DocuSign Envelope ID: 64C820E4-5131-4300-B87E-A2DAC505E0F5 IGE ORDER - BOS APPROVAL
Maricopa County Deparment of Transportation

Date: 6/1/2023 Change Order Number: 22 Amount: $355,522.11 Agenda Item No. C-64-21-084-X-00

Contract No:|2022-011 Work Order No: TT0495

Consultant Name:| NESBITT CONTRACTING CO INC

Project Name:} Lower Buckeye Road - 71st Ave to 67th Ave
Intial Amount: $3,466,986.80| Contract Notice to Proceed Date: 1/24/2022 Total Prior Change Orders: $998,557.86

The Contractor, by mutual agreement of the parties, shall make the herein described changes to the plans and specifications or do the following described work not included in the plans
and specifications on the above-identified contract. All other contract terms and conditions remain unchanged.

This change order is necessary to compensate the Contractor for the additional overhead, quality control and traffic control costs associated with extended
construction time due to substantial differing site conditions. In addition, this change order will further modify the contract amount to reflect the net difference
between the bid quantities and the as-built quantities.

With this Change Order, the total amount of this contract has increased 39.06%
By reason of this change 0 days extension of time will be allowed for construction work. The construction work completion date is: 3/24/2023
By reason of this change 0 days extension of time will be allowed for administrative purposes, after the time allowed for construction work.
With inclusion of this change, this contract has a revised cumulative performance period of 544 days.
The contract completion date is: 7/22/2023

The following financial information is submitted:

Initial Contract Amount $3,466,986.80

Amended Contract Amount w/ previous change orders $4,465,544.66

Current Change Order Request $355,522.11

Amended Contract Amount w/ current change order $4,821,066.77

We, the undersigned Contractor, having given careful consideration to the change(s) proposed, hereby agree that upon execution of this change order that we will provide all
equipment, furnish all material (except as noted in the Bid Line Item Sheet), perform all work specified in Bid Line Item Sheets; and we will accept as full payment therefore the prices
shown in Bid Line Item Sheet.

IN WITNESS WHEREOF, the parties herein have executed this Contract Change Order:

‘DocuSigned by:
Principal (Signature) Cr Buk
Printed Name GregiBéateaee7e40c...

Title Project Manager
Date 67572025

MARICOPA COUNTY DEPARTMENT OF TRANSPORTATION

‘DocuSigned by: DocuSigned by:
‘ 6/5/2023 6/5/2023
(Ty a zn ‘on a Z

Conlstrt@@eQPSQ5PREMBIe) - Doug Lattin Date Const OtArasAviaaeafor - Shawn Coleman Date
DocuSigned by: DocuSigned by:

Al lewichs 6/5/2023 Al Lewicht 6/5/2023
BranctrtaeaZgereamaéfa- Lewicki Date Divisionsbdepagenadtlana Lewicki Date
| certi dbingtange is within the limits authorized by the Maricopa County | certii sbensipiha FN available to accomplish this Change Order
Produrement Code

6/13/2023 oA 6/12/2023
Busty bruni dluwtle williams
Contract SEAneeSBBverly Krumm Date CIP-CASFPRIOR 97KRZger - Charles Williams Date
DocuSigned by:
5 6/12/2023
(sw Gutiurey,
Deputy-TFATRSBITEIIA Director - Jesse Gutierrez Date IGA PM (if applicable) - Date
COUNTY APPROVAL
RECOMMG ND GHddBy:: ACCEPTED AND APPROVED:
‘ 6/12/2023
Jesse Gutiuny
TransponttiGASTeMHEngineer - Jesse Gutierrez Date Chairman, Board of Supervisors - Date
LEGAL REVIEW ATTEST:

Approved as to form and within the powers and authority granted under the laws
of the StatDofsv@igormtos the Maricopa County Department of Transportation.

Nkolaus Duke 6/15/2023

Deputy C&QHiFRREtHa9— Date Clerk of the Board - Date

DocuSign Envelope ID: 64C820E4-5131-4300-B87E-A2DACS5O5E0F5

Maricopa County Department of Transportation
Sheet 1 of 2
Bid Line Items Sheet
CONSTRUCTION CHANGE ORDER NO. 22
Provide description of work to be done, estimate of quantities, and prices to be paid, segregate between additional work at contract price, agreed price and|
actual cost. Unless otherwise stated, rates for rental of equipment on actual cost work cover only such time as equipment is actually used and no allowance]
will be made for idle times.

. nary Estimated As-Built Difference 7 Difference
Bid Item No. Description Unit Quantity Quantity () Unit Price (+)
104.04000-22 Partnering Allowance 0 -0.687716 (0.69) $ 5,000.00 ($3,438.58)
107.01501-22 Community Relations Support Allowance 0 -1.00 (1.00) $ 10,000.00} — ($10,000.00)
407.02000-22 AZPDES Allowance 0) 0.240381 0.240381 $ 10,000.00 $2,403.81
107.02010-22 eae With MS Stormwater Allowance 0 0.008333 0.008333 =| $ 3,000.00 $25.00

egulation
407.02110-22 Environmental Mitigation Compliance] Allowance 0 2.361614 2.361614 $ 5,000.00 $11,808.07
205.01150-22 Roadway Excavation cy 0 27.00 27.00 $ 30.00 $810.00
310.03000-22 Aggregate Base Course Ton 0 -420.00 (420.00) $ 19.00 ($7,980.00)
317.01000-22 Asphalt Milling sy 0 853.00 853.00 $ 1.70 $1,450.10
321.01302-22 AC Pavement (Superpave 3/4” Mix HT) Ton 0 137.61 137.61 $ 78.00 $10,733.58
325.10375-22 ARAC Pavement High Traffic / PMTR Ton 0 232.46 232.46 $ 125.00 $29,057.50
329,01000-22 Bituminous Tack Coat SS1H Diluted Ton 0 -9.70 (9.70) $ 550.00 ($5,335.00)
334,06000-22 Microsurfacing sy 0) -1392.00 (1,392.00) $ 7.00 ($9,744.00)
338.01000-22 Pring Adlustnent tor Binuinous Allowance 0 78102.01 78,102.01 $ 4.00 $78,102.01
Materials
340.01401-22 Driveway Entrance COP Det P1255-1 SF C) -589.00 (589.00) $ 8.00 ($4,712.00)
340.01600-22 ponerere Apron & Valley Gutter MAG SF 0 428,00 128,00 $ 41.00 $1,408.00
Conc. Apron & VG MAG Det 240
340.01601-22 (100% Comp) SF 0 128,00 128.00 $ 2.90 $371.20
345.01100-22 Adjust Frame’& Cover te Grade MAG Each 0 9.00 9.00 $ 670.00 $6,030.00
Det 422
345.01105-22 pau Frame:&: Cover to. Grade Det Each 0 A (1.00) $ 8,300.00] ($8,300.00)
401.01100-22 prvenped OFF Duly Law Enforsoment | au acancs 0 9.738468 9.738468 $ 14,200.00] $109,070.84
Changeable Msg Board for Public
401.06100-22 Notlfication Day 0 685.00 685,00 $ 42.00 $28,770.00
430.43000-22 Decomposed Granite 3 inches Thick sy 0 147.00 147.00 $ 6.80 $999.60
465.01003-22 a oe Alum,'Sign Panel Diamond SF 0 0.50 (0.50) $ 47.70 ($23.85)
472.61302-22 Pole Foundation, Type GP, COP Std Each 0 1.00 1.00 $ 4,600.00 $4,600.00
Det TS-2-2
523.15510-22 SRP Concrete Pipe Collar Det D3 Each 0 -1.00 (1.00) $ 3,000.00 ($3,000.00)
610.27510-22 Adjust Fire Hydrant COP P1360 Each 0 2.00 2.00 $ 600.00 $1,200.00
618.00818-22 Pipe Plug MAG Det 427 18 inch Pipe Each 0 -1.00 (1.00) $ 4,200.00 ($1,200.00)
Total this Sheet ONLY $233,106.28

Revised: 5/29/2023

DocuSign Envelope ID: 64C820E4-5131-4300-B87E-A2DAC5OS5E0F5

Maricopa County Department of Transportation
Sheet 2 of 2
Bid Line Items Sheet
CONSTRUCTION CHANGE ORDER NO. 22
Provide description of work to be done, estimate of quantities, and prices to be paid, segregate between additional work at contract price, agreed price and]
actual cost. Unless otherwise stated, rates for rental of equipment on actual cost work cover only such time as equipment is actually used and no allowance,
will be made for idle times.
5 anti 7 Estimated As-Built Difference i Difference
Bid Item No. Description Unit Quantity Quantity (+) Unit Price Gr)
Additional Costs Due to Changed
640.15000-22 Condition Delays Lump Sum 0 1.00 1.00 $ 127,719.23 $127,719.23
700.01000-22 High Binder Content Penalty Each o 4577.64 4,577.64 $ (1.00) ($4,577.64)
700,02000-22 High Lab Voids Penalty Each 0 725.76 725.76 $ (1.00)| ($725.76)
0.00 $0.00
0.00 $0.00
0.00 $0.00
0.00 $0.00
0.00 $0.00
0.00 $0.00
Total this Sheet ONLY $122,415.83
Total For ALL Sheets $355,522.11

Revised: 5/29/2023

DocuSign Envelope ID: 64C820E4-5131-4300-B87E-A2DAC505E0F5

Project #:
Contract #:

Maricopa County Department of Transportation
ATTACHMENT A (Change Order Scope)
TT0495 Project Name: Lower Buckeye Rd (71st Ave to 67% Ave)
2022-011 Change Order#: 22

Reason:

This change order is necessary to compensate the Contractor for the additional overhead, quality
control and traffic control costs associated with extended construction time due to substantial
differing site conditions. In addition, this change order will further modify the contract amount to
reflect the net difference between the bid quantities and the as-built quantities.

Description:

EXTENDED CONSTRUCTION TIME: Per the original TT0495 project plans, the entire north half of
Lower Buckeye Rd, including all of the 67 Ave work north of Lower Buckeye Rd, was designated to
be constructed in Phase 1. If construction had been allowed to proceed in this manner, the north
portion of Lower Buckeye Rd and north half of the 67 Ave intersection would have been complete
and open while Phase 2 on the south side was allowed to progress uninhibited. However, as
addressed in multiple previous TT0495 change orders and RFI responses, the mid-project addition of
a very large reinforced concrete drainage junction structure (MH19) 20 feet below the centerline of
the 67' Ave at the Lower Buckeye Rd intersection, in conjunction with several directly related fiber
optic and power utility conflicts, rendered the defined project phasing obsolete, and resulted in 2
months of delays. This initial delay imposed a cascading effect in that all of the asphalt rubber final
surface paving was subsequently pushed from the originally scheduled warm late September/early
October 2022 timeframe into the late November/early December 2022 timeframe where cold and wet
weather caused an additional 1 month of delay. Still, the project’s final walk-through was conducted
on December 19, 2022, after which substantial completion was granted by MCDOT, leaving only a few
minor items to complete. With the original and to date change order work substantially complete, the
City of Phoenix, who will ultimately annex this portion of Lower Buckeye Rd, introduced additional
new project scope as a condition of their final approval. The added scope involved the need for
redesigns, new submittals, and re-work of some project features that had already been built per the
originally approved plans. Completing this additional work resulted in an additional 2 months of
delays. For the reasons discussed above, change orders, throughout the project duration,
cumulatively extended the project construction end date from September 16, 2022 to March 24, 2023,
of which 5 months were a result of impacts caused by additional work not originally depicted in the
contract documents. Compensation for the extra work was fully accounted for in the previous 21
change orders, except for 2 months of Contractor overhead, 4 months of quality control, and 4 months
of additional traffic control.

A single new negotiated Lump Sum pay item in the amount of $127,719.23 is being created to provide
compensation for all additional overhead, quality control, and traffic control costs incurred by the
Contractor, except for that which was already included in previous change orders. No additional
contract time is being allowed for this change order.

FINAL QUANTITY ADJUSTMENT: The net change of existing bid item quantities is tabulated in the
Change Order 22 document. The cumulative cost of the net bid item changes is $ 227,802.88.

Bid Items:

Item No.

Description Unit| Qty Unit Price Amount

640.15000-22 | Additional Costs Due to Extended Contract Time | LS| 1 $127,719.23 $127,719.23

Multiple-22

Final Quantity Adjustment (Itemized in CO #22) $227,802.88 | $227,802.88

Total $355,522.11

| Cost:

| $355,522.11 [ Time: | 0 Days

| Specification: | None specified

| Subcategories: Not Preventable

O_ Utility Conflict 1 Right-of-Way Conflict & Quantity Adjustment

Work out of Scope (MCDOT) O Work out of Scope (Other Jurisdiction)

O_sPlan Revisions O Changed Physical Condition O Environmental

O_ Value Engineering O Other:
Contacts:
Alana Lewicki, P.E. Construction Manager MCDOT | Concurred 5/23/2023
Shawn Coleman, P.E. Construction Engineer MCDOT | Concurred 5/23/2023