Contact Name: Tim Murphy – FCD C Number: C-69-20-014-5-01
Phone Number: 506-4605
Return To: Sharon Rogers – FCD
Phone Number: 506-6764
AMENDMENT TO CONSTRUCTION MANAGER AT RISK
Rawhide Wash Flood Hazard Mitigation Project
Action Requested
Amend the authorization under agenda Item number (C-69-20-014-5-00), which authorized the award of
a Construction Manager at Risk contract with Rummel Construction, Inc. This amendment will increase
the current Final Draft Guaranteed Maximum price (GMP) to $30,000,000. The previous amount was
$15,000,000.
Authorize the Chairman to execute all contracts to Rummel Construction necessary to perform and
complete all pre-construction and construction activities without further action by the Board of Directors
provided that the aggregate of all such contracts does not exceed the sum of $30,000,000. The previously
approved total aggregate amount for all pre-construction and construction activities was $15,000,000.
On November 6, 2019, the Board of Directors authorized the Project Pre-Construction Services Contract
FCD 2019C024 (C-69-20-014-5-00) for the not to exceed amount of $500,000 and an estimated
construction cost of $14,500,000. For a combined total not to exceed $15,000,000. To date, Rummel
Construction has provided pre-construction services in the amount of approximately $300,000 through the
final design of Phase 1 and Phase 2. The current construction cost of Phase 1 is $14,300,000, and the
estimated Phase 2 construction cost is $15,400,000, brings the current combined total estimate to
$30,000,000. The increase in construction costs can be attributed to project-specific issues during design,
regulatory agency requirements, constructability input from the contractor, and significant market factors
such as increasing labor rates, equipment rates, and material prices.
This Agenda Item impacts Supervisorial Districts 2 and 3.
Additional Information:
On April 11, 2018 the Board of Directors adopted Resolution FCD2018R005 (C-69-18-028-6-00)
authorizing the District to advertise, select, negotiate, and award contracts for engineering and
construction services, negotiate project IGAs and acquire rights-of-way for the Rawhide Wash Flood
Hazard Mitigation project. The project includes improvements to existing floodwalls and levees which
must be certified to meet the Federal Emergency Management Agency’s requirements for floodwalls and
levees, and the project also includes the construction of new floodwalls and levees to contain the 100-
year flood within the Rawhide Wash corridor. The project construction limits are from Pinnacle Peak
Road to approximately ½ mile north of Happy Valley Road. This is a complex project and, as such, the
District selected the CMAR Contractor based on qualifications in order to obtain valuable
constructability input during the design effort through delivery of pre-construction services under the
CMAR contracting method. The project partners are the cities of Scottsdale and Phoenix along with the