Exhibit C: Approved Project Budget

Applicant Budget Narrative
Maricopa County Air Quality Department Allocation
MCAQD Amount: $529,115.74
Valleywise Health 20% Cost Share Amount: $132,278.94
Total Project Amount: $661,394.68
Administrative Expenses: $55,464.00
Supplies - $47,464.00
$47,464.00 is requested for EV charging equipment consisting of 10 charging stations with a total
of 20 ports. These units will support deployment across Valleywise Health sites (Maryvale, Mesa,
and Peoria) and directly contribute to expanded EV infrastructure and reduced emissions.
Community Outreach - $8,000.00
$8,000.00 is requested for advertising and public relations, media, publication and printing. The
funds will support community engagement activities across Maryvale, Mesa, and Peoria, including
public awareness campaigns, launch events, digital outreach, media, signage, and multilingual
materials to ensure equitable public access and utilization.
Contractual Expenses: $77,327.84
Preliminary Architecture and Engineering Designs – NEPA Review Included - $77,327.84
$77,327.84 is requested for the support of preliminary design services, including engineering
assessments, site design, and NEPA environmental review requirements necessary to prepare the
project for construction.
Construction Expenses: $330,775.20
Architectural And Engineering Basic Fees - $47,040.00
$47,040.00 is requested for permit drawings and engineering design services procured through a
competitive RFQ process.
Project Inspection Fees - $9,600.00
$9,600.00 is requested for Authority Having Jurisdiction (AHJ) inspection fees required during
installation.
Project Improvement - $274,135.20
$274,135.20 is requested for the full construction and turnkey installation of EV charging
infrastructure, including site preparation, installation, and commissioning across Valleywise
Health sites (Maryvale, Mesa, and Peoria). Procurement will follow RFQ and CM/GC methods in
compliance with 2 CFR 200.320.

Miscellaneous Expenses: $65,548.70
Networking - $18,000.00
$18,000.00 is requested to support 4G network integration to enable charger connectivity,
monitoring, and data reporting.
Miscellaneous - $47,548.70
$47,548.70 is requested for inflation adjustments and contingency to account for cost variability
and project risk.
Valleywise Health Cost Share Allocation (20% Match)
Valleywise Health will cover 20% of the budgeted costs. The required 20% Match will be provided through
non-federal cash contributions applied to eligible project costs and documented in the overall budget,
with reporting as in-kind match. All project expenditures, including federal and cost shares, will comply
with Uniform Guidance (2 CFR 200).
Administrative Expenses: $13,866.00
Supplies - $11,866.00
$11,866.00 is requested for EV charging equipment consisting of 10 charging stations with a total
of 20 ports. These units will support deployment across Valleywise Health sites (Maryvale, Mesa,
and Peoria) and directly contribute to expanded EV infrastructure and reduced emissions. The
required 20% Match will be provided through non-federal cash contributions with reporting as in-
kind match.
Community Outreach - $2,000.00
$2,000.00 is requested for advertising and public relations, media, publication and printing. The
funds will support community engagement activities across Maryvale, Mesa, and Peoria, including
public awareness campaigns, launch events, digital outreach, media, signage, and multilingual
materials to ensure equitable public access and utilization. The required 20% Match will be
provided through non-federal cash contributions with reporting as in-kind match.
Contractual Expenses: $19,331.96
Preliminary Architecture and Engineering Designs – NEPA Review Included - $19,331.96
$19,331.96 is requested for the support of preliminary design services, including engineering
assessments, site design, and NEPA environmental review requirements necessary to prepare the
project for construction. The required 20% Match will be provided through non-federal cash
contributions with reporting as in-kind match.
Construction Expenses: $82,693.80
Architectural And Engineering Basic Fees - $11,760
$11,760.00 is requested for permit drawings and engineering design services procured through a
competitive RFQ process. The required 20% Match will be provided through non-federal cash
contributions with reporting as in-kind match.

Project Inspection Fees - $2,400.00
$2,400.00 is requested for Authority Having Jurisdiction (AHJ) inspection fees required during
installation. The required 20% Match will be provided through non-federal cash contributions with
reporting as in-kind match.
Project Improvement - $68,533.80
$68,533.80 is requested for the full construction and turnkey installation of EV charging
infrastructure, including site preparation, installation, and commissioning across Valleywise
Health sites (Maryvale, Mesa, and Peoria). Procurement will follow RFQ and CM/GC methods in
compliance with 2 CFR 200.320. The required 20% Match will be provided through non-federal
cash contributions with reporting as in-kind match.
Miscellaneous Expenses: $16,387.18
Networking - $4,500.00
$4,500.00 is requested to support 4G network integration to enable charger connectivity,
monitoring, and data reporting. The required 20% Match will be provided through non-federal cash
contributions with reporting as in-kind match.
Miscellaneous - $11,887.18
$11,887.18 is requested for inflation adjustments and contingency to account for cost variability
and project risk. The required 20% Match will be provided through non-federal cash contributions
with reporting as in-kind match.

AIR QUALITY DEPARTMENT
Applicant Detailed Budget
1.) ADMINISTRATIVE EXPENSES
a.) PERSONNEL
Hourly Labor Total Personnel Costs Maricopa County
Labor Category (Position) Hours Applicant Cost Share
Rate (S) (S) AQD Costs
Position $0.00 0 $0.00 $0.00 $0.00
Position $0.00 0 $0.00 $0.00 $0.00
Position $0.00 0 $0.00 $0.00 $0.00
Position $0.00 0 $0.00 $0.00 $0.00
Position $0.00 0 $0.00 $0.00 $0.00
TOTAL PERSONNEL COSTS: 0 $0.00 $0.00 $0.00
b.) FRINGE BENEFITS
Basis of Rate (Labor Category or Individual Total Direct Fringe Benefit Fringe Benefit Rate Maricopa County
Period (FY) Applicant Cost Share
Labor) Labor Costs Rate (%) ($) AQD Costs
Position $0.00 0% $0.00 $0.00 $0.00
Position $0.00 0% $0.00 $0.00 $0.00
Position $0.00 0% $0.00 $0.00 $0.00
Position $0.00 0% $0.00 $0.00 $0.00
Position $0.00 0% $0.00 $0.00 $0.00
TOTAL FRINGE BENEFITS COSTS: $0.00 $0.00 $0.00
c.) TRAVEL
Other Travel Maricopa County
Labor Category Airfare Lodging Per Diem Travel Costs ($) Applicant Cost Share
Expenses AQD Costs
Position $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Position $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL TRAVEL COSTS: $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
d.) SUPPLIES
Number of Maricopa County
Supply Item Cost Per Item Supplies Costs ($) Applicant Cost Share
Items AQD Costs
EV Charger Equipment - total of 10 stations w/ 20 ports $5,933.00 10 $59,330.00 $47,464.00 $11,866.00
$0.00 0 $0.00 $0.00 $0.00
TOTAL SUPPLIES COSTS $59,330.00 $47,464.00 $11,866.00
e.) SERVICES
Maricopa County
Service Item Services Costs ($) Applicant Cost Share
AQD Costs
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
TOTAL SERVICES COSTS $0.00 $0.00 $0.00
f.) COMMUNITY OUTREACH
Community Outreach Maricopa County
Community Outreach Item Applicant Cost Share
Costs ($) AQD Costs
Community Enagagement (Maryvale, Mesa, & Peoria): Public Campaign, Launch Ceremony, Digital
& Network Integration, Social Media, Signage, and Multilingual Access Information $10,000.00 $8,000.00 $2,000.00
$0.00 $0.00 $0.00
TOTAL COMMUNITY OUTREACH COSTS $10,000.00 $8,000.00 $2,000.00
g.) INDIRECT COSTS
Indirect Rate Maricopa County
Modified Total Direct Cost (MTDC) Base Amount Period (FY) Indirect Costs ($) Applicant Cost Share
(%) AQD Costs
$0.00 0% $0.00 $0.00 $0.00
$0.00 0% $0.00 $0.00 $0.00
TOTAL INDIRECT COSTS: $0.00 $0.00 $0.00
TOTAL ADMINISTRATIVE EXPENSES: $69,330.00 $55,464.00 $13,866.00

AIR QUALITY DEPARTMENT
Applicant Detailed Budget
2.) CONTRACTUAL EXPENSES
a.) PRELIMINARY EXPENSES
Maricopa County
Preliminary Item Preliminary Costs ($) Applicant Cost Share
AQD Costs
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
TOTAL PRELIMINARY COSTS $0.00 $0.00 $0.00
b.) PRELIMINARY ARCHITECTURE AND ENGINEERING DESIGNS - NEPA REVIEW INCLUDED
Preliminary Architecture and Maricopa County
Preliminary Architecture and Engineering Designs - NEPA Review Included Applicant Cost Share
Engineering Design Costs ($) AQD Costs
Contractual: Preliminary Design w/Architecture & Engineering designs. NEPA
Review included. $96,659.80 $77,327.84 $19,331.96
$0.00 $0.00 $0.00
TOTAL PRELIMINARY ARCHITECTURE AND ENGINEERING DESIGN COSTS $0.00 $77,327.84 $19,331.96
c.) FINAL PRELIMINARY DESIGNS
Maricopa County
Final Preliminary Design Item Final Preliminary Design Costs ($) Applicant Cost Share
AQD Costs
$0.00 $0.00 $0.00
$0.00 $0.00 $0.00
TOTAL FINAL PRELIMINARY DESIGN COSTS $0.00 $0.00 $0.00
TOTAL CONTRACTUAL EXPENSES: $0.00 $77,327.84 $19,331.96

AIR QUALITY DEPARTMENT
Applicant Detailed Budget
3.) CONSTRUCTION EXPENSES
a.) LAND, STRUCTURES, RIGHT-OF-WAY, APPRAISALS, etc.
Land, Structures,
Brief Description Of Each Basis Of The Estimate For Each Right-Of-Way, Maricopa County Applicant Cost
Element SITE 1 SITE 2 SITE 3 SITE 4 SITE 5
Element And Location Element Appraisals, etc. Costs AQD Costs Share
($)
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL LAND, STRUCTURES, RIGHT-OF-WAY, APPRAISALS, etc. COSTS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
b.) ARCHITECTURAL AND ENGINEERING BASIC FEES
Work To Be Performed and Architectural And
Proposed Type Of Competitive Maricopa County Applicant Cost
Entity Name Project Section/Task SITE 1 SITE 2 SITE 3 SITE 4 SITE 5 Engineering Basic Fee
Procurement Method AQD Costs Share
(2 - 3 Sentences) Costs ($)
TBD Permit Drawings ARFQ $14,400.00 $31,200.00 $13,200.00 $0.00 $0.00 $58,800.00 $47,040.00 $11,760.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL ARCHITECTURAL AND ENGINEERING BASIC FEE COSTS $14,400.00 $31,200.00 $13,200.00 $0.00 $0.00 $58,800.00 $47,040.00 $11,760.00
c.) OTHER ARCHITECTURAL AND ENGINEERING FEES
Work To Be Performed and Other Architectural
Proposed Type Of Competitive Maricopa County Applicant Cost
Entity Name Project Section/Task SITE 1 SITE 2 SITE 3 SITE 4 SITE 5 And Engineering Fee
Procurement Method AQD Costs Share
(2 - 3 Sentences) Costs ($)
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL OTHER ARCHITECTURAL AND ENGINEERING FEE COSTS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
d.) PROJECT INSPECTION FEES
Work To Be Performed and Proposed Type Of Competitive Project Inspection Fee Maricopa County Applicant Cost
Entity Name SITE 1 SITE 2 SITE 3 SITE 4 SITE 5
Project Section/Task Procurement Method Costs ($) AQD Costs Share
Project Inspection fees AHJ Inspections N/A $2,831.10 $6,479.46 $2,689.44 $0.00 $0.00 $12,000.00 $9,600.00 $2,400.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL PROJECT INSPECTION FEE COSTS $2,831.10 $6,479.46 $2,689.44 $0.00 $0.00 $12,000.00 $9,600.00 $2,400.00
e.) LAND DEVELOPMENT/SITE WORK
Proposed
Anticipated
Type Of
Project Land Development/ Maricopa County Applicant Cost
Entity Name Description Of Work Competitive SITE 1 SITE 2 SITE 3 SITE 4 SITE 5
Delivery Site Work Costs ($) AQD Costs Share
Procurement
Type**
Method*
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL LAND DEVELOPMENT/SITE WORK COSTS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
*If a noncompetitive procurement is necessary, indicate the circumstance that applies in accordance with 2 CFR 200.320(c) and request approval, if applicable.
**Design-Bid-Build or Design-Build or Construction Manager/General Contractor (CM/GC (as known as Construction Manager at Risk (CMAR)))
f.) RELOCATION EXPENSES AND PAYMENTS
Relocation Expenses
Brief Description Of Elements Basis Of The Estimate For Each Maricopa County Applicant Cost
Element SITE 1 SITE 2 SITE 3 SITE 4 SITE 5 and Payments Costs
And Locations Element AQD Costs Share
($)
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL RELOCATION EXPENSES AND PAYMENTS COSTS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
g.) DEMOLITION AND REMOVAL
Proposed
Anticipated
Type Of
Project Demolition and Maricopa County Applicant Cost
Entity Name Description Of Work Competitive SITE 1 SITE 2 SITE 3 SITE 4 SITE 5
Delivery Removal Costs ($) AQD Costs Share
Procurement
Type**
Method*
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL DEMOLITION AND REMOVAL COSTS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
*If a noncompetitive procurement is necessary, indicate the circumstance that applies in accordance with 2 CFR 200.320(c) and request approval, if applicable.
**Design-Bid-Build or Design-Build or Construction Manager/General Contractor (CM/GC (as known as Construction Manager at Risk (CMAR)))
h.) PROJECT IMPROVEMENT
Proposed
Anticipated
Type Of
Project Project Improvement Maricopa County Applicant Cost
Entity Name Description Of Work Competitive SITE 1 SITE 2 SITE 3 SITE 4 SITE 5
Delivery Costs ($) AQD Costs Share
Procurement
Type**
Method*
All costs associated with
construction and
commissioning for a Turnkey
Installation of EV Charger
Project Improvement Construction stations (excludes permit fees) RFQ CM/GC $86,139.00 $180,329.00 $76,201.00 $0.00 $0.00 $342,669.00 $274,135.20 $68,533.80
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL PROJECT IMPROVEMENT COSTS $86,139.00 $180,329.00 $76,201.00 $0.00 $0.00 $342,669.00 $274,135.20 $68,533.80
*If a noncompetitive procurement is necessary, indicate the circumstance that applies in accordance with 2 CFR 200.320(c) and request approval, if applicable.
**Design-Bid-Build or Design-Build or Construction Manager/General Contractor (CM/GC (as known as Construction Manager at Risk (CMAR)))
TOTAL CONSTRUCTION EXPENSES: $413,469.00 $82,693.80 $0.00

AIR QUALITY DEPARTMENT
Applicant Detailed Budget
4.) MISCELLANEOUS EXPENSES
a.) NETWORKING
Maricopa County
Networking Item SITE 1 SITE 2 SITE 3 SITE 4 SITE 5 Networking Costs ($) Applicant Cost Share
AQD Costs
Networking - 4G Networking $4,500.00 $12,000.00 $6,000.00 $0.00 $0.00 $22,500.00 $18,000.00 $4,500.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL NETWORKING COSTS $4,500.00 $12,000.00 $6,000.00 $0.00 $0.00 $22,500.00 $18,000.00 $4,500.00
b.) CAPITAL EQUIPMENT (Unit cost of $10K or more - for Equipment Items less than $10K use Supplies Section - this includes charging port expenses)
Basis of the Estimate (Vendor Number of Maricopa County
Equipment Item Cost Per Unit SITE 1 SITE 2 SITE 3 SITE 4 SITE 5 Equipment Costs Applicant Cost Share
quotes or Engineering Units AQD Costs
$0.00 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL EQUIPMENT COSTS $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
c.) MISCELLANEOUS
Miscellaneous Costs Maricopa County
Miscellaneous Item SITE 1 SITE 2 SITE 3 SITE 4 SITE 5 Applicant Cost Share
($) AQD Costs
Misc. Inflation + Contingency $15,172.00 $30,153.88 $14,110.00 $0.00 $0.00 $59,435.88 $47,548.70 $11,887.18
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL MISCELLANEOUS COSTS $15,172.00 $30,153.88 $14,110.00 $0.00 $0.00 $59,435.88 $47,548.70 $11,887.18
TOTAL MISCELLANEOUS EXPENSES: $81,935.88 $65,548.70 $16,387.18

AIR QUALITY DEPARTMENT
Applicant Detailed Budget
01 02 03 04
PRELIMINARY DESIGN EQUIPMENT CHARGING STATION SITE LAUNCH
AND NEPA REVIEW PROCUREMENT AND INSTALLED
PERMITS ISSUED • Site opens to the public
• Subrecipient must have • Electrical upgrades to site must
completed their RFP process and • Permits must be obtained for all be complete • Initial site profile data submitted
selected a contractor work being done (construction, to MCAQD
• Received complete preliminary dust control, electrical, etc.) • for Equipment operation installed and ready • Final allowable costs
designs with a quote for final • Equipment matching preliminary reimbursed
installation design quote must be purchased • Networking and software
and received installed and accessible to
• Completed a National MCAQD and subrecipient
Environmental Policy Act (NEPA)
review • Site restored for consumer use
• Final inspections passed
MILESTONE BREAKDOWN
MILESTONE ONE (1) MILESTONE TWO (2) MILESTONE THREE (3) MILESTONE FOUR (4) TOTAL BUDGET
Budget Category Description MCAQD Share ($) Cost Share ($) MILESTONE TOTAL MCAQD Share ($) Cost Share ($) MILESTONE TOTAL MCAQD Share ($) Cost Share ($) MILESTONE TOTAL MCAQD Share ($) Cost Share ($) MILESTONE TOTAL TOTAL COST ($)
1.) Administrative Expenses
Personnel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Benefits (ERE) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Supplies $0.00 $0.00 $0.00 $47,464.00 $11,866.00 $59,330.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $59,330.00
Services $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Community Outreach $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $8,000.00 $2,000.00 $10,000.00 $10,000.00
Indirect Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL Admin Costs $0.00 $0.00 $0.00 $47,464.00 $11,866.00 $59,330.00 $0.00 $0.00 $0.00 $8,000.00 $2,000.00 $10,000.00 $69,330.00
2.) Contractual Expenses
Preliminary Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Preliminary Design w/Architecture and
Engineering designs. NEPA Review
included. $77,327.84 $19,331.96 $96,659.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $96,659.80
Final Design $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TOTAL Contractual Costs $77,327.84 $19,331.96 $96,659.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $96,659.80
3.) Construction Expenses
Land, Structure, Right-of-Way $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Architectural and Engineering Basic Fees $0.00 $0.00 $0.00 $47,040.00 $11,760.00 $58,800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $58,800.00
Other Arch. and Eng. Fees $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Inspection Fees $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $9,600.00 $2,400.00 $12,000.00 $0.00 $0.00 $0.00 $12,000.00
Land Development $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Relocation Expense $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Demolition and Removal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Improvement $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $274,135.20 $68,533.80 $342,669.00 $0.00 $0.00 $0.00 $342,669.00
TOTAL Construction Costs $0.00 $0.00 $0.00 $47,040.00 $11,760.00 $58,800.00 $283,735.20 $70,933.80 $354,669.00 $0.00 $0.00 $0.00 $413,469.00
4.) Miscellaneous Expenses
Networking $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $18,000.00 $4,500.00 $22,500.00 $0.00 $0.00 $0.00 $22,500.00
Equipment $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Miscellaneous Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $42,793.83 $10,698.46 $53,492.29 $4,754.87 $1,188.72 $5,943.59 $59,435.88
TOTAL Miscellaneous Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $60,793.83 $15,198.46 $75,992.29 $4,754.87 $1,188.72 $5,943.59 $81,935.88
TOTAL BILLING $77,327.84 $19,331.96 $96,659.80 $94,504.00 $23,626.00 $118,130.00 $344,529.03 $86,132.26 $430,661.29 $12,754.87 $3,188.72 $15,943.59 $661,394.68
Cost Share Percentage 80% 20% 100% 80% 20% 100% 80% 20% 100% 80% 20% 100%

Application Budget Template
Prepared for the Maricopa County CFI Funded EV Infrastructure Program
Project Name: Valleywise Health EV Charging Stations
Project Manager: Lalitha Madhavan (Valleywise)
Organization/Entity: MCAQD
Unique ID: 1443703434
Project Budget Summary
Budget Category Description MCAQD Share ($) Cost Share ($) Project Total ($)
Admin: Personnel $0.00 $0.00 $0.00
Admin: Benefits (ERE) $0.00 $0.00 $0.00
Admin: Travel $0.00 $0.00 $0.00
Admin: Supplies $47,464.00 $11,866.00 $59,330.00
Admin: Services $0.00 $0.00 $0.00
Admin: Community Outreach $8,000.00 $2,000.00 $10,000.00
Admin: Indirect Costs $0.00 $0.00 $0.00
TOTAL Admin Costs $55,464.00 $13,866.00 $69,330.00
Contractual: Preliminary Expenses $0.00 $0.00 $0.00
Contractual: Preliminary Design w/Architecture and
Engineering designs. NEPA Review included. $77,327.84 $19,331.96 $96,659.80
Contractual: Final Design $0.00 $0.00 $0.00
TOTAL Contractual Costs $77,327.84 $19,331.96 $96,659.80 Site Costs Site 1 Site 2 Site 3 Site 4 Site 5
Constr: Land, Structure, Right-of-Way $0.00 $0.00 $0.00 Land, Structure, Right-of-Way $0.00 $0.00 $0.00 $0.00 $0.00
Constr: Architectural and Engineering Basic Fees $47,040.00 $11,760.00 $58,800.00 Basic Fees $14,400.00 $31,200.00 $13,200.00 $0.00 $0.00
Constr: Other Arch. and Eng. Fees $0.00 $0.00 $0.00 Other Arch. and Eng. Fees $0.00 $0.00 $0.00 $0.00 $0.00
Constr: Project Inspection Fees $9,600.00 $2,400.00 $12,000.00 Project Inspection Fees $2,831.10 $6,479.46 $2,689.44 $0.00 $0.00
Constr: Land Development $0.00 $0.00 $0.00 Land Development $0.00 $0.00 $0.00 $0.00 $0.00
Constr: Relocation Expense $0.00 $0.00 $0.00 Relocation Expense $0.00 $0.00 $0.00 $0.00 $0.00
Constr: Demolition and Removal $0.00 $0.00 $0.00 Demolition and Removal $0.00 $0.00 $0.00 $0.00 $0.00
Constr: Project Improvement $274,135.20 $68,533.80 $342,669.00 Project Improvement $86,139.00 $180,329.00 $76,201.00 $0.00 $0.00
TOTAL Construction Costs $330,775.20 $82,693.80 $413,469.00
Networking $18,000.00 $4,500.00 $22,500.00 Networking $4,500.00 $12,000.00 $6,000.00 $0.00 $0.00
Equipment $0.00 $0.00 $0.00 Equipment $0.00 $0.00 $0.00 $0.00 $0.00
Miscellaneous Costs $47,548.70 $11,887.18 $59,435.88 Miscellaneous Costs $15,172.00 $30,153.88 $14,110.00 $0.00 $0.00
TOTAL Miscellaneous Costs $65,548.70 $16,387.18 $81,935.88 TOTAL SITE COSTS $123,042.10 $260,162.34 $112,200.44 $0.00 $0.00
TOTAL BILLING $529,115.74 $132,278.94 $661,394.68
Cost Share Percentage 80% 20% 100%