since expired. He explained that because the end user has 
changed, modifications are being requested to tailor the site plan to the new use. (See 
Attachment 1)

Planning and Zoning Board Study Session 
May 13, 2026 
Page 2 
Mr. Balmer pointed out that the General Plan designation for the 170-acre site is Industrial, the 
place type is Industrial, and the growth strategy is Evolve. He clarified that the project is phrased 
as "warehousing and storage" because the application was submitted just prior to the effective 
date of the city's data center specific ordinance, meaning it is being reviewed under the previous 
ordinance. (See Page 4 of Attachment 1) 
 
Mr. Balmer displayed the proposed site plan, highlighting seven data center buildings on the 
west side of the site, a Salt River Project (SRP) substation, and an NTT-specific substation. He 
noted that generators are located internally behind the buildings, and access includes two points 
on Pecos Road and four points on Crismon Road. He stated that the applicant is proposing to 
maintain the previously approved PAD deviations regarding height, setbacks, and solid waste 
requirements, with an update to the parking ratio (one space per 7,270 square feet) to reflect 
the lower parking demands of the new end user compared to the previously approved office 
building. (See Page 6 of Attachment 1) 
 
Mr. Balmer presented the landscape plan, identifying tree species such as Blue Cypress, Palo 
Blanco, and Texas Red Bud, alongside a variety of shrubs. He also displayed building 
elevations and color renderings, noting that Building 1 faces State Route 24, while Buildings 2 
through 7 are the same building replicated throughout the site. He confirmed the plans were 
reviewed by the Design Review Board in December and minor comments on the elevations 
have been addressed. Staff recommended approval with conditions. (See Pages 8 through 15 
of Attachment 1) 
 
In response to questions from Vice Chair Peterson regarding significant changes from the 
previous plan, Mr. Balmer reiterated that the northernmost building was changed from a large 
office building to a data hall, resulting in less required parking and a reduction in the open space 
and employee amenities that the previous user had emphasized. 
 
In response to questions from Boardmember Pitcher regarding a "future water well" shown on 
the site plan and whether the data center would use a high volume of water, Mr. Balmer clarified 
that the well is a City of Mesa facility dedicated through an agreement with the property owner 
to serve the general area, not the data center specifically. 
 
Asif Kazimi, representing the applicant and design team, addressed the Board to clarify that the 
facility will utilize an internal, closed-loop chiller system on the roof of each building rather than a 
campus-wide resource system, thereby minimizing water consumption. 
 
In response to questions from Boardmember Carpenter regarding the right-of-way for Crimson 
Road and Pecos Road, Mr. Balmer and staff explained that the city is working with adjacent 
property owners via development agreements to build Crismon Road to its full right-of-way to 
align with the construction timing of State Route 24. Staff confirmed that the City of Mesa is 
requesting a 75-foot right-of-way along Pecos Road, which will encompass the existing 33-foot 
and 22-foot highway easements. 
 
Chairperson Ayers raised concerns regarding the landscape plan, stating that the planting 
density along Pecos Road appeared too thin and that the selected species (such as the Blue 
Cypress and the small-scale Palo Blanco) were inappropriate or lacked the scale necessary for 
a project of this magnitude in Arizona. 
 
Mr. Balmer noted that while the applicant met the required plant count, staff would support 
adding a condition to adjust the species to more drought-tolerant, desert-adapted varieties and

Planning and Zoning Board Study Session 
May 13, 2026 
Page 3 
to redistribute them to create a fuller appearance. He noted that the city’s transportation 
department maintains a preferred plant list for the right-of-way that prioritizes low-water use. 
Following a brief discussion, the Board expressed consensus and support for modifying the 
landscape conditions to address species appropriateness and density. 
3.
Adjourn.
Without objection, the Planning and Zoning Board Study Session adjourned at 3:50 p.m.
I hereby certify that the foregoing minutes are a true and correct copy of the minutes of the Planning 
and Zoning Board Study Session meeting of the City of Mesa, Arizona, held on the 13th day of May 
2026. I further certify that the meeting was duly called and held and that a quorum was present. 
_________________________________________
BENJAMIN AYERS, CHAIRPERSON 
DH 
(Attachments - 1)

Planning and Zoning Board
City of Mesa

ZON25-00626
NTT PH10
Josh Grandlienard, AICP

Location
DEVELOPMENT SERVICES
3
•
10126 E. Pecos
•
170± parcel
•
North side of Pecos Road
•
East side of Crismon Road 
Alignment

General Plan
•
Industrial Placetype
•
Evolve Strategy
•
Warehousing and Storage is a 
Principal Use
4
DEVELOPMENT SERVICES

5
Site Photos
Looking northwest towards the site
Looking northeast towards the site
DEVELOPMENT SERVICES

• 7 Data Center buildings
• 2,257,581 total sq. ft.
• Generators located 
internally
• 2 access points onto Pecos 
Road Rd.  and 4 from future 
Crismon Road Alignment
6
DEVELOPMENT SERVICES
Site Plan

• Trees: Blue Cypresses, Palo 
Blanco, Texas Redbud, 
Mulga, Willow Acacia, Etc. 
• Shrubs: Brittlebush, 
Creosote Buse, Green Cloud 
Texas Sage, Jojoba, Tuscan 
Blue Rosemary, Etc. 
7
DEVELOPMENT SERVICES
Landscape Plan

8
DEVELOPMENT SERVICES
Elevations – Building 1

9
DEVELOPMENT SERVICES
Elevations – Building 1

10
DEVELOPMENT SERVICES
Elevations – Buildings 2-7

11
DEVELOPMENT SERVICES
Elevations – Buildings 2-7

12
DEVELOPMENT SERVICES
• Color Integrated Tilt-up 
Panels with formliners
• Metal Composite 
• Formed Metal Panels
Materials & Colors

13
DEVELOPMENT SERVICES
Renderings
Looking southeast from SR 24

14
DEVELOPMENT SERVICES
Renderings
Looking southwest from SR 24

15
DEVELOPMENT SERVICES
Recommendation
Approval with conditions

Planning and Zoning Board
City of Mesa