Amended and Restated Development Agreement

City of Chandler — Study Session (2026-09-14)

View PDF Meeting page

Extracted text (via pymupdf) 85517 characters
66184353.2  
-1- 
 
When recorded, return to: 
 
Chandler City Attorney’s Office  
City of Chandler  
Post Office Box 4008, Mailstop 602 
Attn: City Attorney 
 
 
 
 
 
 
 
AMENDED AND RESTATED 
DEVELOPMENT AGREEMENT 
 
SITE 7 
 
 
CITY OF CHANDLER, 
an Arizona municipal corporation 
 
and 
 
One Chandler Owner, LLC,  
a Delaware limited liability company  
 
and 
 
SAM CDT I LLC, a Delaware limited liability company 
 
 
Approved by City Council on September 17, 2026

-2- 
AMENDED AND RESTATED  
DEVELOPMENT AGREEMENT  
 
This Amended and Restated development agreement (the “Agreement”) is made by and 
between the City of Chandler, an Arizona municipal corporation (“City”) and One Chandler 
Owner, LLC, a Delaware limited liability company (“One Chandler Owner”) and SAM CDT I 
LLC, a Delaware limited liability company (“Developer”). This Agreement is effective September 
17, 2026 (the “Effective Date”). City, One Chandler Owner, and Developer will be referred to in 
this Agreement collectively as “Parties” and individually as a “Party.”  Following Land Closing, 
references to the “Parties” mean City and Developer only, except where One Chandler Owner is 
expressly referenced. 
RECITALS 
The Parties recite and state the following, each of which is a material term and provision of this 
Agreement: 
A. 
One Chandler Owner and City entered into a Development Agreement dated 
October 27, 2022, and recorded in the Maricopa County Recorder’s Office as document number 
2022-084053, as amended by the First Amendment to Development Agreement dated April 2, 
2025, and recorded in the Maricopa County Recorder’s Office as document number 2025-0185971 
(collectively, both the agreement and the first amendment will be referred to as the “2022 
Agreement”) governing real property legally described in the attached Exhibit A (the 
“Property”).  
B. 
Under the terms of the 2022 Agreement, One Chandler Owner could not sell, 
assign, or transfer its interest in the 2022 Agreement to another entity or person without the express 
written consent of City.  One Chandler Owner desires to assign the 2022 Agreement, as amended 
and restated by this Agreement, to the Developer, City expressly consents to the assignment in 
accordance with the terms and provisions of this Agreement, and Developer agrees to assume all 
of the One Chandler Owner’s obligations under the 2022 Agreement, as amended and restated by 
this Agreement. 
C. 
This Agreement is entered into by and between One Chandler Owner, City, and 
Developer for the purpose of amending, restating, and replacing in its entirety the 2022 Agreement 
and assigning it to Developer and, upon execution, this Agreement supersedes and completely 
replaces the 2022 Agreement, except that the 2022 Agreement is reinstated if this Agreement 
becomes null and void under Section 2.6.   
D. 
Before the 2022 Agreement was executed by the Parties, the City owned real 
property equaling 1.77 acres along Buffalo Street, from Arizona Avenue to Washington Street, 
within the City of Chandler, Maricopa County, Arizona as legally described in the attached 
Exhibit B (the “City Property”). The City Property was acquired by the City as part of its plan to 
redevelop and revitalize the downtown area of the City as described in the Chandler 
Redevelopment Area Plan.

-3- 
 
 
 
E. 
Before the 2022 Agreement, One Chandler Owner owned the assembled parcels 
immediately adjacent to the City Property along its north boundary, a legal description of which 
is contained in Exhibit C (the “Developer Property”).  
F. 
The Property is currently zoned Planned Area Development (PAD) under 
Ordinance No. 5062.   
G. 
Developer will acquire the Property and intends to develop it as one development 
known as “One Chandler.”   
H. 
Developer has proposed to build a nine-story, mixed-use structure with three-
hundred and twenty (320) units of housing, 12,000 square feet of office space, 16,000 square feet 
of retail space, and a self-contained parking structure that will complement the area surrounding 
the Property (the “Project”), built in two phases, one for each tower. The Parties believe the 
Project will contribute to the implementation and achievement of the City’s goals of 
redevelopment and revitalization of the City’s downtown area.  
I. 
Developer has submitted an updated development plan for the Project through the 
City’s Administrative Design Review process, which was approved as case number PLA26-0130. 
Throughout this Agreement, the proposal approved by the City will be referred to as the “Proposed 
Development Plan.” 
J. 
The Parties acknowledge that the Property is intended to be developed as an 
integrated Project, built in two phases, and City requires assurance of the timely construction of 
the Minimum Improvements, such that the Parties agree that City will have purchase options on 
the City Property and the Developer Property if Developer does not complete the Minimum 
Improvements according to the timeline contained in this Agreement. 
K. 
The City and Developer acknowledge and agree that redevelopment of the Project 
will result in significant direct and indirect benefits accruing to the City and the general public, 
including, without limitation, increased value of the Property, increased tax revenues, expansion 
of the employment base within the City and incentivizing the redevelopment of the City’s 
downtown. 
L. 
The City has determined that the proposed development of the Property in 
accordance with this Agreement is consistent with the City’s General Plan, the Chandler 
Redevelopment Area Plan, and the PAD zoning under Ordinance No. 5062. 
M. 
This Agreement is intended to set forth certain obligations of the Parties with 
respect to the contemplated redevelopment of the Property, as permitted by Arizona law.  The 
Parties intend for this Agreement to be a “Development Agreement” within the meaning of A.R.S. 
§ 9-500.05 and an agreement to promote economic development activities within the meaning of 
A.R.S. § 9-500.11 and redevelopment of the Chandler Redevelopment Area consistent with A.R.S. 
§ 34-1471 et seq. 
AGREEMENT 
This Agreement amends and restates in its entirety the 2022 Agreement, and this

-4- 
 
 
 
Agreement supersedes and completely replaces the 2022 Agreement.  In consideration of the 
foregoing recitals and representations and the mutual covenants and conditions in this Agreement, 
and for other good and valuable consideration, the receipt and sufficiency of which are hereby 
acknowledged, the Parties agree as follows: 
SECTION 1.  
DEFINITIONS.  In this Agreement, unless a different meaning clearly 
appears from the context: 
1.2 
“Agreement” means this Agreement, as amended or supplemented in writing from 
time to time, and includes all exhibits and schedules attached hereto.  References to Sections or 
Exhibits are to this Agreement unless otherwise qualified. 
1.3 
 “Applicable Laws” means the federal, state, county and local laws (statutory and 
common law), charter provisions, codes, ordinances, rules, regulations, permit requirements, fee 
schedules and assessments, and other requirements and official policies of City which apply to the 
development of all or any part of the Property. 
1.4 
 “Business Day” means any day of the week when the Development Services 
Department is open to the public for the conduct of the department's business. 
1.5 
“Certificate of Completion” means a certificate issued by the City certifying that 
the improvement is substantially completed in accordance with approved plans in accordance with 
Applicable Laws. 
1.6 
“City” means the City of Chandler, an Arizona municipal corporation (and any 
successor public body or officer hereafter designated by or pursuant to law). 
1.7 
“City Code” or “Code” means the Chandler City Code and regulations of the City. 
1.8 
“City Delay” means as defined in Section 3.2(D). 
1.9 
“Completion Deadline” means as defined in Section 3.1(F), which is that 
Developer shall achieve substantial completion of the Minimum Improvements, subject to Force 
Majeure Events and City Delay events,  as set forth by the Completion of Minimum Improvements, 
but in all events no later than May 1, 2028. 
1.10 
“Completion of Minimum Improvements” means the City’s issuance of a 
building permit for the Project, which shall not be unreasonably withheld, conditioned, or delayed. 
1.11 
“Default” means as defined in Section 6.1. 
1.12 
“Design Costs” means as defined in Section 4.12. 
1.13 
“Design Documents” means as defined in Section 4.12. 
1.14 
“Developer” means SAM CDT I, LLC, a Delaware limited liability company, and 
its permitted successors and assigns under Section 7.

-5- 
 
 
 
1.15 
“Fair Market Value” means as defined in Section 4.7. 
1.16 
“Force Majeure Events” means any one or more of the following which prohibits 
or materially interferes with, delays, or alters the performance of the applicable duty under this 
Agreement: strikes or lockouts; shortages of material or transportation fuel (excluding those 
caused by lack of funds) or labor; acts of the public enemy; confiscation or seizure by any 
government or public authority; injunction, restraining order or other court order or decree; 
blockades; insurrections; riots; civil disturbances; epidemics; pandemics; regional or national 
health crises; acts of nature; fires; explosions; nuclear reaction or radiation; radioactive 
contamination; as to Developer, the failure or delay by the City in issuing any approvals, permits 
or certificates required, authorized or contemplated by this Agreement, including a City Delay; 
any delays caused by any utility provider that are not the result of any intentional action or inaction 
by Developer to cause said delay; any other similar cause (excluding those caused by lack of 
funds); and any other event not within the reasonable control of the applicable Party.  
1.17 
“Improvement Reimbursement” means as defined in Section 4.11. 
1.18 
“Improvement Work” means as defined in Section 4.11. 
1.19 
“Land Closing” means as defined in Section 2.5. 
1.20 
“Land Closing Deadline” means as defined in Section 2.6. 
1.21 
“Land Purchase” means as defined in Section 2.5. 
1.22 
“Lender” means any lender providing financing or refinancing to Developer for 
the acquisition, development, or construction of the Property or the Project, and any successor or 
assign of that lender. 
1.23 
“Improvements” means all privately owned buildings and other structures to be 
located on the Property, exclusive of the Minimum Improvements. 
1.24 
“Minimum Improvements” means as described in Section 3.1(A). 
1.25 
“Proposed Development Plan” means the development plan proposed by 
Developer and approved as case number PLA26-0130 for the Project that illustrates and 
demonstrates the general components of the Minimum Improvements and the Project. 
1.26 
“Person” means and includes natural persons, corporations, limited partnerships, 
general partnerships, joint stock companies, joint ventures associations, limited liability 
companies, limited liability partnerships, trusts, land trusts, business trusts or other organizations, 
whether or not legal entities. 
1.27 
“Project” means as defined in Recital H. 
1.28 
“Public Infrastructure Improvements” means as described in Section 5. 
1.29 
“Purchase Options” means as defined in Section 4.1.

-6- 
 
 
 
1.30 
“The Property” means the real property specifically identified on Exhibit A. 
1.31 
“System Development Fee” means any fee owed by Developer in connection with 
the development described herein pursuant to Chapter 38 of the Chandler City Code. 
1.32 
 “Zoning Code” means Chapter 35 of the Chandler City Code. 
SECTION 2. 
ACQUISITION AND DISPOSITION OF PROPERTY. 
2.1 
Purchase. One Chandler Owner purchased the City Property from City after 
executing the 2022 Agreement.  
2.2 
City Property Purchase Price. The purchase price for the City Property was two 
million nine hundred and forty thousand dollars ($2,940,000.00) (the “City Property Purchase 
Price”). 
2.3 
Resale to City. If (i) Developer fails to achieve Completion of Minimum 
Improvements on or before the Completion Deadline, or (ii) a Default by Developer occurs and is 
not cured within the cure periods stated in Section 6.1, City shall have the right, at its option, to 
re-purchase the City Property from Developer for the City Property Purchase Price stated in 
Section 2.2. City shall exercise that right only in accordance with Section 4. 
2.4 
Assignment. Assignment of this Agreement by One Chandler Owner and by 
Developer, and the assumption of the obligations under this Agreement, are governed by Section 
7. 
2.5 
Purchase of the Property by Developer. One Chandler Owner and Developer have 
entered into a purchase and sale agreement under which Developer will acquire the Property from 
One Chandler Owner (the “Land Purchase”). Developer shall use commercially reasonable 
efforts to complete the Land Purchase. The closing of the Land Purchase is the “Land Closing.” 
Developer shall give City written notice of the Land Closing within five (5) Business Days after it 
occurs, together with a copy of the recorded deed conveying the Property to Developer. The 
purchase and sale agreement between One Chandler Owner and Developer is a separate 
instrument. Its terms, performance, and enforcement are not governed by this Agreement, City is 
not a party to it, and City has no obligation or liability with respect to it. Nothing in this Agreement 
obligates City to consent to, approve, or participate in the Land Purchase. 
2.6 
Land Closing Deadline; Agreement Null and Void. Developer shall complete the 
Land Closing on or before the date that is sixty (60) days after the recordation of this Agreement 
(the “Land Closing Deadline”). The Parties may extend the Land Closing Deadline by written 
agreement. If the Land Closing has not occurred on or before the Land Closing Deadline, this 
Agreement is automatically null and void and of no force or effect, without any action by any 
Party, and no Party has any further right, obligation, or liability under it. In that event: (i) the 2022 
Agreement is reinstated and continues in full force and effect as though this Agreement had not 
been executed; (ii) the assignment, assumption, waiver, and releases in Section 7 are of no force 
or effect; (iii) the Purchase Options do not arise, and City has no right under this Agreement to 
acquire the City Property or the Developer Property; and (iv) upon the written request of any Party, 
the Parties shall execute, acknowledge, and record an instrument confirming that this Agreement

-7- 
 
 
 
is null and void and that the 2022 Agreement is reinstated.  Notwithstanding the foregoing, the 
City’s acknowledgment, waiver and release of any default or alleged default of One Chandler 
Owner arising from or relating to the March 31, 2026 Construction Commencement deadline, as 
set forth in Section 3.1(H), shall be effective as of the Effective Date and shall survive any 
termination, nullification or reinstatement contemplated by this Section 2.6. The reinstatement of 
the 2022 Agreement shall not revive, reinstate or otherwise give effect to the May 6, 2026 Notice 
of Default or any claim, default, right or remedy based upon One Chandler Owner’s failure to 
satisfy the March 31, 2026 Construction Commencement deadline. 
2.7 
Developer Ownership and Management. Upon request by City, Developer must 
provide information to City that describes all persons or entities having ownership or management 
of Developer, including a description of the ownership percentages or decision-making authority 
of each person or entity. Developer may not make changes to the ownership percentages or 
management authority of the individuals or entities having control of Developer without the 
written consent of City.  
SECTION 3. DEVELOPMENT OF PROPERTY. 
3.1 
Developer Obligations.   
A. 
Minimum Improvements. Developer shall construct, at Developer’s cost: (i) any 
required utility relocation and improvements; (ii) the water laterals in Buffalo Street and 
Washington Street and the required sewer laterals in Buffalo Street and Chandler Blvd 
shown in the permitted civil plans, (iii) and excavation needed to start construction on the 
underground parking garage (collectively, the “Minimum Improvements”). Minimum 
Improvements located within, or constructed to serve, the public rights-of-way may also 
constitute Public Infrastructure Improvements under Section 5. Developer must construct 
the Minimum Improvements in substantial conformance to the Proposed Development 
Plan unless City and Developer mutually agree in writing upon changes during the plan 
review process.  Failure of the City and Developer to agree on any changes during the 
plan review process constitutes a City Delay event. 
B. 
The construction of the Minimum Improvements as described in this Section A 
shall occur in accordance with the timeline set forth in Section 3.1(F). Developer’s 
compliance with the timing of its provision of the Minimum Improvements and its 
compliance with the Proposed Development Plan were material considerations for City’s 
determination to enter into this Agreement as a method for revitalization and 
redevelopment of the Chandler Redevelopment Area.   
C. 
Alleyway Improvements and License.  Provided there are no conflicts with utilities, 
Developer agrees to improve and incorporate into the Project the alleyway that exists 
between the Project and the adjacent Jack-in-the-Box parcels, identified as parcels 
numbered 303-06-017A and 303-06-075 on the records of the Maricopa County Assessor. 
The alleyway improvements will include paving, lighting, and landscaping to create a safe 
and inviting pedestrian space (the “Alleyway Improvements”). Developer and City will 
execute a separate license agreement (“Alleyway License”) within ninety (90) days of the 
Effective Date for use of the alleyway to govern Developer’s continued use and

-8- 
 
 
 
maintenance obligations for the alleyway property. This ninety (90) day period can be 
extended by written mutual consent.  Developer will maintain the Alleyway 
Improvements during the entire term of the Alleyway License. Developer agrees that this 
maintenance obligation is ongoing during the term of the Alleyway License and will 
continue beyond the termination of this Agreement. If the Parties are unable to execute 
the Alleyway License due to unforeseen circumstances beyond the Parties’ control or due 
to utility clearances and conflicts, the Parties agree that the Alleyway Improvements will 
be removed from the Project and will not be required of Developer under this Agreement. 
At all times during the term of the Alleyway License, City shall maintain ownership of 
the alleyway in fee. Upon termination of the Alleyway License, City will assume all 
maintenance of the alleyway.  City previously delivered to One Chandler Owner a Notice 
of Default dated May 6, 2026 relating to One Chandler Owner’s failure to achieve 
Construction Commencement by March 31, 2026. The Parties desire through this 
Agreement to establish a new development and construction schedule for the Project, to 
supersede the prior construction deadlines contained in the 2022 Agreement, and to 
confirm that One Chandler Owner has no continuing default or liability arising from its 
failure to satisfy the prior Construction Commencement deadline. 
D. 
City Development Standards. Developer shall construct the Minimum 
Improvements according to City’s construction and development standards.  
E. 
Enhanced Municipal Services District. Developer understands that the Property is 
contained within the Downtown Chandler Enhanced Municipal Services District and 
Developer will promptly pay all associated assessments when due. 
F. 
Developer’s Construction Timeline; Completion Deadline. The timely construction 
of the Minimum Improvements is a material part of the consideration provided by 
Developer under this Agreement. Developer shall achieve substantial completion of the 
Minimum Improvements, subject to Force Majeure Events and City Delay events,  as set 
forth by the Completion of Minimum Improvements, but in all events no later than May 
1, 2028 (the “Completion Deadline”).  The Completion Deadline shall be automatically 
adjusted by the corresponding number of days of a Force Majeure Event or City Delay.  
If Developer has not substantially performed items 1-3 by the dates set forth below, City 
may proceed to declare a Default as set forth in Section 6. 
CONSTRUCTION TIMELINE 
ACTION 
TIME PERIOD 
(1) Developer’s submittal of 100% 
completed civil plans for off-site and 
on-site improvements, including the 
water and sewer plans to relocate 
existing utilities  
No later than nine (9) months from the 
Effective Date of this Agreement

-9- 
 
 
 
(2) Developer’s initiation of utility 
relocation work by payment to the 
utility providers to start the utility 
company’s design process 
Twenty (20) Business Days after the 
later of (a) the land closing referenced 
in Section 2.5 of this Agreement, (b) 
receiving an invoice from the 
respective utility provider, and (c) 
approval by Jack-in-the-Box of the 
utility relocation 
(3) Developer’s Completion of 
Minimum Improvements 
Upon City’s issuance of a building 
permit, which shall not be 
unreasonably withheld, conditioned, or 
delayed. Developer must achieve 
substantial completion of the 
Minimum Improvements no later than 
May 1, 2028, subject to Force Majeure 
or City Delay events. 
(4) Developer’s completion of one 
tower 
Thirty-six (36) months after issuance 
of a building permit. 
(5) Developer’s completion of the 
second tower 
Forty-eight (48) months after issuance 
of a building permit. 
 
City further acknowledges and agrees that, upon the Effective Date of this 
Agreement, any default or alleged default of One Chandler Owner arising 
from or relating to the failure to commence construction by March 31, 2026, 
including the default identified in City’s Notice of Default dated May 6, 
2026, is fully cured, waived, released and of no further force or effect.  One 
Chandler Owner is not, and shall not be deemed to be, in Default under the 
2022 Agreement or this Agreement as a result of the failure to satisfy any 
construction commencement or other development deadline arising prior to 
the Effective Date.  Upon the Land Closing, City waives and relinquishes 
any right or remedy against One Chandler Owner arising from or relating to 
any such prior deadline or alleged default, including any right to terminate 
the 2022 Agreement, exercise any repurchase or repossession right, recover 
damages, or exercise any other remedy based thereon. Notwithstanding the 
foregoing, if the Land Closing does not occur, City maintains all rights and 
remedies available under the 2022 Agreement, including the right to 
terminate the 2022 Agreement and exercise its repurchase and repossession 
rights contained therein.  
From and after the Effective Date, compliance with the construction and 
development schedule shall be determined solely by reference to the 
deadlines and requirements expressly set forth in this Agreement, and

-10- 
 
 
 
Developer shall be solely responsible for satisfying such deadlines and 
requirements. 
G. 
Utility Relocation. Developer will seek an agreement with the owner of the Jack-
in-the-Box parcels identified in Section 3.1(C) that allows the existing utilities to be 
relocated across those parcels (the “JIB Agreement”). Developer shall use commercially 
reasonable efforts to reach the JIB Agreement within four (4) months after the Land 
Closing. If Developer reaches the JIB Agreement within that period, Developer shall pay 
the relocation fees charged by the affected utility providers for their design and relocation 
of those utilities. If Developer does not reach the JIB Agreement within that period, 
Developer shall modify the design of the Project as necessary to accommodate the utilities 
without crossing those parcels and City agrees to allow the access required by the 
modified design. City shall not unreasonably withhold, condition, or delay its approval of 
a modified design that complies with this Section, the Zoning Code, the Proposed 
Development Plan, or any requirement otherwise applicable to the Project. If City 
determines that the modified design for the Jack-in-the-Box utility relocation requires 
zoning approval by the City Council, City will make reasonable efforts to expeditiously 
process any applicable zoning application. All zoning decisions are at the legislative 
discretion of the City Council.  
3.2 
City’s Obligations.  
A. 
Coordination Meetings. From the Effective Date through the completion of the 
Improvements, the respective designated representatives of the City and Developer shall 
meet once monthly or upon request of either party to coordinate the development of the 
Project and to otherwise facilitate the orderly development of the Project. This Section 
may be waived upon mutual agreement of the Parties.    
B. 
Rights of Lenders.  City is aware that Developer may obtain financing or 
refinancing for acquisition, development and/or construction of the Property and/or 
Project, in whole or in part, from time to time, by one or more third parties.  The City 
shall, upon written notice by Developer, provide to any Lender an estoppel certificate or 
other document evidencing that this Agreement is in full force and effect and that no Event 
of Default by Developer exists hereunder (or, if appropriate, specifying the nature and 
duration of any existing Event of Default).  Upon reasonable written request by a Lender, 
City will enter into a separate non-disturbance and recognition agreement with the Lender 
in such commercially reasonable form as may be consistent with the provisions of this 
Section and otherwise reasonably acceptable to the City. 
C. 
Alleyway Abandonment. The Project contains an alley bisecting the Developer 
Property. A depiction of the alley contemplated by this section is shown in the attached 
Exhibit D. Developer has submitted a written request to City for the abandonment. 
Adoption of the abandonment ordinance shall remain within the sole legislative discretion 
of the City Council and shall occur only after all statutory and procedural requirements 
have been satisfied. Developer shall provide City with all information, legal descriptions, 
exhibits, maps, and supporting documentation reasonably required by City staff to prepare 
the abandonment ordinance and present it for consideration. Developer may terminate this

-11- 
 
 
 
Agreement if City fails to adopt an ordinance vacating the alley within sixty (60) days the 
Effective Date of this Agreement, or within a timeframe mutually agreed to by the Parties. 
If the Alleyway Abandonment is not approved, this will constitute a City Delay Event 
until such time as the Alleyway Abandonment is approved.  
D. 
Timing for City Approvals.  City agrees to expedite its review of development 
submittals according to the following schedule for granting or issuing its approvals or 
permits (as applicable):  
1. City will provide submittal comments indicating the need for additional 
information or design revisions from Developer within ten (10) working days of 
receipt by City. Design submittals will be deemed “final and complete” when all 
comments by City staff have been addressed to City’s reasonable satisfaction and the 
submittal complies with City Codes and applicable design standards. 
2. City will approve Developer’s civil drawings and issue all permits for on-site and 
off-site work within fifteen (15) Business Days of Developer’s final and complete 
submission to City and payment of all applicable fees. For each round of plan review, 
the City will require comments in twenty (20) Business Days for a first review; ten 
(10) Business Days for second review.  
3. City will approve Developer’s building construction plans and issue all permits for 
construction within fifteen (15) Business Days of Developer’s final and complete 
submission to the City and payment of all applicable fees. For each round of plan 
review, the City will provide comments in twenty (20) Business Days for a first 
review, and ten (10) Business Days for a second review.  
4. The failure of City to reasonably comply with any of the matters listed in this 
Section 3.2(D) is a default by City under this Agreement and shall be a “City Delay.” 
Each review beyond an initial submittal and subsequent resubmittal shall be a City 
Delay.  
SECTION 4. 
CITY PURCHASE OPTIONS 
4.1 
Grant of Purchase Options. If (i) Developer does not achieve Completion of 
Minimum Improvements on or before the Completion Deadline, subject to Force Majeure Events 
and City Delay, or (ii) a Default by Developer that is not cured within the cure periods stated in 
Section 6.1, then City shall have the right, but not the obligation, to purchase (i) the City Property 
on the terms set forth in this Section 4 (the “City Property Option”), and (ii) the Developer 
Property on the terms set forth in this Section 4 (the “Developer Property Option”). The City 
Property Option and the Developer Property Option are referred to in this Agreement collectively 
as the “Purchase Options” and individually as a “Purchase Option.” City may exercise either 
Purchase Option alone or both Purchase Options together. This Section 4 is the exclusive means 
by which City may acquire the City Property or the Developer Property under this Agreement. 
4.2 
Vesting. The Purchase Options vest in City on the earlier of (i) the day after the 
Completion Deadline, if Completion of Minimal Improvements has not occurred by then, or (ii) 
the day after the applicable cure period stated in Section 6.1 expires without cure of a Default by

-12- 
 
 
 
Developer. Developer acknowledges and agrees that time is of the essence for purposes of 
determining Completion of Minimal Improvements. 
4.3 
Termination of Purchase Options. The Purchase Options terminate automatically and 
are of no further force or effect upon Completion of Minimum Improvements. Within ten (10) 
days after Developer’s written request, City shall execute, acknowledge, and deliver to Developer 
a recordable instrument confirming that the Purchase Options have terminated. Developer will 
provide City with a draft of a recordable instrument, which draft will be subject to reasonable 
revision by City in compliance with this Section before recordation. 
4.4 
Exercise. City may exercise either or both of the Purchase Options by delivering 
written notice to Developer at any time within one (1) year after the Purchase Options vest. The 
notice must identify which Purchase Option or Purchase Options City is exercising. The date City 
delivers its written notice is the “Exercise Date.” 
4.5 
City Property Purchase Price. If City exercises the City Property Option, the purchase 
price is the City Property Purchase Price stated in Section 2.2. 
4.6 
Developer Property Purchase Price. If City exercises the Developer Property Option, 
Developer shall convey fee simple title to the Developer Property to City for a purchase price equal 
to the sum of (i) the Fair Market Value of the Developer Property, determined under Sections 4.7 
through 4.10, and (ii) the Improvement Reimbursement, determined under Section 4.11 (together, 
the “Developer Property Purchase Price”). The Design Costs determined under Section 4.12 are 
payable in addition to the Developer Property Purchase Price. 
4.7 
Fair Market Value; Agreement of the Parties. “Fair Market Value” means the fair 
market value of the Developer Property as of the Exercise Date, determined exclusive of the value 
of the Improvement Work. Within thirty (30) days after the Exercise Date, the Parties shall attempt 
in good faith to agree in writing upon the Fair Market Value. If the Parties agree in writing within 
that period, that amount is the Fair Market Value and Sections 4.8 and 4.9 do not apply. 
4.8 
Appraisals. If the Parties do not agree in writing upon the Fair Market Value within 
the period stated in Section 4.7, then within sixty (60) days after the end of that period City shall 
obtain an appraisal of the Fair Market Value and Developer may obtain an appraisal of the Fair 
Market Value. Each appraisal must be prepared by an appraiser who holds the MAI designation of 
the Appraisal Institute, is certified as a general real estate appraiser in Arizona, and has at least ten 
(10) years of experience appraising commercial real property in Maricopa County. Each appraisal 
must value the Developer Property as of the Exercise Date and must exclude the value of the 
Improvement Work, so that Developer is neither compensated twice nor left uncompensated for 
the Improvement Work. The Parties shall exchange their appraisals simultaneously at the end of 
the sixty (60) day period. If Developer does not obtain an appraisal within that period, City’s 
appraisal establishes the Fair Market Value. If the two appraisals state the same amount, that 
amount is the Fair Market Value. 
4.9 
Submission to Neutral Appraiser. If the two appraisals state different amounts, the 
Parties shall submit both appraisals to a neutral appraiser (the “Neutral Appraiser”) for final 
determination of the Fair Market Value. The Neutral Appraiser must meet the appraiser

-13- 
 
 
 
qualifications stated in Section 4.8 and must have no present or prior business relationship with 
either Party. The Parties shall select the Neutral Appraiser by mutual agreement within fifteen (15) 
days after they exchange appraisals. If the Parties do not select the Neutral Appraiser within that 
period, either Party may apply to the Presiding Judge of the Superior Court of Arizona in and for 
Maricopa County to appoint the Neutral Appraiser. The Neutral Appraiser shall determine the Fair 
Market Value within thirty (30) days after appointment, based on the two appraisals and any 
additional information the Neutral Appraiser requests. The Fair Market Value determined by the 
Neutral Appraiser may not be more than the higher of the two appraisals and may not be less than 
the lower of the two appraisals. The Neutral Appraiser’s determination is final and binding on the 
Parties, is not subject to appeal absent fraud, and may be entered as a judgment in any court of 
competent jurisdiction. 
4.10 
Appraisal Costs; Effect on Closing. Each Party shall pay the cost of the appraisal it 
obtains. The Parties shall share equally the fees and costs of the Neutral Appraiser. If the Fair 
Market Value has not been determined by the date Closing would otherwise occur under Section 
4.15, Closing is extended to the date that is thirty (30) days after the Fair Market Value is 
determined. 
4.11 
Improvement Reimbursement. In addition to the Fair Market Value, City shall 
reimburse Developer for the actual, documented, out-of-pocket costs Developer incurred for (i) 
the Minimum Improvements, wherever performed, and (ii) improvements made to the Developer 
Property in connection with the Project, in each case whether or not that work is complete, 
including site work, demolition, grading, drainage, utility installation and relocation, foundations, 
and structural work in place (the “Improvement Work,” and the reimbursement, the 
“Improvement Reimbursement”). No later than thirty (30) days after the Exercise Date, 
Developer shall deliver to City an itemized statement of the Improvement Work costs, together 
with the supporting contracts, invoices, lien waivers, and payment records. If City disputes any 
item in the statement, City shall deliver written notice of the disputed items to Developer within 
thirty (30) days after receiving the statement, and the Parties shall attempt in good faith to resolve 
the dispute within thirty (30) days after that notice. Any dispute the Parties do not resolve within 
that period shall be submitted to binding arbitration under Sections 4.13 and 4.14. The 
Improvement Reimbursement covers only Improvement Work, the value of which is excluded 
from the Fair Market Value under Section 4.7. Developer is not entitled to be paid twice for the 
same work, and no item may be included in both the Fair Market Value and the Improvement 
Reimbursement. 
4.12 
Design Documents and Design Costs. Upon City’s exercise of either Purchase 
Option, Developer shall assign and deliver to City, to the extent assignable and subject to the 
consent of the design professionals who prepared them, all plans, specifications, civil plans and 
drawings, architectural drawings, building construction drawings, engineering, geotechnical, and 
environmental studies, surveys, reports, and related design work product prepared for the Project 
applicable only to the Developer Property (collectively, the “Design Documents”). The amount 
City shall pay Developer for the Design Documents (the “Design Costs”) shall be negotiated 
between the Parties in good faith. Developer shall make available to City the contracts, invoices, 
and payment records relating to the Design Documents that City reasonably requests. If the Parties 
do not reach written agreement on the Design Costs within forty-five (45) days after the Exercise 
Date, the determination of the Design Costs shall be submitted to binding arbitration under

-14- 
 
 
 
Sections 4.13 and 4.14. City shall pay the Design Costs at Closing if they have been determined 
by then, and otherwise within thirty (30) days after they are determined. An arbitration under this 
Section does not delay Closing. Developer makes no representation or warranty regarding the 
Design Documents, and City’s use of the Design Documents is at City’s sole risk. 
4.13 
Binding Arbitration. Any dispute expressly submitted to arbitration under Section 
4.11 or Section 4.12 shall be resolved by binding arbitration under the American Arbitration 
Association (“AAA”) Commercial Arbitration Rules then in effect, as modified by this Section 
4.13 and Section 4.14. This Section applies only to disputes expressly submitted to arbitration 
under Section 4.11 and Section 4.12. All other disputes between the Parties are governed by 
Section 10.6. Either Party may commence the arbitration by delivering a written demand to the 
other Party. The arbitration shall be conducted before a single arbitrator selected by mutual 
agreement of the Parties within thirty (30) days after the demand is delivered. If the Parties do not 
agree upon the arbitrator within that period, either Party may apply to the Presiding Judge of the 
Superior Court of Arizona in and for Maricopa County to appoint the arbitrator as provided in 
A.R.S. § 12-3011. The arbitration is not administered by AAA, and the AAA Commercial 
Arbitration Rules apply as the procedural rules of the arbitration only. The arbitrator must be an 
attorney licensed in Arizona or a person with at least ten (10) years of experience in commercial 
real estate development, and must have no present or prior business relationship with either Party. 
The arbitration shall be held in Phoenix, Maricopa County, Arizona, shall be governed by the 
substantive law of the State of Arizona, and shall be conducted under the Arizona Revised Uniform 
Arbitration Act, A.R.S. § 12-3001 et seq. 
4.14 
Arbitration Procedure and Award. Discovery in the arbitration is limited to the 
exchange of the documents on which each Party relies and to no more than two (2) depositions for 
each Party, unless the arbitrator orders otherwise for good cause. The arbitrator shall hold the 
hearing within one hundred twenty (120) days after appointment and shall issue the award within 
thirty (30) days after the hearing closes. The award shall be in writing and shall state the arbitrator’s 
findings of fact and conclusions of law. The arbitrator may not award punitive, consequential, 
indirect, exemplary, or multiple damages. The award is final and binding on the Parties, and 
judgment on the award may be entered in any court of competent jurisdiction. The Parties shall 
advance the arbitrator’s fees and any administrative fees equally, and the arbitrator shall allocate 
those fees and award reasonable attorneys’ fees and costs to the prevailing Party as provided in 
Section 10.4. Each Party shall continue to perform its obligations under this Agreement while the 
arbitration is pending. Either Party may seek provisional or injunctive relief from a court of 
competent jurisdiction without waiving its right to arbitrate. The Parties shall keep the arbitration 
confidential, except that City may disclose the arbitration and the records of it to the extent required 
by the Arizona public records law, A.R.S. § 39-121 et seq., or other Applicable Laws. 
4.15 
Closing. Closing on the exercise of the Purchase Options shall occur within ninety 
(90) days after the Exercise Date, as that date may be extended under Section 4.10, unless the 
Parties agree otherwise in writing (the “Closing”). At Closing: 
A. 
Developer shall convey the City Property, the Developer Property, or both, as 
applicable, to City by special warranty deed, free and clear of all monetary 
liens other than those expressly approved by City;

-15- 
 
 
 
B. 
City shall pay to Developer in immediately available funds the City Property 
Purchase Price, the Developer Property Purchase Price, and the Design Costs, 
as applicable, less any portion of the Improvement Reimbursement or the 
Design Costs that remains in dispute, and City shall pay any disputed portion 
within thirty (30) days after it is determined; 
C. 
Developer shall assign and deliver the Design Documents to City as provided 
in Section 4.12; and 
D. 
The Parties shall execute all documents reasonably necessary to complete the 
conveyance. 
4.16 
Cooperation. Upon City’s exercise of either Purchase Option, Developer shall take 
all actions reasonably required to facilitate Closing and shall not encumber, transfer, or otherwise 
impair title to the City Property or the Developer Property prior to Closing. 
4.17 
Right of First Refusal. In addition to the Purchase Options granted in this Section, 
Developer grants to City a right of first refusal under the terms contained herein. Until Developer 
has achieved substantial completion of the entire Project, including completion of all phases of 
development, Developer shall not sell, assign, transfer, convey, or otherwise dispose of any portion 
of the Developer Property or City Property or any real property interest therein (each, a “Proposed 
Transfer”) without first providing City a right of first refusal in accordance with this Section. 
A. 
If Developer receives a bona fide written offer from a third party to purchase 
any portion of the Developer Property, Developer shall deliver written notice 
to the City (“ROFR Notice”) together with a complete copy of the third-party 
offer, including all terms, conditions, exhibits, and schedules. The City shall 
have thirty (30) days after receipt of the ROFR Notice to elect, by written 
notice to Developer, to purchase the property that is the subject of the 
Proposed Transfer on the same terms and conditions as contained in the 
third-party offer. 
B. 
If the City elects to exercise its right of first refusal, Developer and City shall 
proceed to closing on the same schedule and under the same conditions 
required of the third-party purchaser, subject to reasonable extension if 
necessary to accommodate a City Council vote on the adoption of an 
ordinance authorizing the purchase and the time necessary for such ordinance 
to become effective. Developer may not modify any material term of the 
Proposed Transfer after delivery of the ROFR Notice to City. If the City does 
not exercise its right of first refusal within the applicable election period, 
Developer may proceed with the Proposed Transfer to the third party only on 
the identical terms provided to the City. 
C. 
Any attempted transfer made in violation of this Section shall be void and 
shall constitute a Default under this Agreement. This right of first refusal is 
in addition to, and does not limit or alter, the City’s Purchase Options under 
this Section.

-16- 
 
 
 
SECTION 5. 
PUBLIC INFRASTRUCTURE IMPROVEMENTS.   
5.1 
Developer shall construct offsite public infrastructure improvements within the 
public right-of-way sufficient to serve the Project if City determines following consultation with 
Developer that such improvements are necessary as defined in Section 3 (the “Public 
Infrastructure Improvements”).  Nothing contained herein shall limit Developer’s obligation to 
provide additional street and traffic signal improvements or public water and wastewater 
infrastructure should Developer obtain approvals to construct Improvements on the Property that 
are of a greater intensity or density than the development described in Recital H. The Public 
Infrastructure Improvements may include those Minimum Improvements that are located within, 
or that are constructed to serve, the public rights-of-way. If an improvement is both a Minimum 
Improvement and a Public Infrastructure Improvement, Developer’s construction of that 
improvement satisfies both obligations, and the improvement is counted only once for purposes of 
the Improvement Reimbursement under Section 4.11. 
SECTION 6. 
DEFAULTS.  
6.1 
Events of Default.  It shall be a default hereunder (“Default”) if either Party fails to 
perform any of its obligations hereunder, and such failure continues for a period of thirty (30) days 
after Notice from the non-defaulting Party specifying in reasonable detail the nature of the failure 
in the case of a  monetary default, or ninety (90) days after Notice from the non-defaulting Party 
specifying in reasonable detail the nature of the failure in the case of a non-monetary default; 
provided, however, that no non-monetary Default shall be deemed to exist if a cure within ninety 
(90) days is not practicable and the defaulting Party commences a cure within such ninety (90) day 
period and diligently and expeditiously pursues such cure to completion within one hundred eighty 
(180) days after Notice from the non-defaulting Party. 
6.2 
Remedy of City.  In the event of a Default by Developer and Developer’s failure to 
timely cure the default as provided in this Section 6, the City’s remedy shall be as follows: 
A. 
City shall provide notice of the Default to Developer and Developer’s Lender (if 
any) to provide the Lender such time to cure Developer’s Default as is reasonably 
necessary, but in no event more than one hundred eighty (180) days from such Notice to 
Lender; and 
B. 
If Developer or Developer’s Lender fails to cure Developer’s default within the 
time permitted above, City shall have all remedies available to it at law or in equity. City 
may institute a legal action to cure, correct, or remedy any default, to enforce any covenant 
or agreement herein, to terminate this Agreement, or to enjoin any threatened or attempted 
violation, including suits for declaratory relief, specific performance, and actions for 
damages, provided, however, that claims for damages shall be limited to actual damages. 
City hereby waives any right to seek indirect, consequential, punitive, multiple, 
exemplary, or any other damages other than actual damages for a breach of this 
Agreement by Developer.   
C. 
Remedy of City if Minimum Improvements are not Completed. In addition to those 
remedies outlined above, if Developer does not complete the Minimum Improvements

-17- 
 
 
 
within the time specified in this Agreement, including all applicable cure periods after a 
Notice of Default by City, then City may terminate this Agreement and may exercise the 
Purchase Options in accordance with Section 4. Any acquisition of the City Property or 
the Developer Property under the Purchase Options by City shall be made only in 
accordance with Section 4, including its pricing, exercise, and Closing provisions. If City 
invokes the remedy provided by this Section, Developer agrees to execute, acknowledge, 
and deliver to City at Closing a proper recordable instrument prepared by City conveying 
via special warranty deed to City any right, title, and interest in the applicable property 
and the improvements thereon. 
i. Developer grants City, its employees, agents, consultants, and contractors 
reasonable access to the City Property at all times after City’s election to 
purchase the City Property pursuant to this Section, and at such other times as 
reasonably necessary prior to Closing, for the purpose of conducting inspections, 
surveys, testing, environmental assessments, structural evaluations, or any other 
investigations City deems necessary to assess the condition of the City Property 
and to determine the need for remediation, demolition, removal of incomplete 
improvements, or site stabilization. Developer shall reasonably cooperate with 
City in facilitating such access, including unlocking gates, providing entry to 
secured areas, and ensuring that no actions by Developer or its contractors 
impede City’s inspections or assessments. City shall endeavor to provide 
Developer with reasonable advance notice of any such entry, except in 
circumstances where immediate access is necessary for safety or preservation of 
the Property. City’s exercise of its inspection and assessment rights under this 
Section shall not constitute a waiver of any right or remedy available to City 
under this Agreement. 
6.3 
Remedy of Developer.  In the event of a Default by City and failure by City to timely 
cure the Default as provided in Section 6.1, Developer shall have all remedies available to it at law 
or in equity. Developer, or any successor-in-interest or assignee, may institute a legal action to 
cure, correct, or remedy any default, to enforce any covenant or agreement herein, to terminate 
this Agreement, or to enjoin any threatened or attempted violation, including suits for declaratory 
relief, specific performance, relief in the nature of mandamus and actions for damages, provided, 
however, that claims for damages shall be limited to actual damages. Developer hereby waives 
any right to seek indirect, consequential, punitive, multiple, exemplary or any other damages other 
than actual damages for a breach of this Agreement by City. Notwithstanding the foregoing, solely 
in the event of a City Delay, Developer in its sole election may elect to (i) treat the City Delay as 
a Force Majeure Event with each day of the City Delay extending the dates of any required 
performance by Developer by the same number of days; or (ii) give the City Notice and an 
opportunity to cure its Default in accordance with Section 6.1; or (iii) without any requirement or 
obligation of notice and opportunity to cure, immediately terminate this Agreement by written 
Notice to the City, in which event Developer shall retain all other rights and remedies set forth in 
this Section 6.3. 
6.4 
Delays; Waivers. Except as otherwise expressly provided in this Agreement, any 
delay by any Party in asserting any right or remedy under this Agreement shall not operate as a 
waiver of any such rights or limit such rights in any way; and any waiver in fact made by such

-18- 
 
 
 
Party with respect to any default by the other Party shall not be considered as a waiver of rights 
with respect to any other default by the non-defaulting Party or with respect to the particular default 
except to the extent specifically waived in writing. 
6.5 
Rights and Remedies Cumulative.  Subject to the limitations of Section 6.2 and 
Section 6.3, the rights and remedies of the Parties are cumulative, and the exercise by either Party 
of any one or more of such rights shall not preclude the exercise by it, at the same or different 
times, of any other right or remedy for any other default by the other Party. 
6.6 
Good Faith Efforts to Achieve Deadlines.  Each Party agrees that it shall act in good 
faith with respect to its efforts timely to make all submissions and comply with all deadlines in 
order to allow the timely and successful performance of the other Party. 
 
SECTION 7. 
ASSIGNMENT AND ASSUMPTION BY DEVELOPER.  
7.1 
Assignment by One Chandler Owner. Effective as of the Effective Date, One 
Chandler Owner assigns, transfers, and conveys to Developer all of One Chandler Owner’s right, 
title, and interest in and to the 2022 Agreement, as amended and restated by this Agreement, and 
all rights, benefits, and privileges under it. City expressly consents to this assignment and 
delegation and accepts Developer as the successor to and substitute for One Chandler Owner with 
respect to all rights, obligations, liabilities, duties, covenants and responsibilities arising under or 
relating to the 2022 Agreement and this Agreement.  From and after the Land Closing, Developer 
shall be the sole “Developer” and obligor under this Agreement, and One Chandler Owner shall 
have no further duties, obligations or liabilities under the 2022 Agreement or this Agreement, 
whether arising on or after the Land Closing. The Parties intend this assignment, assumption and 
release to constitute a novation as of the Land Closing. 
7.2 
Assumption by Developer. Developer accepts the assignment described in Section 
7.1 and assumes and agrees to perform, pay, and discharge all obligations, liabilities, duties, 
covenants, and responsibilities of One Chandler Owner under the 2022 Agreement, as amended 
and restated by this Agreement, on or after the Land Closing and based upon acts, omissions, 
events or circumstances occurring on or after such dates.  Developer agrees to be bound by this 
Agreement as the “Developer” for all purposes and, from and after the Land Closing, shall be 
solely responsible for all obligations of Developer hereunder. 
7.3 
Waiver and Release by One Chandler Owner. Effective as of the Effective Date, and 
as material consideration for City’s consent to the assignment described in Section 7.1 and City’s 
agreement to enter into this Agreement, One Chandler Owner, for itself and its successors and 
assigns, knowingly, voluntarily, irrevocably, and unconditionally releases and discharges City and 
its elected officials, officers, employees, and agents from all claims, demands, causes of action, 
damages, and liabilities of every kind, whether known or unknown, that One Chandler Owner has 
or may have as of the Effective Date arising out of or relating to (i) the 2022 Agreement or any 
amendment thereto, (ii) the City Property or Developer Property, (iii)  the transactions 
contemplated by this Agreement,  (iv) any and all rights to compensation for diminution in value 
under A.R.S. § 12-1134  or any similar statutory, constitutional, or common-law theory that may 
now or in the future exist as a result of the approval or performance of, or any condition, term, or 
agreement contained in, this Agreement or the 2022 Agreement, or (v) any land-use decision,

-19- 
 
 
 
condition, approval, zoning action, administrative decision, or City regulation applicable to the 
Property or the Project. One Chandler Owner represents that it has had the opportunity to consult 
counsel of its choosing regarding this waiver and release, that it grants this waiver and release 
knowingly and voluntarily, and that it has not assigned to any other person any claim released 
under this Section. Nothing in this Section waives or releases City’s obligations under this 
Agreement. This Section survives the expiration or earlier termination of this Agreement. This 
waiver and release are material, bargained‑for consideration, and shall survive the expiration, 
termination, assignment, of this Agreement, and shall remain binding upon One Chandler Owner 
and its successors and assigns regardless of any change in circumstances, property ownership, or 
land‑use status.  Notwithstanding anything contained herein to the contrary, the foregoing waiver 
and release is expressly conditioned upon (i) consummation of the Land Closing, and (ii) City’s 
full release of One Chandler Owner pursuant to Section 7.4.  
7.4 
Release of One Chandler Owner;. Upon the Land Closing, City irrevocably and 
unconditionally releases and discharges One Chandler Owner and its members, managers, officers, 
directors, employees, agents, affiliates, successors and assigns from any and all obligations, 
liabilities, duties, covenants, claims and responsibilities arising under or relating to the 2022 
Agreement or this Agreement, whether known or unknown, fixed or contingent, accrued or 
unaccrued, and whether arising from acts, omissions, circumstances or events occurring before, on 
or after the Effective Date or Land Closing.  Upon the Land Closing, Developer assumes and 
agrees to perform all such obligations of the “Developer” under this Agreement.  Effective upon 
the Land Closing, Developer is substituted for One Chandler Owner as the obligor under this 
Agreement.  Developer shall indemnify, hold harmless and defend One Chandler Owner, its 
members, managers, officers and affiliates from and against any claim or matter in connection with 
or arising under the Development Agreement first arising and occurring subsequent to the Closing. 
This Section shall survive the expiration or termination of this Agreement. 
7.5 
Further Assignment by Developer. After the Effective Date, Developer may not sell, 
assign, or transfer its interest in this Agreement or the Property to another entity or person without 
the express written consent of City, which consent shall not be unreasonably withheld, 
conditioned, or delayed. Notwithstanding the foregoing, Developer may assign or transfer its rights 
and duties under this Agreement without City’s consent to (i) an entity that is one hundred percent 
(100%) controlled by Developer or under common control with Developer. Developer shall give 
City written notice of any assignment made under this Section within ten (10) days after the 
assignment is made. 
7.6 
Assignment and Assumption Agreement. As a condition to any assignment under 
Section 7.5, the assignee shall execute and deliver to City a written assignment and assumption 
agreement, in recordable form and reasonably acceptable to City, under which the assignee 
assumes all obligations, liabilities, duties, covenants, and responsibilities of Developer under this 
Agreement that relate to the interest assigned. Upon delivery of that agreement to City, Developer 
is released from the obligations and liabilities the assignee assumes that arise after the effective 
date of the assignment. Developer remains liable for all obligations and liabilities that arose before 
that date and for any obligation the assignee does not assume. 
7.7 
Effect of Prohibited Assignment. Any sale, assignment, or transfer made in violation 
of this Section 7 is void and is a Default under this Agreement.

-20- 
 
 
 
7.8 
Binding Effect. This Section 7 binds and benefits the Parties and their respective 
successors and permitted assigns. 
SECTION 8. 
REPRESENTATIONS. 
8.1 
City Representations.  The City represents and warrants to Developer and One 
Chandler Owner that: 
A. 
The City is duly formed and validly existing under Arizona law and that the 
individual(s) executing this Agreement on behalf of the City is authorized and empowered 
to bind the City. 
B. 
The City has the full right, power, and authorization to enter into and perform this 
Agreement and each of the City’s obligations and undertakings under this Agreement, 
and the City’s execution, delivery, and performance of this Agreement have been duly 
authorized and agreed to in compliance with the requirements of its Charter and Arizona 
law. 
C. 
All consents and approvals necessary to the execution, delivery and performance 
of this Agreement have been obtained, and no further action needs to be taken in 
connection with such execution, delivery, and performance; provided, however, the 
Parties hereby acknowledge and agree that pursuant to Chandler’s City Charter, additional 
documents may require approval from Chandler City Council. 
D. 
The City will execute and acknowledge when appropriate all documents and 
instruments and take all actions necessary to implement, evidence and enforce this 
Agreement. 
8.2 
Developer Representations. Developer represents and warrants to the City that: 
A. 
Developer is duly registered as a foreign entity doing business in Arizona and 
validly existing under the laws of its state of formation and that the individual(s) executing 
this Agreement on behalf of Developer is authorized and empowered to bind Developer. 
B. 
Developer has the full right, power and authorization to enter into and perform this 
Agreement and of the obligations and undertakings of Developer under this Agreement, 
and the execution, delivery and performance of this Agreement has been duly authorized 
and agreed to in compliance with its organizational documents and Arizona law. 
C. 
All consents and approvals necessary to the execution, delivery and performance 
of this Agreement have been obtained, and no further action needs to be taken in 
connection with such execution, delivery and performance. 
D. 
Developer will execute and acknowledge when appropriate all documents and 
instruments and take all actions necessary to implement, evidence and enforce this 
Agreement.

-21- 
 
 
 
8.3 
One Chandler Owner Representations.  Solely as of the Effective Date and 
the Land Closing, and solely for purposes of effectuating the assignment and Land Closing 
contemplated by this Agreement, One Chandler Owner represents and warrants to the City 
and Developer that: 
A. 
One Chandler Owner is duly formed and validly existing under the laws of its state 
of formation, is authorized to do business in Arizona, and the individual(s) executing this 
Agreement on behalf of One Chandler Owner is authorized and empowered to bind One 
Chandler Owner. 
B. 
One Chandler Owner has the full right, power, and authorization to enter into and 
perform this Agreement, including the assignment in Section 7.1 and the waiver and 
release in Section 7.3, and the execution, delivery, and performance of this Agreement 
have been duly authorized and agreed to in compliance with its organizational documents 
and Arizona law. 
C. 
All consents and approvals necessary to the execution, delivery, and performance 
of this Agreement have been obtained, and no further action needs to be taken in 
connection with such execution, delivery, and performance. 
D. 
One Chandler Owner has not assigned, transferred, or encumbered its right, title, or 
interest in the 2022 Agreement other than as provided in Section 7.1, and holds the right 
to grant the waiver and release in Section 7.3. 
E. 
One Chandler Owner will execute and acknowledge when appropriate all 
documents and instruments as are reasonably necessary solely to evidence or effectuate 
the assignment, assumption, release and novation contemplated by Section 7 and the Land 
Closing; provided that One Chandler Owner shall not be required to assume or incur any 
additional liability or obligation, make any payment, guaranty any obligation of 
Developer, or undertake any obligation with respect to the development, construction, 
ownership, operation or maintenance of the Property or Project. Following the Land 
Closing, One Chandler Owner shall have no continuing obligation under this Agreement 
except as expressly set forth in this sentence.   
The representations and warranties of One Chandler Owner under this Section 8.3 shall not 
constitute continuing covenants and shall terminate upon the Land Closing, except for 
representations concerning One Chandler Owner’s authority to execute the assignment and the 
absence of prior assignments of its interest in the 2022 Agreement. 
SECTION 9. 
EFFECTIVE DATE AND TERM  
9.1 
Effective Date.  This Agreement shall be effective as of the date that it is approved 
by the Chandler City Council.  This Agreement shall be recorded in the Official Records of 
Maricopa County, Arizona, in accordance with the requirement of A.R.S. § 9-500.05. 
9.2 
Term.  The term of this Agreement (“Term”) shall be until the issuance of the final 
certificate of occupancy for all phases of the Project, or as otherwise set forth in this Agreement.

-22- 
 
 
 
SECTION 10. 
GENERAL PROVISIONS. 
10.1 
Force Majeure.  If either Party is delayed or prevented from the performance of any 
duty or obligation under this Agreement by reason of a Force Majeure Event, then the performance 
of such duty or obligation shall be excused for the period of the delay, and the period for the 
performance by such Party of any such duty or obligation shall be extended for a period equivalent 
to the period of such delay.  The Party subject to any Force Majeure Event shall provide Notice to 
the other Party as soon as reasonably practicable. 
10.2 
Notices.  Except as otherwise required by law, any notice, demand or other 
communication required to be given by this Agreement (each, a “Notice”) shall be in writing and 
shall be given by (i) personal delivery; (ii) by certified or registered U.S. Mail, return receipt 
requested; or (iii) by any nationally recognized express or overnight delivery service (e.g., FedEx 
or UPS), with all postage and other delivery charges prepaid and addressed to the Parties at their 
respective addresses set forth below, or at such other address as a Party may designate in writing 
pursuant to the terms of this paragraph: 
 
To One Chandler Owner: 
One Chandler Owner, LLC 
 
 
 
 
 
510 South Neil Street 
 
 
 
 
 
Champaign, IL  61820 
 
 
 
 
 
Attention:  Christopher R. Saunders 
 
 
 
 
 
Email:  chris@greenstrealty.com  
 
 
With a copy to: 
 
Jennings, Strouss & Salmon, P.L.C. 
 
 
 
 
 
One East Washington Street, Suite 1900 
 
 
 
 
 
Phoenix, AZ 85004-2554 
 
  
 
 
 
 
 
Attention:  Brett D. Siglin 
 
 
 
 
 
Email:  bsiglin@jsslaw.com 
 
 
To Developer:  
 
SAM CDT I, LLC 
 
 
 
 
Attn: Stu Hansen 
 
 
 
 
 
7333 E. Doubletree Ranch Road, Suite 270 
 
 
 
 
 
Scottsdale, AZ 85258 
 
 
 
 
 
Email: stu.hansen@shelterasset.com  
 
 
With a copy to: 
 
Ray Law Firm 
Attn: M. Brennan Ray 
P.O. Box 6430 
 
Chandler, AZ 85246  
  
 
 
 
 
 
Email:  bray@raylawaz.com  
 
 
 
To the City: 
 
City of Chandler 
Cultural Development Department (MS 498) 
P. O. Box 4008 
Chandler, AZ 85244-4008 
 
Attention: 
Cultural Development Director

-23- 
 
 
 
 
With a copy to: 
 
City of Chandler 
City Attorney’s Office 
P. O. Box 4008 
Chandler, AZ  84244-4008 
 
Attention: 
City Attorney 
 
10.3 
Effective Date of Notices.  Any Notice will (i) if delivered personally or delivered 
through a same day delivery/courier service be deemed effective upon delivery or refusal to accept 
delivery by the addressee; and (ii) if delivered by U.S. mail in the manner described above be 
deemed effective upon the earlier of receipt or three (3) Business Days after deposit in a post office 
operated by the United States or with a United States postal officer; and (iii) if sent by a recognized 
national overnight delivery service be deemed effective one (1) Business Day after deposit with 
such service.  Notwithstanding the foregoing, no payment shall be deemed to be made until 
actually received in good and available funds by the intended payee.   
10.4 
Attorneys’ Fees.  In the event of a dispute, action, proceeding, or litigation arising 
out of or relating to this Agreement, including any action for declaratory, injunctive or other 
equitable relief, the prevailing Party in any such action shall be entitled to reimbursement of its 
reasonable attorneys’ fees and court costs, including, but not limited to, its costs of expert 
witnesses, transportation, lodging and meal costs of the Party and witnesses, costs of transcript 
preparation and other reasonable and necessary direct and incidental costs of such dispute. 
10.5 
Recordation.  The City will cause this Agreement to be recorded in its entirety in the 
Official Records of Maricopa County, Arizona, not later than ten (10) days after execution of the 
Agreement by the Parties, and shall thereafter promptly provide a recorded copy of this Agreement 
to Developer. 
10.6 
Governing Law.  This Agreement shall be governed by and construed under the 
internal, substantive laws of the State of Arizona, without reference to the principles of conflict of 
laws.  The City and Developer agree that the proper venue for any matters in connection herewith 
shall be in the State or Federal courts located in Phoenix, Arizona.  City and Developer hereby 
submit themselves to the jurisdiction of such courts for the purpose of adjudicating any matters 
relating to or arising from this Agreement. 
10.7 
Severability.  If any provision of this Agreement is declared void or unenforceable, 
such provision shall be severed from this Agreement, which shall otherwise remain in full force 
and effect.  If any applicable law or court of competent jurisdiction prohibits or excuses the City 
from undertaking any contractual commitment to perform under any provision of this Agreement, 
the remaining portions of this Agreement shall remain in full force and effect, and the Parties will 
negotiate diligently in good faith for such amendments of this Agreement as may be necessary to 
achieve the original intent of this Agreement, notwithstanding such invalidity or unenforceability.   
10.8 
Amendment.  No change or addition is to be made to this Agreement except by 
written amendment executed by the City and Developer.  Within ten (10) days after any 
amendment to this Agreement, the City will cause such amendment to be recorded in the Official 
Records of Maricopa County, Arizona, and shall thereafter promptly provide a recorded copy of 
such amendment to Developer.

-24- 
 
 
 
10.9 
Further Assurances.  Each Party agrees to perform such other and further acts and to 
execute and deliver such additional agreements, documents, affidavits, certifications, 
acknowledgments and instruments as any other Party may reasonably require to consummate, 
evidence, confirm or carry out the matters contemplated by this Agreement or confirm the status 
of (i) this Agreement as in full force and effect, and (ii) the performance of the obligations 
hereunder at any time. 
10.10 Calculation of Days.  If the last day of any time period stated in this Agreement or 
the date on which any obligation to be performed under this Agreement shall fall on a Saturday, 
Sunday or legal holiday in the State of Arizona, then the duration of such time period or the date 
of performance, as applicable, shall be extended so that it shall end on the next succeeding day 
which is not a Saturday, Sunday or legal holiday in the State of Arizona. 
10.11 Section Headings.  The Section headings contained in this Agreement are for 
convenience in reference only and are not intended to define or limit the scope of any provision of 
this Agreement.  References to sections or exhibits are to Sections or Exhibits of this Agreement 
unless otherwise qualified. 
10.12 No Partnerships; Third Parties.  It is not intended by this Agreement to, and nothing 
contained in this Agreement shall, create any partnership, joint venture or other arrangement 
between Developer and the City.  No term or provision of this Agreement is intended to, or shall, 
be for the benefit of any Person not a party hereto, and no such other Person shall have any right 
or cause of action hereunder, except for permitted transferees or assignees to the extent that they 
assume or succeed to the rights and/or obligations of Developer under this Agreement. 
10.13 Recitals, Exhibits.  The Recitals set forth in this Agreement are incorporated herein 
by reference and form a part of this Agreement.  The Parties agree that all references to this 
Agreement include all Exhibits designated in and attached to this Agreement, such Exhibits being 
incorporated into and made an integral part of this Agreement for all purposes.  Parties 
acknowledge, however, that the Maricopa County Recorder may refuse to record graphical 
exhibits; and accordingly, some of the incorporated exhibits may not be contained in the recorded 
copy of this Agreement but are deemed attached and incorporated herein nonetheless.  Exhibits 
that are not included in the recorded copy of this Agreement are attached to the copy of this 
Agreement in the office of the Chandler City Clerk.   
10.14 Entire Agreement.  This Agreement and all exhibits thereto attached and incorporated 
constitute the entire agreement between the Parties pertaining to the subject matter hereof.  All 
prior and contemporaneous agreements, representations, and understandings of the Parties, oral or 
written, are hereby superseded and merged herein, except that the 2022 Agreement is reinstated if 
this Agreement becomes null and void under Section 2.6.. 
10.15 Prop 207 Waiver.  Developer agrees to and does knowingly waive any and all rights 
to compensation for diminution in value pursuant to A.R.S. § 12-1134 that may now or in the 
future exist as a result of the approval or performance of, and all conditions, terms, and agreements 
contained in this Agreement.

-25- 
 
 
 
10.16 Conflict of Interest. This Agreement is subject to the cancellation provisions for 
conflicts of interest pursuant to A.R.S. §38-511. 
10.17 Time of Essence.  Time is of the essence of this Agreement and each provision of 
this Agreement. 
10.18 Counterparts. This Agreement may be executed in counterparts, each of which will 
be deemed an original, but all of which taken together constitute one agreement. A signed copy of 
this Agreement delivered by facsimile, email, or other means of electronic transmission will be 
deemed to have the same legal effect as delivery of an original signed copy. 
IN WITNESS WHEREOF, the Parties have duly executed this Agreement as of the 
Effective Date. 
CITY: 
 
 
 
 
 
 
 
CITY OF CHANDLER, 
 
 
 
 
 
 
an Arizona municipal corporation 
 
 
By: 
 
                                                                                         Mayor Kevin Hartke 
 
Date: ____________________________ 
 
 
 
ATTEST: 
 
_______________________________ 
CITY CLERK 
 
 
APPROVED AS TO FORM: 
 
 
 
 
 
 
 
CITY ATTORNEY

-26- 
 
 
 
STATE OF ARIZONA 
) 
 
 
 
 
) ss. 
County of Maricopa  
) 
 
The foregoing Agreement was acknowledged before me this ____ day of _________, 2026, by 
Kevin Hartke, Mayor of City of Chandler, an Arizona municipal corporation, on behalf of the 
municipal corporation. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Notary Public 
My Commission Expires:

-27- 
 
 
 
ONE CHANDLER OWNER:  
 
 
 
 
 
One Chandler Owner, LLC 
 
a Delaware limited liability company 
 
 
By:______________________________ 
 
 
Name:____________________________ 
 
 
Title:_____________________________ 
 
 
Date: ____________________________ 
 
 
 
 
 
 
 
 
 
 
 
STATE OF _____________ ) 
 
 
 
 
) ss. 
County of ______________ ) 
 
The foregoing Agreement was acknowledged before me this _____ day of ______________, 2026, 
by ___________________________, the __________________________ of One Chandler 
Owner, LLC, on behalf of the limited liability company. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Notary Public 
My Commission Expires:

-28- 
 
 
 
DEVELOPER:  
 
 
 
 
 
SAM CDT I LLC 
 
A  
 
 
 limited liability company 
 
 
By:______________________________ 
 
 
Name:____________________________ 
 
 
Title:_____________________________ 
 
 
Date: ____________________________ 
 
 
 
 
 
 
 
 
 
 
 
STATE OF _____________ ) 
 
 
 
 
) ss. 
County of ______________ ) 
 
The foregoing Agreement was acknowledged before me this _____ day of ______________, 2026, 
by ___________________________, the __________________________ of SAM CDT I, LLC, 
on behalf of the limited liability company. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Notary Public 
My Commission Expires:

-29- 
 
 
 
EXHIBIT A 
 
LEGAL DESCRIPTION 
 
LOTS DESCRIPTION 
 
Lots 128, 129, 130, 131, 132, 133, 134, 135, 136, 137, 138, 139, 268, 270, 272,274 TOWNSITE OF 
CHANDLER, according to the plat of record in the office of the Maricopa County Recorder, in Book 5 of 
Maps, Page 34.   
 
EXCEPT the north 3.00 feet of Lot 268 
 
EXCEPT that portion of Lot 139 described as follows: 
 
BEGINNING at the Southwest corner of said Lot 139; thence South 89 degrees 24 minutes 17 seconds 
East along the South line thereof, a distance of 3.00 feet; thence North 29 degrees 41 minutes 53 seconds 
West 5.79 feet to the West line of said Lot; thence South 1 degree 30 minutes 18 seconds West along said 
West Lot line, a distance of 5.00 feet to the Point of Beginning. 
 
ALLEY VACATION RECORDED PER ORDINANCE NO. 3509 RECORDED 2004-0365563 
 
A portion of TOWNSITE OF CHANDLER, according to the plat of record in the office of the Maricopa 
County Recorder, in Book 5 of Maps, Page 34, being more particularly described as follows: 
 
BEGINNING at a point marking the northeast corner of Lot 128 as shown in said Book 5 of Maps, Page 
34 of Maricopa County records; 
 
THENCE Westerly along the north line of Lots 128 through 139 to the northwesterly corner of Lot 139; 
 
THENCE along the northerly prolongation of the west line of said Lot 139 to a point that lies 10 feet 
north of said north line of Lots 128 through 139; 
 
THENCE easterly, parallel with and 10 feet north of said north line of Lots 128 through 139 to a point 
being on the southerly prolongation of a line parallel with and 10 feet west of the west line of Lots 270, 
272 and 274; 
 
THENCE northerly, parallel with and 10 feet west of said west line of Lots 270, 272 and 274 to a point on 
the westerly prolongation of the north line of Lot 270; 
 
THENCE easterly to the northwest corner of said Lot 270; 
 
THENCE southerly along said west line of Lots 270, 272 and 274 to the southwest corner of Lot 274; 
 
THENCE easterly along the south line of said Lot 274 of the southeast corner of said lot; 
THENCE southerly to the POINT OF BEGINNING.

-30- 
 
 
 
EXHIBIT B  
 
City Property Legal Description 
 
 
PARCEL NO. 1:  
LOTS 128 THROUGH 139, INCLUSIVE, CHANDLER, ACCORDING TO BOOK 5 OF 
MAPS, PAGE 34, RECORDS OF MARICOPA COUNTY, ARIZONA;  
EXCEPT THAT PART OF LOT 139 DESCRIBED AS FOLLOWS:  
BEGINNING AT THE SOUTHWEST CORNER OF SAID LOT 139; THENCE SOUTH 89 
DEGREES 24 MINUTES 17 SECONDS EAST ALONG THE SOUTH LINE THEREOF, A 
DISTANCE OF 3.00 FEET; 
THENCE NORTH 29 DEGREES 41 MINUTES 53 SECONDS EAST 5.79 FEET TO THE 
WEST LINE OF SAID LOT; 
THENCE SOUTH 1 DEGREES 30 MINUTES 18 SECONDS WEST ALONG SAID WEST 
LOT LINE, A DISTANCE OF 5.00 FEET TO THE POINT OF BEGINNING.  
PARCEL NO. 2:  
LOTS 268, 270, 272 AND 274, CHANDLER, ACCORDING TO BOOK 5 OF MAPS, PAGE 
34, RECORDS OF MARICOPA COUNTY, ARIZONA; EXCEPT THE NORTH 3 FEET OF 
LOT 268.  
PARCEL NO. 3:  
ABANDONED ALLEY BEING A PORTION OF CHANDLER, ACCORDING TO BOOK 5 
OF MAPS, PAGE 34, RECORDS OF MARICOPA COUNTY, ARIZONA, BEING MORE 
PARTICULARLY DESCRIBED AS FOLLOWS:  
BEGINNING AT A POINT MARKING THE NORTHEAST CORNER OF LOT 128 AS 
SHOWN IN SAID BOOK 5 OF MAPS, PAGE 34 OF MARICOPA COUNTY RECORDS;  
THENCE WESTERLY ALONG THE NORTH LINE OF LOTS 128 THROUGH 139 TO THE 
NORTHWESTERLY CORNER OF LOT 139;  
THENCE ALONG A NORTHERLY PROLONGATION OF THE WEST LINE OF SAID LOT 
139 TO A POINT THAT LIES 10 FEET NORTH OF SAID NORTH LINE OF LOTS 128 
THROUGH 139;  
THENCE EASTERLY, PARALLEL WITH AND 10 FEET NORTH OF SAID NORTH LINE 
OF LOTS 128 THROUGH 139 TO A POINT BEING ON THE SOUTHERLY PROLONGA-
TION OF A LINE PARALLEL WITH AND 10 FEET WEST OF THE WEST LINE OF LOTS 
270, 272 AND 274;  
THENCE NORTHERLY, PARALLEL WITH AND 10 FEET WEST OF SAID WEST LINE 
OF LOTS 270, 272 AND 274 TO A POINT ON THE WESTERLY PROLONGATION OF THE 
NORTH LINE OF LOT 270; \ 
THENCE EASTERLY TO THE NORTHWEST CORNER OF SAID LOT 270;  
THENCE SOUTHERLY ALONG SAID WEST LINE OF LOTS 270, 272 AND 274 TO THE 
SOUTHWEST CORNER OF LOT 274;

-31- 
 
 
 
THENCE EASTERLY TO THE SOUTH LINE OF SAID LOT 27 4 TO THE SOUTHEAST 
CORNER OF SAID LOT;  
THENCE SOUTHERLY TO THE POINT OF BEGINNING.

-32- 
 
 
 
EXHIBIT C  
Developer Property Legal Description  
 
PARCEL NO. 1:  
LOT 262 AND THE NORTH HALF OF LOT 264, CHANDLER, ACCORDING TO BOOK 5 
OF MAPS, PAGE 34, RECORDS OF MARICOPA COUNTY, ARIZONA;  
EXCEPT THE NORTH 5 FEET OF LOT 262; AND  
EXCEPT ANY PORTION OF SAID LOT 262, LYING WITHIN THE PROPERTY CON-
VEYED TO THE CITY OF CHANDLER IN SPECIAL WARRANTY DEED RECORDED 
AUGUST 19, 2005 AS 2005-1203142, OF OFFICIAL RECORDS, MORE PARTICULARLY 
DESCRIBED AS FOLLOWS:  
COMMENCING AT A BRASS CAP IN HAND HOLE, BEING THE NORTHWEST CORNER 
OF SECTION 34, TOWNSHIP 1 SOUTH, RANGE 5 EAST, AND MARKING THE MONU-
MENTED LINE OF ARIZONA AVENUE AT THE INTERSECTION OF CHANDLER 
BOULEVARD AND ARIZONA AVENUE, FROM WHICH A BRASS CAP FLUSH, MARK-
ING THE SAID MONUMENTED LINE AT THE INTERSECTION OF CHANDLER BOULE-
VARD AND WASHINGTON STREET, BEARS NORTH 89 DEGREES 48 MINUTES 00 
SECONDS EAST, 409.75 FEET;  
THENCE SOUTH 79 DEGREES 51 MINUTES 38 SECONDS EAST APPROXIMATELY 
222.87 FEET TO THE WEST LINE OF LOT 262, OF CHANDLER, ACCORDING TO BOOK 
5 OF MAPS, PAGE 34, RECORDS OF MARICOPA COUNTY, ARIZONA, AND A LINE 
PARALLEL WITH AND 40.00 FEET MEASURED PERPENDICULAR SOUTHERLY TO 
THE MONUMENTED LINE OF CHANDLER BOULEVARD, AND THE POINT OF BEGIN-
NING;  
THENCE NORTH 89 DEGREES 48 MINUTES 00 SECONDS EAST 149.93 FEET ALONG 
SAID PARALLEL LINE TO THE EAST LINE OF SAID LOT 262;  
THENCE SOUTH 00 DEGREES 37 MINUTES 30 SECONDS WEST 8.00 FEET ALONG 
SAID EAST LINE TO A LINE PARALLEL WITH AND 48.00 FEET MEASURED PERPEN-
DICULAR SOUTHERLY TO THE MONUMENTED LINE OF CHANDLER BOULEVARD;  
THENCE SOUTH 89 DEGREES 48 MINUTES 00 SECONDS WEST 149.93 FEET TO SAID 
WEST LINE OF LOT 262;  
THENCE NORTH 00 DEGREES 37 MINUTES 35 SECONDS EAST 8.00 FEET ALONG 
SAID WEST LINE TO THE POINT OF BEGINNING.  
PARCEL NO. 2:  
THE NORTH HALF OF LOT 266 AND THE SOUTH HALF OF LOT 264 AND THE NORTH 
3 FEET OF THE SOUTH HALF OF LOT 266, OF CHANDLER, ACCORDING TO BOOK 5 
OF MAPS, PAGE 34, RECORDS OF MARICOPA COUNTY, ARIZONA.

-33- 
 
 
 
PARCEL NO. 3:  
THE SOUTH 22 FEET OF LOT 266 AND THE NORTH 3 FEET OF LOT 268, OF CHAN-
DLER, ACCORDING TO THE BOOK 5 OF MAPS, PAGE 34 RECORDS OF MARICOPA 
COUNTY, ARIZONA.  
PARCEL NO. 4:  
LOTS 263, 265, 267 AND 269, OF CHANDLER, ACCORDING TO THE PLAT OF RECORD 
IN THE OFFICE OF THE COUNTY RECORDER OF MARICOPA COUNTY, ARIZONA, 
RECORDED AS BOOK 5 OF MAPS, PAGE 34;  
EXCEPTING FROM LOT 263, THE NORTH 5.00 FEET THEREOF; AND 
EXCEPTING THAT PORTION OF LOT 263 DESCRIBED AS FOLLOWS; 
BEGINNING AT THE NORTHWEST CORNER OF SAID LOT 263;  
THENCE SOUTH 01 DEGREES 30 MINUTES 18 SECONDS WEST ALONG THE WEST 
LINE THEREOF, A DISTANCE OF 5.00 FEET TO THE TRUE POINT OF BEGINNING;  
THENCE CONTINUING SOUTH 01 DEGREES 30 MINUTES 18 SECONDS WEST ALONG 
SAID WEST LOT LINE, A DISTANCE OF 20.00 FEET;  
THENCE NORTH 46 DEGREES 05 MINUTES 39 SECONDS EAST, 28.49 FEET TO THE 
SOUTHERLY RIGHT-OF-WAY LINE OF WILLIAMS FIELD ROAD;  
THENCE NORTH 89 DEGREES 19 MINUTES 01 SECONDS WEST ALONG SAID SOUTH-
ERLY RIGHT-OF-WAY LINE, A DISTANCE OF 20.00 FEET TO THE TRUE POINT OF 
BEGINNING.

-34- 
 
 
 
EXHIBIT D  
Alleyway License Area

r·4s•oo" E E CHANDLER-BOULEVARD
a 
N s9·4s'oo" E 
-.:t"o:::: 
rr20.oo· 
I 
I 
50'
R/W 
I 
w 
::, 
w 
z 
N 
N
r--­n 
b 
0 
z 
w 
n >
,: <( 
<.O <( 
LD z 
0 
N 
Ö 
I 
<( z 
50' A
I 7 
lleyway
A 
L 
A 
icense 
rea I 
L 
r,,11 AW
I 
I 
I 
I 
I 
I 
I 
I 
I 
I 
r 
l 
.--------------
Ç 
LOT 263 / 
È
É
LOT 262 
I ½ 
I 
(.(:, . 
APN:303-06-064A I 
c::, -"Sj-
I 
<D 
"'") 
. 
Ë Ì 
Ê V/ 
Í 
f") 
APN:303-06-063A 
r.o 
Ì 
LOT 264 
0) 
..-
f-
0 
....J
LOT 265 I 
Î ..-
I 
a..: 
Ï 
I 
-
LOT 267 
w Ð 
Ñ 
-----------
APN:303-06-066 
i-20" ALLEY 
3 
LOT 266 
Ò 
APN:303-06-068 
N ½ 
... -----------
?J 
APN:303-06-067A 
n 
r---
Ó 
-----------
n 
LOT269 
b 
b 
APN:303-06-069 
z ½ 
Ô 
0 
LOT 268 
<.n 
APN:303-06-0678 
POINTOFÕI/ 
BEGINNING 
LOT 270 
s 89·45'55" w_; 
APN:J0J-06-0l0A 
20.00' 
LOT 272 
APN:303-06-0 72A 
ALLEY VACATION- i-
I-
LOT 274 
DOC. NO. 04-0365563, MCR 
APN:J0J-06-074A 
C:::i 
× 
Ø 
(.(:, 
c::, 
c::, 
I CO r--.. I 
(.(:, ('") 
('") (.(:, 
<::) ..--
..-c::, 
If-
f- I 
80 08 
"')....I 
....J 
Î 
a..:
a..: 
Ï 
Ï 
----- ----.-----
I 
! 
I 
Ù 
Ú 
Û 
C:::i 
Ü 
Ý 
lco tr) 
tr) 
Þ 
c::, I.{) 
'q" c::, ('") N ,..-
0 <::}O) 
ro <::) 
Iß I C'0 
('") I C'0 
('") 
(.(:, ('") 
('") 
IN 
NI 
à ...... 
..--
(.(:, ..-
..--
..--
(.0..-
..-
(.(:, 
jf-
c::, f-
<::) ...... 
<::)f-
f-? 
I f-
f-
f-
I f-
f-
19 80 
0 o 0 80 0 o 
08
"'") ....J 
....J 
$s....J
....J
"'") ....J
....J 
$s....J
....J "'") 
I 
Î 
Î 
Î 
á 
â 
a..:
a..:
I 
Ï
Ï 
Ï 
Ï 
Ï 
I 
E BUFFALO STREET 
i 
S 89"46'09" W 
409.89' __ _ 
40'
R/W 
I-w 
w 
Ö 
I-
(/) z 
0 
z 
I 
C/) 
<( s 
z 
40' 
R/W 
_J 
..-, 
r..o 
LD 
ã 
N
"Sj-
r---
n 
10 
<.n 
I l A j YINGw: 
PO BOX 2170, CHANDLER, AZ 85244 
PH: (480) 244-7630 
darmijo@awlandsurvey.com 
EXHIBIT D 
ONE CHANDLER 
Job No.:21-105 Date:03-03-26 SH 2 of 2 
Exhibit D