CONSTRUCTION MANAGEMENT AT RISK (CMR) PROFESSIONAL SERVICES CONTRACT Durango Juvenile Courts Demolition Office of Procurement Services Serial # 260056-ROQ Contract # 250056-ROQ C-__________________________________ Project # 1706-27-00812 Facilities Management, Maricopa County Arizona AGREEMENT BETWEEN THE COUNTY OF MARICOPA, ARIZONA AND DESIGN PROFESSIONAL -For- CONSTRUCTION MANAGER AT RISK (CMR) PROJECT PROJECT DELIVERY METHOD THIS AGREEMENT made this 30th day of September in the year 2026. BY AND BETWEEN THE COUNTY OF MARICOPA, ARIZONA, hereinafter called the "Owner,” and Shive-Hattery hereinafter called the "Design Professional" or “DP.” NOW, THEREFORE, for and in consideration of the mutual covenants and agreements set forth herein, and other good and valuable consideration, the receipt and sufficiency of which is hereby acknowledged, the parties hereto, intending to be legally bound hereby, do covenant and agree as follows: PROJECT NAME: Durango Juvenile Courts Demolition PROJECT NUMBER: _FMD Project # 1706-27-0082_________________________________ CONTRACT NUMBER: _26006-ROQ____________________________________________ Durango Juvenile Courts Demolition Page | 2 CMR Professional Services Contract Serial # 260056-ROQ TABLE OF CONTENTS PAGE # SCOPE OF WORK ...................................................................................................................... 4 ARTICLE 1: DEFINITIONS ....................................................................................................... 5 ARTICLE 2: DP SERVICES AND RESPONSIBILITIES ....................................................... 8 ARTICLE 3: SUBCONSULTANTS ......................................................................................... 18 ARTICLE 4: OWNER’S RESPONSIBILITIES ...................................................................... 19 ARTICLE 5: PROJECT MANAGEMENT AND REVIEW PROCEDURES ....................... 19 ARTICLE 6: BASIS OF COMPENSATION ........................................................................... 20 ARTICLE 7: PAYMENTS TO DP ............................................................................................ 22 ARTICLE 8: INDEMNIFICATION AND INSURANCE ......................................................... 22 ARTICLE 9: PERFORMANCE ................................................................................................ 25 ARTICLE 10: OWNERSHIP OF DOCUMENTS .................................................................. 25 ARTICLE 11: ALTERNATIVE DISPUTE RESOLUTION .................................................... 26 ARTICLE 12: SUSPENSION AND TERMINATION ............................................................ 29 ARTICLE 13: MISCELLANEOUS ........................................................................................... 30 EXHIBIT “A”: HOURLY RATES AND HOURS ................................................................... 37 EXHIBIT “B”: LUMP SUM AMOUNT ...................................................................................... 38 EXHIBIT ‘C’: Record Drawing Procedures ........................................................................... 39 Durango Juvenile Courts Demolition Page | 3 CMR Professional Services Contract Serial # 260056-ROQ SCOPE OF WORK Design Professionals (“DP”) shall furnish Architectural and Engineering Services (“A/E Services”) for the Project and Contract described above, upon issuance by the Director of Maricopa County Facilities Management Department (“MCFMD”) (“Director”) or Director’s designee of DP’s Authorization(s) to Proceed. DP shall furnish: planning, programming, feasibility studies, Construction Estimates, partial or complete design services, including preparation drawings and documents necessary for Subcontractor bidding and development of a GMP, construction contract administration and observation, review of recommendations and other deliverables of the Construction Manager At Risk (“CMR”), review of Contractor Change Order Requests, review of Baseline and updated Construction Schedules, review work prepared by other professional consultants and the Contractor, building commissioning, and other miscellaneous A/E Services that may be required and are authorized by Owner. DP acknowledges and warrants to Owner that in connection with Entering into this Agreement DP has received and reviewed a copy of Owner’s Standard Form of Agreement for Services by a CMR for Pre- Construction Services and for Construction Phase Services to be used for the Project and has familiarized itself with the contents of both of those Agreements and all attachments or exhibits thereto and will develop all design documents hereunder to be fully compatible to and consistent with those Agreements. The terms of that Standard Form of Agreement for Services by a CMR are incorporated herein by reference (as outlining DP duties) and are made a part hereof. DP also agrees that at time of execution of any agreement between Owner and CMR, DP will have the responsibility to obtain from Owner an executed or conformed copy of all contracts constituting the CMR contract for reference and use in DP’s A/E Services at all times after the CMR Agreement is executed and in force. The Director or Director’s designee may issue an Authorization to Proceed to encompass the entire Basic Services as described in Section 2.2 herein for the Project or a portion of Basic Services, or for discretionary tasks as specified in Section 2.3 herein for Additional Services or 2.4 herein for Reimbursable Costs. The fees to be paid by Owner for DP Services shall be: A lump sum, not to exceed (See Section 6.1 herein). (Exhibit ‘B’). However, DP shall provide Hourly Rates and hours (by phase and service). (See Section 6.2 herein Exhibit ‘A’) for reference in the event of added services or change orders. The Director or Director’s designee will confer with DP before any Authorization to Proceed is issued. DP will discuss the scope of the DP Services covered by the Authorization, the time to complete those DP Services and the fee for those DP Services provided that when no agreement is reached as to the fee for a particular Authorization to Proceed, payment for those DP Services will be made in accordance with Section 6.1. Durango Juvenile Courts Demolition Page | 4 CMR Professional Services Contract Serial # 260056-ROQ ARTICLE 1: DEFINITIONS 1.1 ADDITIONAL SERVICES: Those DP Services specified in Section 2.3. 1.2 AS-BUILT DRAWINGS: The As-Built Drawings (provided by the Contractor) shall consist of a set of drawings which clearly indicate all field changes (modifications, additions and deletions) that were made to the Contract Documents to adapt to field conditions and field changes. Such drawings shall include but not be limited to all new and existing buried and concealed installation of piping, conduit and utility services identified and/or field-surveyed in the course of design through construction. All buried and concealed items both inside and outside the facility shall be accurately located on the As-Built Drawings as to depth, size and material and in relationship to not less than two permanent features such as interior or exterior wall faces. The As-Built Drawings shall be clean and all changes, corrections, and dimensions shall be indicated in a neat and legible manner and fully comply with the format guidelines prescribed in attached Exhibit ‘C. One (1) hard-copy set of the As-Built Drawings shall be submitted to the Owner with submittal of the Record Drawings. See Section 1.28 below for “Record Drawings.”. 1.3 AUTHORITY HAVING JURISDICTION: The Maricopa County Planning and Development Department, the State Fire Marshal, the State Elevator Inspector and any Arizona municipal corporation within which the Project is situated. 1.4 AUTHORIZATION TO PROCEED: A document issued by the Director or Director’s designee to DP authorizing the performance of specific professional services, and stating the time for completion and the amount of fee authorized for such services. 1.5 BASIC SERVICES: Those DP Services defined in Section 2.2. 1.6 CHECK SET: A set of drawings that have been checked for errors and discrepancies between the design disciplines. 1.7 CONSTRUCTION DOCUMENTS: The documents prepared by DP and their Sub-consultants and referred to in Section 2.2 of this Agreement to be used for permitting and construction of the Project. 1.8 CONSTRUCTION ESTIMATE: A detailed estimate of all construction cost, including but not limited to all on-site and off-site construction activities, all utility designs, equipment and construction fees, Contractor general conditions, general requirements, mark-ups and contingencies and escalation. 1.9 CONSTRUCTION MANAGER AT RISK (“CMR”): A consultant selected pursuant to a Request for Qualifications that shall contract with Owner in two (2) phases: initially as a consultant to Owner during the design phase, and then serving the function of the Contract Manager during construction if a Contract is executed. 1.10 CONSTRUCTION MANAGEMENT AT RISK: A process that allows an Owner to select a CMR based on qualifications; makes the CMR a member of a collaborative project team; centralize responsibility for construction under a single contract; obtain a bonded, guaranteed maximum price; produce a more manageable, predictable project; saves time and money; and reduces risk for the client, Owner, DP and the CMR. 1.11 CONSTRUCTION PROJECT MANAGER: An employee of Owner or agent of the Owner assigned by the Director to monitor the construction and design services to be performed under this Agreement and the construction of the Project as a direct representative of Owner. The Director reserves the right, not to assign a Construction Project Manager to the project. In such case the Owner’s Project Manager will assume all Owner responsibilities for the project. Durango Juvenile Courts Demolition Page | 5 CMR Professional Services Contract Serial # 260056-ROQ 1.12 CONTRACT DOCUMENTS: This Agreement, the CMR Proposal, the Design Proposal by CMR, the Construction Contract for this Project (with its attachments), the Drawings and Project Specifications and Construction Documents and exhibits and documents related thereto or contemplated thereby, as well as all Addenda, Amendments and Change Orders related to each with respect to the Project and all changes to said documents issued by Owner after execution of this Agreement. 1.13 CONTRACT TIME: The time between the date when the Notice to Proceed is issued to the CMR and Final Completion of the Work. 1.14 COUNTY MANAGER: The chief executive officer of Owner. 1.15 DAY: Shall mean a calendar day. 1.16 DEFERRED SUBMITTALS: Design deferred to the Contractor by the DP for completion of the design due to the complexity and associated Code impacts. Typical Deferred Submittals may include Curtain Wall Systems, Stairs, Precast, Fire Alarm, and Fire Protection System. DP shall provide a list of recommended Deferred Submittals to the Owner for approval. 1.17 DESIGN DEVELOPMENT DOCUMENTS: The drawings, outline specifications and other documents to delineate and describe the size and character of the entire Project as to architectural, civil, structural, mechanical, plumbing, fire alarm, and electrical systems, landscaping, construction and finish materials and other items incidental thereto, and as required by the Project Manager. 1.18 DESIGN PROFESSIONAL (“DP”): The individual, partnership, LLC, professional association, corporation, association, joint venture, or any combination thereof, of properly registered professional architects and/or engineers, that has entered into the Agreement to provide professional services to Owner. DP is the prime Project professional as defined in the Rules issued by the Arizona Board of Technical Registration. 1.19 DIRECTOR OF THE FACILITIES MANAGEMENT DEPARTMENT OR DIRECTOR: The Director of Facilities Management Department of the County of Maricopa, Arizona, having the authority and responsibility for management of the specific project(s) to be carried out under this Agreement. From time to time the Director may act through a Director’s designee. 1.20 FINAL CONSTRUCTION DOCUMENTS: A complete and accurate set of drawings and specifications advancing the content of Design Development documents so as to allow the permitting and construction of the Project. 1.21 INSPECTOR: An employee or consultant assigned by the Project Manager or Construction Project Manager to make observations of Work performed by the CMR. 1.22 MAXIMUM COST LIMIT: The maximum amount budgeted by Maricopa for the total cost of the construction of the Work on the Project. 1.23 OWNER: The Owner is Maricopa County Facilities Management Department (FMD), the public body which is a party hereto and the entity for which this contract is to be performed. In all respects hereunder, Owner’s performance is pursuant to Owner’s position as Owner of the Project. In the event Owner exercises its regulatory authority as a governmental body, the exercise of such regulatory authority and the enforcement of any rules, regulations, codes, laws and ordinances shall be deemed to have occurred pursuant to Owner’s authority as a governmental body and shall not be attributable in any manner to Owner as a party to this contract. 1.24 PAYMENT APPLICATION: The certified form submitted by the CMR requesting payment for construction work to be reviewed by DP and approved by the Construction Project Manager and/or Project Manager. Durango Juvenile Courts Demolition Page | 6 CMR Professional Services Contract Serial # 260056-ROQ 1.25 PROJECT: The scope of construction, alteration, or repair and all services and incidents thereto of a County of Maricopa, Arizona facility as approved by Owner. 1.26 PROJECT DEVELOPMENT SCHEDULE: A written document providing the proposed completion date of each Phase of the Project through design, selection of CMR, construction and proposed date of occupancy by Owner. 1.27 PROJECT MANAGER: An employee of Owner or agent of the Owner assigned by the Director to monitor the services to be performed under this Agreement and the construction of the Project as a direct representative of Owner. 1.28 RECORD DRAWINGS: Record Drawings are the official record drawings that document what was constructed. The DP shall prepare Record Drawings from the As-Built documents for the Project. The DP shall provide to Owner one (1) set of Record Drawings as a printed, hard-copy full-sized set with one (1) corresponding set of digital media containing the complete Construction Drawings for the Project in AutoCAD, complying with the guidelines prescribed in attached Exhibit ‘C’. The resulting image produced on the viewing screen shall include all of the kinds of information that is visible on full-sized originals approved for permit and issued for construction. These provisions apply to all projects conducted at Maricopa County. All electronic media with As-Built or Record Drawings MUST be in AutoCAD or BIM format (consistent with guidelines in attached Exhibit C) with a matching PDF. 1.29 SCHEMATIC DESIGN DOCUMENTS: The drawings and other documents illustrating the scale and relationship of the Project components including the selection of materials, systems, and equipment, as well as initial program drawings and documents that establish and describe the size and character of the Project as to architectural, structural, mechanical, electrical, plumbing, fire alarm, and fire protection systems, materials and additional engineering services as deemed necessary by the Owner and DP to produce a complete and accurate set of drawings and specifications for the permitting and construction of the Project. 1.30 SCHEMATIC DESIGN STUDIES: Site and floor plans, elevations, sections, and other items as required by the Project Manager and shall show the scale and relationship of the parts and the design concept of the whole. 1.31 SUBSTANTIAL COMPLETION: That date on which, as certified in writing by DP, the Work, or a portion thereof designated by the Construction Project Manager or Project Manager is at a level of completion in substantial compliance with the Contract Documents and has satisfied all requirements in the Project Specifications and other Contract Documents such that all conditions of permits and authorized authorities having jurisdiction have been satisfied and Owner or Owner’s designee can enjoy beneficial use and occupy and can use or operate in all respects for its intended purposes. 1.32 SUB-CONSULTANT: A person or organization of properly registered professional architects and/or engineers, who has entered into an agreement with DP to furnish professional services for a project or task, described under Basic Services or a task described under Additional Services or Reimbursable Costs. 1.33 WORK: The entire construction or various separately identifiable parts thereof required to be furnished under the Contract Documents. Work is the result of performing services, furnishing labor and furnishing incorporating materials and equipment into the construction, all as required by the Contract Documents. Durango Juvenile Courts Demolition Page | 7 CMR Professional Services Contract Serial # 260056-ROQ ARTICLE 2: DP SERVICES AND RESPONSIBILITIES 2.1 SUSTAINABILITY: 2.1.1 The Project shall comply with designated Maricopa County goals for sustainability. The project shall incorporate “green” building practices to achieve the highest efficiency standards reasonable to reduce operating costs via energy savings; improve worker productivity; and reduce potential liability resulting from indoor air quality problems. 2.2 BASIC SERVICES: DP agrees to provide complete professional A/E Services set forth below, including code-compliant architectural, civil, structural, mechanical, electrical engineering, plumbing, fire protection systems, landscape design and other engineering services normally required for a project of this specific type, hereinafter collectively called “Basic Services.” 2.2.1 Programming and Schematic Design: 2.2.1.1 DP shall confer with the Director or Director’s designee to establish the Program or program verification, consisting of a detailed listing of all functions and spaces together with the square footage of each assignable space, gross square footage, and a description of the relationships between and among the principal programmatic elements. Based upon Owner’s input, DP shall establish a design concept which shall incorporate environmental and visual elements. Design of the Project is to include wastewater, storm water, drainage, parking, lighting and any other design element necessary to complete the facility. 2.2.1.2 DP shall prepare and present, for approval by Owner, a Design Concept and Schematics Report, comprising the Schematic Design Studies, including identification of any special requirements affecting the Project. All presentations shall be made to FMD and approved prior to proceeding with further design. Written approval from FMD is required prior to the release of any information to the end user or stakeholders. 2.2.1.2.1 Schematic Design Documents shall consist of but not be limited to site and floor elevation plans, elevations, sections, etc. as required by the Project Manager and the scale of the relationship of the parts and design concept of the Project and shall also include a review of all Building Codes and applicable laws to determine compliance, scheduling and construction budget information. 2.2.1.2.2 Schematic Design Studies shall consist of but not be limited to site and floor plans, elevations, sections, etc. as required by the Project Manager and shall show the scale and relationship of the parts and the design concept of the whole. 2.2.1.2.3 DP shall submit hard copies and one (1) electronic media set (in PDF format, but generated from AutoCAD files complying with guidelines prescribed in Exhibit ‘C’) on disk of all documents required, without additional charge, for approval by Owner. DP shall not proceed with the Design Development Phase until the documents have been approved by Owner and a written Authorization to Proceed with the next phase of the design has been issued by the Director or Director’s designee. Durango Juvenile Courts Demolition Page | 8 CMR Professional Services Contract Serial # 260056-ROQ 2.2.1.2.4 DP shall prepare an energy efficiency study necessary to comply with all applicable mechanical and electrical codes, requirements and standards for Owner. 2.2.2 Selection and Award of Construction Management at Risk Contractor: 2.2.2.1 Solicitation of CMR: At such other time as Owner may elect, DP shall participate in the evaluation and selection of a qualified construction management firm to serve as the CMR. 2.2.2.2 Issuance of Addenda and Selection: 2.2.2.2.1 At the request of the Project Manager, DP shall participate in any selection committee meetings and meet with Owner’s staff and Project Manager to assist in evaluating Responses to the RFQ and qualifications. 2.2.2.2.2 At the direction of the Project Manager, DP shall attend all presentations or interviews with CMR candidates. 2.2.3 Design Development: 2.2.3.1 Working from the previously approved Schematic Design Documents, DP, with requisite input and assistance from the CMR, shall prepare and present, for review and approval by Owner, the Design Development Documents, comprising the drawings, outline specifications and other documents necessary to delineate and describe the size and character of the entire Project including architectural, civil, structural, mechanical, plumbing, fire alarm and fire protection, and electric systems, landscaping, construction materials and finish materials. DP shall fully involve the CMR during this phase to allow the CMR to prepare and deliver ongoing constructability and bidding reviews, value engineering proposals, and construction cost estimates. DP shall be required to make at least one (1) presentation of the Design Development Documents to Owner. As and if requested by the Project Manager, Sub-consultants engaged by DP shall attend this presentation to explain the design concept of their respective systems. All presentations shall be made to FMD and approved prior proceeding with further design. Written approval from FMD is required prior to the release of any information to the end user or stakeholders. 2.2.3.2 If the CMR’s Design Development Construction Estimate exceeds the Owner’s Construction Budget the DP shall provide a list of appropriate cost or scope reduction recommendations at no cost to Owner. 2.2.3.3 DP shall submit hard copies and, one (1) electronic media set (in PDF format, but generated from AutoCAD files complying with guidelines prescribed in Exhibit ‘C’) on disk of all documents required under this Phase, without additional charge, for approval by Owner, and DP shall not proceed with the next Phase of the design until Owner has approved the documents and a written authorization for the next Phase has been issued. 2.2.3.4 If requested by the Project Manager, DP shall prepare Finish Material Sample boards as necessary to review the color selections of all finish materials with the Project Manager and DP will furnish the approved colors to the CMR within a Durango Juvenile Courts Demolition Page | 9 CMR Professional Services Contract Serial # 260056-ROQ timeframe acceptable to the Project Manager. This shall be done in a timely manner so as to not delay Project progress. 2.2.4 Construction Documents Development: Working from the approved Design Development Documents, DP with assistance from the CMR shall prepare for approval by Owner 50% Construction Documents, setting forth in detail all requirements necessary for the permitting, bidding and construction of the Project. DP shall fully involve the CMR during this design phase to perform as needed or authorized, ongoing bidding and constructability reviews, value engineering proposals, estimate of final construction cost and a, preliminary baseline construction schedule. DP is responsible for full compliance of the design and the Construction Documents with all applicable codes of building officials or entities having jurisdiction and shall opine to Owner that the Project can be constructed within the construction budget established by Owner. 2.2.4.1 50% Construction Documents Submittal: DP shall complete and submit a 50% Construction Document set and Specifications to the CMR for review. Upon review and acceptance of the CMR that the drawings and specifications represent a 50% Construction Document set, the DP shall submit the 50% Construction Documents and Specifications, with the CMR comments incorporated to the Owner for approval. The submission shall include: 2.2.4.1.1 Hard copies and one (1) electronic media set of all drawings (AutoCAD complying with guidelines prescribed in Exhibit ‘C’ with matching PDF) and specifications (complying with designated products/materials/systems prescribed by the Owner). 2.2.4.1.2 A complete index of every drawing sheet, to become part of the Construction Documents. 2.2.4.1.3 DP shall, in the preparation of the Project Specifications, use the most recent edition of CSI Standards promulgated by the Construction Specifications Institute and these technical specifications shall not be merely outline specifications as were submitted during the Design Development Phase. Specification content shall be coordinated in conjunction with prescribed products/materials/systems of the Owner, as identified during Design Development. The specifications content shall be coordinated and comply with the Owner provided preferred equipment product and system specifications. 2.2.4.1.4 An Authorization to Proceed with the completion of 100% Construction Documents will not be issued by the Director or Director’s designee if CMR latest Construction Estimate exceeds the Construction Budget, unless Owner increases the Construction Budget or the CMR, DP and Owner mutually agree on methods of cost reduction sufficient to enable construction of the Project within the Construction Budget. 2.2.4.2 DP shall not proceed with further design until approval from the Director or Director’s designee is received. DP, with input from the CMR, shall make all required changes to the documents and resolve all questions prior to proceeding with the design. Durango Juvenile Courts Demolition Page | 10 CMR Professional Services Contract Serial # 260056-ROQ 2.2.4.3 100% Construction Documents Submittal: 2.2.4.3.1 Upon completion of the 100% Construction Documents, DP shall submit the 100% Construction Document set to the CMR for review. Upon review and acceptance of the CMR that the drawings and specifications represent a complete 100% Construction Document set, the DP shall submit the 100% Construction Documents and Specifications, with the CMR comments incorporated to the Owner for approval. Submission shall include: 2.2.4.3.1.1 Hard copies and one (1) electronic media set (AutoCAD complying with guidelines prescribed in Exhibit ‘C’ with matching PDF) on disk. Include all drawings, specifications, reports, programs, etc. All recommendations of Owner and CMR from this review shall be incorporated by DP into the Construction Documents prior to submission of the 100% Construction Documents for permit. Once approved by Owner, the 100% Construction Documents shall become the Approved 100% Construction Documents and shall not be altered, modified, or revised without Owner’s prior written consent. Construction Documents must be reviewed by the CMR and confirmed by its written that the entire Project can be constructed within the construction budget set by Owner. 2.2.4.3.2 Following approval by the Owner the DP shall be responsible for preparing and submitting the completed construction documents for approval by governmental authorities having jurisdiction over the Project and in obtaining certifications of “permit approval” by such reviewing authorities. Any revisions required by permitting agencies comments shall be incorporated into the Construction Documents. Upon receiving permitted construction documents the DP shall make the permit and approved documents available to Owner for reproduction of additional copies as may be required for bid solicitation and/or construction purposes. 2.2.4.3.3 DP expressly warrants that the Drawings and Project Specifications and Construction Documents for the Project have been prepared by DP and the Sub-consultants by exercising their professional skills with care and diligence and in a reasonable non-negligent manner consistent with the standard of care of like professionals in Maricopa County, Arizona. 2.2.4.3.4 DP shall be responsible for the cost of any additional design necessary to correct errors or omissions caused by or attributable to DP that fall outside the applicable standard of care. 2.2.4.4 CMR Contract: 2.2.4.4.1 During the timeframe of Owner’s Agreement with the CMR for Pre- Construction Services, DP shall, as requested by the Project Manager or Construction Project Manager, provide assistance to Owner in connection with Owner’s acceptance of CMR’s Guaranteed Maximum Price (“GMP”) proposal, including but not limited to determining and memorializing the criteria and factors on which the GMP proposal is based; 2.2.4.4.2 In the event Owner does not accept the CMR’s last proposal of a GMP, after value engineering and other steps to arrive at a GMP have been Durango Juvenile Courts Demolition Page | 11 CMR Professional Services Contract Serial # 260056-ROQ taken, Owner may, in accordance with A.R.S. § 34-104(E), direct DP at no added cost to Owner to revise the Project scope or quality or both as approved by Owner, and then assist Owner in soliciting bids from qualified, licensed general contractors in accordance with A.R.S. § 34- 201 in its then existing statutory form. 2.2.4.4.3 During the timeframe of Owner’s agreement with CMR for Construction Phase Services, DP acknowledges its responsibility and duties called out and set forth in Owner’s agreement with CMR (incorporated herein by this reference) in addition to the responsibilities set forth herein. 2.2.5 Phase V - Observation and Administration of the Construction Contract: 2.2.5.1 The Construction Phase of the Project will commence with the award of the Construction Contract and will end when final payment is made by Owner. During this period, DP shall observe and provide administration of the Construction Contract as set forth in the Construction Contract entered and other Contract Documents and as provided herein. 2.2.5.2 During the Construction Phase, DP shall advise and consult with Owner and shall have authority to act on behalf of Owner only as set forth herein and to the extent provided in the Construction Contract between Owner and CMR, incorporated by this reference. 2.2.5.3 DP shall be responsible for and provide all special inspections required for the project. 2.2.5.4 DP shall visit the site at least weekly and at such times as requested by the Project Manager, and at all key construction events. DP’s Sub-consultants shall visit the site weekly, to ascertain the progress of the Project and to determine in general if the Work is proceeding in accordance with the Contract Documents. On the basis of on-site observations, DP shall endeavor to guard Owner against defects and deficiencies in the Work. DP shall notify Owner of any non-compliant work discovered during the site visits. DP will not be required to make extensive inspections or provide continuous daily on-site inspections to check the quality or quantity of the Work unless otherwise set forth in this Agreement. DP is not responsible for the CMR’s construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the performance of the Work, nor will DP be held responsible for the CMR's or Subcontractors', or any of their agents’ or employees’, failure to perform the Work in compliance with the Contract Documents. 2.2.5.5 DP shall furnish Owner with a written report of all observations of the Work made by DP during each visit made to the Project. DP shall keep a log of all non- compliant work and shall keep track of all such issues to resolution. DP shall also state in the log the final resolution action and the date correction was made. DP shall also note the general status and progress of the Work, and submit same in a timely manner or more often if requested by the Construction Project Manager or Project Manager. DP shall ascertain that the CMR is making timely, accurate, and complete notations on its As-Built Drawings as the Work proceeds by reviewing the CMR As-Built Drawings on a monthly basis and providing written confirmation to the Owner, prior to the CMR application for payment. Durango Juvenile Courts Demolition Page | 12 CMR Professional Services Contract Serial # 260056-ROQ 2.2.5.6 Based on observations at the site and consultation with the Construction Project Manager, DP shall assist in determining the amount due the CMR in progress payments and shall recommend approval or disapproval of amounts applied for by executing AIA Form G702. This recommendation shall constitute a representation by DP to Owner that, to the best of DP’s knowledge, information and belief, the Work has progressed to the point indicated in the pay application and the quality and quantity of the Work is in compliance with the Contract Documents subject to: 2.2.5.6.1 an evaluation of the Work for compliance with the Contract Documents upon Substantial Completion, 2.2.5.6.2 the results of any subsequent tests required by the Contract Documents, 2.2.5.6.3 minor deviations from the Contract Documents correctable prior to Project completion, and 2.2.5.6.4 any specific qualifications stated in the Payment Application. 2.2.5.7 If Owner elects to withhold, in whole or in part, any progress payment to CMR, DP may be required to assist Owner in preparation of specific written findings about the deficiency in the Work and in calculating the reasonable cost necessary to correct the deficient work and complete same. 2.2.5.8 DP shall be the initial interpreter of the requirements of the Contract Documents and the initial judge of performance thereunder. DP shall render written interpretations necessary for the proper execution or progress of the Work with reasonable promptness on written request of either Owner or the CMR. If revisions to the Drawings and/or Project Specifications become necessary, DP shall make a written proposal as to the cost unless the need for revision is attributable to DP. 2.2.5.9 DP shall render written recommendations, within a reasonable time, on all claims, disputes or other matters in question between Owner and the CMR relating to the execution or progress of the Work or the interpretation of the Contract Documents. The Director or Director’s designee shall make final decisions regarding interpretations or disputes related to or arising therefrom. 2.2.5.10 Such interpretations and recommendations of DP shall be consistent with the intent of and reasonably inferable from, the Contract Documents and shall be in written form with graphic supplementation if helpful. In the capacity of interpreter, DP shall endeavor to secure faithful performance of the Contract by both Owner and the CMR, and shall not show partiality to either. 2.2.5.11 DP shall have authority to recommend rejection of Work which does not conform to the Contract Documents. Whenever, in DP’s reasonable opinion, it is necessary or advisable to insure compliance of the work with the Contract Documents, DP will recommend special inspection or testing of any Work deemed to be not in compliance with the Contract Documents, whether or not such Work has been fabricated and delivered to the Project, or installed and completed but such inspection or testing may only be authorized by Owner. DP shall provide such normal mechanical, plumbing, electrical, structural, landscape or other related inspection expertise and services as is necessary from time to time to determine compliance with the Construction Contract. Durango Juvenile Courts Demolition Page | 13 CMR Professional Services Contract Serial # 260056-ROQ 2.2.5.12 DP shall review and return all submittals, shop drawings, samples, deferred submittals and other submissions of the CMR for conformance with the design concept of the Project and for compliance with the Contract Documents within fourteen (14) days from receipt. 2.2.5.13 DP shall respond to all Requests for Information or Clarification from the CMR or Owner within seven (7) days from receipt and shall do so with graphic supplementation when requested. All reviews are to be conducted in a timely manner so as to not delay progress of the construction. Changes to or substitution of Construction Documents shall not be authorized without the written concurrence of Owner. 2.2.5.14 DP shall issue a Proposal Request (PR) to the Owner for each revision to the contract but only after consulting with and with the agreement of the Owner. The DP shall review and make recommendations to the Owner on all Change Order Requests submitted by the CMR. DP shall assist the Owner in review of all Contractor requests for time extensions and make recommendations to the Owner. DP may issue supplemental instruction or interpretation of the Contract Documents or order minor changes in the Work so long as they involve no change in Contract Time or Contract Price. 2.2.5.15 Upon receipt of CMR’s request for Substantial Completion with CMR’s Punch List attached, DP shall, prior to occupancy by Owner, confirm and recommend to the Owner that the project is substantially complete in accordance with the Contract requirements. Upon Owner written concurrence, DP shall develop a complete, final punch list of any remaining defects and discrepancies in the Work. The punch list shall be created with the Owner’s involvement and include Owner’s comments. The complete punch list shall be attached to the DP Certificate of Substantial Completion. DP shall be responsible for all punch list back-checks and confirmation of full and satisfactory performance before DP recommends to the Owner that a Final Acceptance Final Payment be made to the CMR. 2.2.5.16 For Substantial Completion, DP shall obtain from the CMR all guarantees, Operation and Maintenance manuals for equipment, and such other documents and certificates as may be required by applicable codes, laws, Project Specifications and the Owner, review them for compliance with Contract requirements, and deliver them to Owner if in compliance. 2.2.5.17 DP shall provide assistance in obtaining the CMR's compliance with the Contract Documents relative to 1) initial instruction of Owner's personnel in the operation and maintenance of any equipment or system, 2) initial start-up and testing, adjusting and balancing of equipment and systems, and 4) final clean-up of the Project. 2.2.5.18 During all Phases of the Project, DP shall notify Owner in writing of all conflicts between the Plans and Specifications and/or Contract Documents and any laws, codes, ordinances, rules, regulations and restrictions that come to the attention of DP or should have reasonably come to DP’s attention with the exercise of due care. 2.2.5.19 DP shall prepare and submit to Owner weekly and/or monthly reports, as required by the Owner, throughout the Construction Phase of the Project. The reports shall provide the current status of activities of DP, CMR, subcontractors, Consultants, Sub-consultants, and others whose activities affect the Project. The reports shall Durango Juvenile Courts Demolition Page | 14 CMR Professional Services Contract Serial # 260056-ROQ also include a copy of the log on all non-compliant work and all resolution information. 2.2.5.20 For both Basic and Additional Services, DP shall prepare Record Drawings (reference Exhibit C) based on the CMR’s As-Builts Drawings and provide to Owner one (1) printed hard-copy full-size set of Record Drawings and one (1) corresponding set of digital media containing the complete drawings for the Project in AutoCAD and in matching PDF. The image on screen shall include all title blocks, borders, details, and all notes that are visible on the full-sized originals. Each sheet provided shall indicate it is a Record Drawing. DP shall also prepare a simplified version of all approved Egress Plans in the Drawings used in the permit approval process and provide such to Owner upon request for purposes of installation of evacuation / exiting diagrams in the completed Project. DP acknowledges that the quantity thereof and extent of depicted information may be determined by the Authority Having Jurisdiction over the Project. 2.2.5.21 In connection with Final Acceptance and final payment, DP shall inspect the Work and determine: 2.2.5.21.1 Whether the CMR has satisfactorily completed or corrected all items on the punch list attached to the Request for Substantial Completion; 2.2.5.21.2 Whether the work complies with i) the Contract Documents, and ii) all applicable laws, building codes or authorities having jurisdiction; 2.2.5.21.3 Whether required inspections by building officials have been completed; and 2.2.5.21.4 In consultation with Owner, whether the Work is finally complete. If the Work is not finally complete, the process as set forth above shall be repeated until such time as the Work is finally completed in compliance with the Contract Documents. DP shall also incorporate As-Built Drawings as defined in Article 1, above, into the Record Drawings prior to Final Acceptance. 2.2.5.22 DP shall assist Owner in conducting a post-construction inspection at least thirty (30) days prior to the expiration of the one-year post-construction warranty period to identify deficiencies and warranty-related problems. DP shall note, prepare and submit to Owner a written report on all faults, deficiencies or warranty problems observed. 2.2.6 Maximum Cost Limit: If at any time during the design phase the latest Construction Estimate submitted by CMR exceeds Owner’s Maximum Cost Limit, DP shall, with the CMR’s assistance, at no additional cost to Owner, revise the Design Documents to bring the Project costs within the Maximum Cost Limit. Such revised Design Documents must be completed by DP within the time period designated in writing by the Owner. The Maximum Cost Limit for the Work is not to be changed unless amended by Maricopa County. 2.3 ADDITIONAL SERVICES: Durango Juvenile Courts Demolition Page | 15 CMR Professional Services Contract Serial # 260056-ROQ 2.3.1 The Additional Services listed below are beyond the scope of the Basic Services as same are defined in this Agreement, and if authorized in advance by an appropriate written directive from the Director or Director’s designee, will be compensated for by lump sum, not-to-exceed agreed to by Owner under Section 6.2. 2.3.1.1 Special analyses of Owner’s needs, and special detailed programming requirements for the Project authorized by Director or Director’s designee. 2.3.1.2 Financial feasibility, life cycle costing or other special studies. 2.3.1.3 If not provided for in Basic Services or Owner’s own program, planning surveys, site evaluations, geo-technical surveys or comparative studies of prospective sites as authorized by Director or Director’s designee. 2.3.1.4 Design services relative to future facilities, systems and equipment which are not intended to be constructed as part of the Project. 2.3.1.5 Providing services to investigate existing conditions of facilities or to make measured drawings thereof, after DP has expended an amount of time deemed to be the normal requirement for renovation and alteration projects. 2.3.1.6 Detailed Estimates of Construction Cost consisting of quantity surveys itemizing all material, equipment and labor required for the Project. 2.3.1.7 Excluding all equipment, materials, supplies and related items included in the Construction Contract, design services required for or in connection with the selection of furniture or furnishings or fixtures. 2.3.1.8 Investigation and making detailed appraisals and valuations of existing facilities, and surveys or inventories in connection with construction performed by Owner. 2.3.1.9 Any additional special professional services (other than the customary architectural, civil, structural, geo-technical, mechanical, plumbing, fire alarm, fire protection, security and electrical engineering and landscape design services) as may be required for the Project, including but not limited to: acoustical, food service, theatrical, electronic, telephone/data, artists, and sculptors. 2.3.1.10 The services of one or more full-time Project Field Representatives during construction as deemed appropriate and as approved and authorized, in advance by the Owner. 2.3.1.11 Extended assistance beyond that provided under Basic Services for the initial start-up, testing, adjusting and balancing of any equipment or system; extended training of Owner's personnel in operation and maintenance of equipment and systems, and consultation during such training; and preparation of operating and maintenance manuals, other than those provided by the CMR, subcontractor, or equipment manufacturer. 2.3.1.12 A/E Services concerning replacement of any Work damaged or built in non- compliance with the Contract Documents, providing the cause for such non- compliance is determined by Owner to be other than by fault of DP or beyond control of DP. 2.3.1.13 Making major revisions changing the scope of the Project, to Drawings and Project Specifications, when such revisions are inconsistent with written Durango Juvenile Courts Demolition Page | 16 CMR Professional Services Contract Serial # 260056-ROQ approvals or instructions previously given by Owner and are due to causes beyond the control of DP. (Major revisions are defined as those changing the scope and arrangement of spaces and/or scheme and/or any significant portion thereof.) 2.3.1.14 Preparing to serve or serving as an expert witness in connection with any public hearing, arbitration or legal proceeding, providing, however, that DP cannot testify or give evidence against Owner in any matters during the course of providing services under this Agreement. 2.3.1.15 Providing services after Final Completion and final payment has been made to the CMR, other than those called for in this Agreement. 2.3.1.16 Additional Observation and Administration, in the event the time period of Observation of DP under Basic Services exceeds the Contract Time for the Work by more than 15%, and only if the delay in completion of the Work is in the opinion of Owner beyond the control of DP and the Additional Observations and Administration is approved by the Owner. 2.3.1.17 Renderings, sketches, models or photographs to further convey the proposed design concept to the Owner. 2.3.1.18 Any other services not otherwise included in this Agreement. 2.3.2 Failure to timely perform any part of requested Additional Services identified in this Agreement shall be a breach of the Agreement and Owner may, in its sole discretion, without liability, contract with others to perform those services and the cost for these services and others incurred by Owner shall be borne by DP. 2.3.3 DP shall not perform any services not covered by this Agreement and any such services performed by DP without prior written authorization shall be at DP’s own risk and cost. DP hereby agrees that in the absence of prior written authorization, DP’s work will be at its own risk, cost, and expense and DP agrees that without such prior written authorization, DP will make no claim for compensation for unauthorized services. 2.4 REIMBURSABLE COSTS: Reimbursable Costs are those items that are authorized by Owner in writing for payment in addition to the Basic and Additional Services and consist of actual expenditures (as verified by invoices) made by DP and its Sub-consultants in the interest of the progress of Work and in accordance with the County’s Contractor Travel Policy for the following purposes: 2.4.1 Identifiable transportation expenses in connection with the Project to locations outside the Maricopa County area or from locations outside the Maricopa County area will not be reimbursed unless specifically pre-authorized in writing by the Owner. 2.4.2 Meals and lodging expenses will not be reimbursed for temporarily relocating DP’s employees from one of DP’s offices to another office if the employee is relocated for more than ten (10) consecutive working days. 2.4.3 Identifiable communication expenses approved by the Owner, long distance telephone, courier and express mail between DP’s various permanent offices. DP’s field office at the Project is not considered a permanent office. Durango Juvenile Courts Demolition Page | 17 CMR Professional Services Contract Serial # 260056-ROQ 2.4.4 Cost of printing, reproduction or photography which is required by or of DP to deliver services set forth in this Agreement. 2.4.5 Identifiable testing costs approved by Owner. 2.4.6 All Permit fees paid to regulatory agencies for approvals directly attributable to the Project. 2.4.7 Reimbursable Sub-consultant expenses are limited to the items described above and on the same basis. 2.4.8 All Reimbursable Costs will be approved by Owner only if prior written approval was received and pursuant to verified invoices, receipts or other acceptable proof of expenditure provided by DP. ARTICLE 3: SUBCONSULTANTS 3.1 REGISTRATION OF SUBCONSULTANTS: All contracts entered into by DP with Sub-consultants or Special Sub-consultants engaged to provide professional services on the Project must be with registrants with the Arizona Board of Technical Registration. All such contracts with Sub-consultants must incorporate all terms and provisions of this Agreement (including those re: Alternative Dispute Resolution) as they relate to the duties and responsibilities of DP on the Project. 3.2 SUB-CONSULTANTS' RELATIONSHIP: 3.2.1 All services provided by the Sub-consultants shall be pursuant to appropriate written agreements between DP and the Sub-consultants, which shall contain provisions that preserve and protect the rights of Owner and DP under this Agreement. 3.2.2 Nothing contained in this Agreement shall create any contractual or business relationship between Owner and the Sub-consultants. DP acknowledges the Sub-consultants are to perform those professional services under the direction, control and supervision of DP as the prime Project professional. 3.2.3 DP proposes to utilize the following Sub-consultants: FIRM NAME CONSULTING SERVICE Broderick Structural Pearson Mechanical, Plumbing, Elect. CSQ Estimator SAM Companies Surveying ____________________ ____ _______________________ 3.2.4 DP shall not change or replace any Sub-consultant without first obtaining prior written approval from the Director or Director’s designee in response to a written request stating the reasons for any proposed substitution. Such approval shall not be unreasonably delayed by the Director or Director’s designee and, if the request is denied, an explanation will be provided. Durango Juvenile Courts Demolition Page | 18 CMR Professional Services Contract Serial # 260056-ROQ ARTICLE 4: OWNER’S RESPONSIBILITIES 4.1 INFORMATION FURNISHED: If available, the Owner, at its expense shall furnish DP with the following information: 4.1.1 Surveys of building sites, giving boundary dimensions, locations of existing structures and/or trees, the grades and lines of street, pavement, and adjoining properties; the rights, restrictions, easements, boundaries, and topographic data of a building site, and such information as it has relative to sewer, water, gas and electrical services. Information contained in such provided documents will be provided by Owner with no express guarantee for their accuracy or completeness or lack thereof. DP agrees to field-verify the accuracy or completeness of any information provided by the Owner as deemed necessary by the DP to provide Contract Documents meeting expectations set forth under Articles 2 and 3 herein. 4.1.2 If available, soil borings or test pits information, mechanical, structural, or other tests when deemed necessary by Owner. 4.1.3 If available, drawings representing as-built conditions at the time of original construction will be furnished to DP; however, they are not warranted to represent conditions as of the date of this Agreement. DP must perform field investigations as deemed necessary by the DP and Sub-consultants in order to obtain sufficient information to perform services complying with Articles 2 and 3 herein. ARTICLE 5: PROJECT MANAGEMENT AND REVIEW PROCEDURES 5.1 PROJECT MANAGEMENT: 5.1.1 The Director or Director’s designee shall act on behalf of Owner in all matters pertaining to this Agreement, and with the approval of the County Manager, the Director or Director’s designee shall issue all Authorizations to Proceed to DP. The Director or Director’s designee shall approve all invoices for payment to DP upon recommendation of the Project Manager or Construction Project Manager. 5.1.2 Maricopa County Facilities Management Department is the Owner. The Director shall designate a Project Manager and/or a Construction Project Manager to have general responsibility for management of the Project through all Phases of this Agreement. The Project Manager and Construction Project Manager shall have authority to issue Authorizations to Proceed to DP and meet with DP at periodic intervals throughout the preparation of the Contract Documents to assess the progress of the design and professional services and the Work in accordance with approved schedules. The Project Manager and Construction Project Manager shall also examine documents submitted by DP, including invoices, and shall promptly render decisions and/or recommendations pertaining thereto, to avoid unreasonable delay in the progress of DP's work. 5.1.3 If Owner observes or otherwise becomes aware of any faulty or defective work in the Project, or other nonconformance with the Contract Documents during the Construction Phase, Owner shall give prompt notice thereof to DP. 5.2 REVIEW PROCEDURES: Durango Juvenile Courts Demolition Page | 19 CMR Professional Services Contract Serial # 260056-ROQ The following procedures shall be followed for review of all submittals required by Article 2 of this Agreement: 5.2.1 DP shall submit programming when called for herein, Schematic Studies and Schematic Documents, Design Development Documents and Construction Documents for review by Owner and CMR in accordance with the Project Design Schedule. 5.2.2 Owner and CMR will be required to provide all review comments to DP within thirty (30) calendar days from receipt of the submittal. 5.2.3 DP shall respond to and incorporate review comments transmitted by Owner and CMR. Any budgetary overruns or discrepancies shall be resolved by design and engineering modifications to match or get below the Construction Budget established by the Owner. 5.2.4 Unless otherwise agreed to in writing, DP shall respond in writing within seven (7) calendar days of receipt of the review comments. Owner Project Manager or Construction Project Manager will log, transmit and facilitate the exchange of review comments. DP shall also maintain a similar log and make it available to Owner at all times. 5.2.5 Replies to DP Responses: Owner, Project Manager, Construction Project Manager or CMR will reply within fourteen (14) calendar days to any responses requiring confirmation and will advise DP if any further reconciliation is required. 5.2.6 Resolution of Differences: Owner, Project Manager or Construction Project will schedule a meeting between DP, CMR and Owner, to take place within fourteen (14) calendar days after review comments are issued to DP, in order to resolve all issues between teams. The Owner will arrange additional meetings or conference calls as necessary, in order to expedite resolution and avoid impact to the Project Schedule or the Contract Documents. 5.2.7 Punch List and Back-Check Review: Upon notice from the Contractor that the project is substantially complete, the DP shall develop a punch list with assistance from the Owner, incorporating all comments into one punch list for issuance with the Certificate of Substantial Completion. The DP will be responsible for all back-checks to the punch list. If any comments remain unsatisfied, additional back-checks shall be required from DP until all comments have been satisfied. Any costs associated with DP’s preparation of the back- checks shall be DP’s responsibility 5.2.8 Resolution of all review comments is requisite for completion of any phase of the Design Services. 5.2.9 Any failure of Owner to make a decision within the time limits set forth herein shall not be construed as acquiescence in all or any part of a subsequent DP claim for relief or remedy. ARTICLE 6: BASIS OF COMPENSATION 6.1 FEES FOR PROFESSIONAL SERVICES: Owner agrees to pay DP, and DP agrees to accept as payment for all of the Basic Services rendered pursuant to this Agreement, a Lump Sum, Not-to-Exceed Fee mutually agreed upon of $783,960 as set forth on Exhibit ‘B’, DP’s Proposal, based upon hourly rates and hours, which shall be indicated in DP’s proposal and in Exhibit A. DP Basic Proposal of fees shall indicated positions, hours and rates per hour required for each design phase as follows: Programming/Schematic Design, Design Development, Construction Document, Construction Administration and Post Construction. DP shall Durango Juvenile Courts Demolition Page | 20 CMR Professional Services Contract Serial # 260056-ROQ also include a Design Schedule indicating days required for each phase, including days for Owner review and permitting of the Construction Documents. 6.1.1 Payments to DP on account of the Lump Sum Fee shall be made on the percentage of the services completed and approved. 6.1.2 The Lump Sum fee shall include all costs associated with performing the Basic Services including but not limited to attendance at all meetings with Owner staff, Project Manager, Construction Project Manager, CMR, and Sub-consultants necessary to perform all of the Basic Services. 6.1.3 Owner shall have no obligation or liability to pay any fee, expenditure or cost beyond the Lump Sum Compensation agreed to. Unless specifically authorized in writing in advance as part of the approve scope of work, the COUNTY will not pay for any of the following expenses of the DP or its Sub-consultant: 1. Vehicle mileage to any COUNTY-owned facility located within the State of Arizona, 2. Vehicle mileage for the DP or its sub- consultants to attend project related meetings located within the State of Arizona. 3. Meal costs for employees of DP or its sub-consultants whether or not employees of the COUNTY are in attendance for meetings or other gatherings related to project work for the COUNTY, except where authorized in writing in advance for out-of-state consultants/sub-consultants traveling to Arizona or out of state travel related to the assignment. 6.1.4 Unless specifically authorized in writing, the DP shall use the COUNTY contracted printing vendor for all reproduction work if copies are required by the COUNTY in addition to the review document sets required elsewhere in this Agreement. 6.2 ADDITIONAL SERVICES/REIMBURSABLES FEE: DP may be authorized to perform Additional Services described under Section 2.3 and Reimbursable Costs described in 2.4. The proposal for such services will be a negotiated Lump Sum, Not-to-Exceed Fee (negotiated by reference to the hours and hourly rates): 6.2.1 Hourly rates shall be as defined pursuant to Exhibit A. 6.2.2 The following principals may be employed on the Project: _Ted W. Schmidt, PE _____ __Project Manager_____ __ _Michael S. Lewis, AIA____ _Justice Team Leader______ _Liam D. Larkin, AIA_______ _Civil Buildings Market Leader _____________ _____ _________ __ _______ 6.2.3 Personnel directly engaged on a Project by DP may include architects, engineers, designers, job captains, draftsmen, specification writers, field accountants and manufacturer representatives engaged in consultation, research and design, production of drawings, specifications and related documents construction inspection and other services pertinent to a project during all phases therein. 6.2.4 Any authorized reimbursable services fee shall not include charges for office rent or overhead expenses of any kind, including local telephone and utility charges, office and drafting supplies, depreciation of equipment, professional dues, internet services, subscriptions, etc., reproduction of drawings and specifications, mailing, stenographic, Durango Juvenile Courts Demolition Page | 21 CMR Professional Services Contract Serial # 260056-ROQ clerical, or other employees time or travel and subsistence not directly related to a project. For all reimbursable services Owner will pay DP the direct cost of the service without a multiplier. Authorized reproductions and duplicate BIM models in excess of sets required at each phase of the work will be a Reimbursable Service. 6.2.5 Owner upon recommendation of the Director or Director’s Designee will reimburse DP for authorized Reimbursable Services as verified by appropriate bills, invoices or statements, pursuant to Article 7.2. 6.3 Absent an Amendment to the Agreement, the aggregate total of Reimbursable Costs under Section 2.4 shall not exceed $___0___, without the prior written approval of the Director or Director’s designee. In the event that sum is exceeded, Owner shall have no liability or responsibility for paying any such excess which will be DP’s own cost and expense. ARTICLE 7: PAYMENTS TO DP 7.1 PAYMENT FOR BASIC SERVICES: Payments for Basic Services will be made monthly in proportion to the professional services performed during each Phase of DP Services. 7.2 PAYMENT FOR ADDITIONAL/REIMBURSABLE SERVICES: 7.2.1 Payment for Additional Services may be requested monthly in proportion to the services performed. When such services are authorized as an hourly rate, DP shall submit for approval by the Director or Director’s designee, a duly certified invoice, giving names, classification, salary rate per hour, hours worked and total charge for all personnel directly engaged on a project or task. To the sum thus obtained, any authorized Reimbursable Services Cost may be added. DP shall attach to the invoice all supporting data for payments made to the Sub-consultants engaged on the Project or task. 7.2.2 In addition to the invoice, DP shall, for Hourly Rate authorizations, submit a progress report giving the percentage of completion of the Project development and the total estimated fee to completion. 7.3 DEDUCTIONS: No deductions shall be made from the DP’s compensation on account of liquidated damages assessed against CMR or other sums withheld from payments to CMR. ARTICLE 8: INDEMNIFICATION AND INSURANCE 8.1 INDEMNIFICATION: 8.1.1 DP’s Duty to Indemnify and Defend. To the fullest extent permitted by law, the DP shall defend, indemnity and hold harmless the Owner, its agents, representatives, officers, directors, officials, and employees from and against all claims, damages losses, and expenses, including but not limited to attorney fees, court costs, expert witness fees, and the cost of appellate proceedings, relating to, arising out of, or alleged to have resulted from the negligent, reckless, or intentionally wrongful acts, errors, omissions or mistakes of the DP, its agents, representatives, employees, or Subcontractors relating to the performance of this Contract. DP’s duty to defend, indemnify and hold harmless the Owner, its agents, representatives, officers, directors, officials, and employees shall arise Durango Juvenile Courts Demolition Page | 22 CMR Professional Services Contract Serial # 260056-ROQ in connection with any claim, damage loss or expense that is attributable to bodily injury, sickness, disease, death or injury to, impairment, or destruction of property, including loss of use resulting therefrom, caused by the referenced acts, errors, omissions or mistakes in the performance of this Contract, including those made by any person for whose acts, errors, omissions or mistakes, the DP may be legally liable. 8.1.2 The amount and type of insurance coverage requirements set forth below will in no way be construed as limiting the scope of the indemnity 8.2 INSURANCE REQUIREMENTS: DP, at DP’s own expense, shall purchase and maintain the herein stipulated minimum insurance from a company or companies duly licensed by the State of Arizona and possessing a current A.M. Best, Inc., rating of B++. In lieu of State of Arizona licensing, the stipulated insurance may be purchased from a company or companies, which are authorized to do business in the State of Arizona, provided that said insurance companies meet the approval of Owner. The format of any insurance policies and related forms must be acceptable to Owner. 8.2.1 All insurance required herein shall be maintained in full force and effect until all work or service required to be performed under the terms of the Agreement is satisfactorily completed and formally accepted. Failure to do so may, at the sole discretion of Owner, constitute a material breach of this Agreement. 8.2.2 DP’s insurance shall be primary insurance as respects Owner, and any insurance or self- insurance maintained by Owner shall not contribute to it. 8.2.3 Any failure to comply with the claim reporting provisions of the insurance policies or any breach of an insurance policy warranty shall not affect Owner’s right to coverage afforded under the insurance policies. 8.2.4 The insurance policies may provide coverage that contains deductibles or self-insured retentions. Such deductible and/or self-insured retentions shall not be applicable with respect to the coverage provided to Owner. DP shall be solely responsible for the deductible and/or self-insured retention and Owner, at its option may require DP to secure payment of such deductibles or self-insured retentions by a surety bond or an irrevocable and unconditional letter of credit. 8.2.5 Owner reserves the right to request and to receive, within ten (10) working days, certified copies of any and all of the herein required insurance policies and/or endorsements. Owner shall not be obligated, however, to review such policies and/or endorsements or to advise DP of any deficiencies in such policies and endorsements, and such receipt shall not relieve DP from, or be deemed a waiver of Owner’s right to insist on strict fulfillment of DP’s obligations under this Agreement. 8.2.6 The insurance policies required by this Agreement, except Workers’ Compensation, and Errors and Omissions, shall name Owner, its agents, representatives, officers, directors, officials and employees as Additional Insureds. 8.2.7 The policies required hereunder, except Worker’s Compensation, and Errors and Omissions, shall contain a waiver of transfer of rights of recovery (subrogation) against Owner, its agents, representatives, officers, directors, officials and employees for any claims arising out of DP’s work or service. 8.3 REQUIRED COVERAGE: DP is required to procure and maintain the following coverage’s: Durango Juvenile Courts Demolition Page | 23 CMR Professional Services Contract Serial # 260056-ROQ 8.3.1 Commercial General Liability. Commercial General Liability insurance and, when necessary, Commercial Umbrella insurance with a limit of not less than $2,000,000 for each occurrence, $2,000,000 Personal/Advertising Injury, $4,000,000 Products/ Completed Operations Aggregate, and $4,000,000 General Aggregate Limit. The policy shall include coverage for bodily injury, broad form property damage, and blanket contractual coverage, and shall not contain any provision that would serve to limit third party action over claims. There shall be no endorsement or modification of the CGL limiting the scope of coverage for liability arising from explosion, collapse, or underground property damage. 8.3.2 Automobile Liability. Commercial/Business Automobile Liability insurance and, if necessary, Commercial Umbrella insurance with a combined single limit for bodily injury and property damage of not less than $2,000,000 each occurrence with respect to any of DP’s owned, hired and non-owed vehicles assigned to or used in performance of DP’s work or services under this Agreement. 8.3.3 Worker’s Compensation: Workers’ Compensation insurance to cover obligations imposed by federal and state statutes having jurisdiction of DP’s employees engaged in the performance of the work or services under this Contract; and Employer’s Liability insurance of not less than $1,000,000 for each accident, $1,000,000 disease for each employee, and $1,000,000 disease policy limit. 8.3.4 Errors and Omissions (Professional Liability) Insurance. Errors and Omissions (Professional Liability) insurance and, if necessary, Commercial Umbrella insurance, which will insure and provide coverage for errors or omissions or professional liability of DP, with limits of no less than $2,000,000 for each claim. 8.4 COVERAGES: Commercial General Liability $2,000,000 Each Occurrence $2,000,000 Personal & Advertising Injury $4,000,000 General Aggregate $4,000,000 Products/Completed Operations Automotive Liability $2,000,000 Each Occurrence Workers’ Compensation $1,000,000 Each Accident $1,000,000 Disease for Each Employee $1,000,000 Disease Policy Limit Errors and Omissions $2,000,000 Each Claim 8.5 CERTIFICATES OF INSURANCE: Prior to commencing work or services under this Agreement, DP shall furnish Owner with Certificates of Insurance in a form acceptable to Owner, or formal endorsements as required by the Contract in the form provided by Owner, issued by DP’s insurer(s), as evidence that policies providing the required coverage’s, conditions and limits required by this Agreement are in full force and effect. Such certificates shall identify this contract number and title. 8.5.1 In the event any insurance policy(ies) required by this contract is(are) written on a “claims made” basis, coverage shall extend for two years past completion and acceptance of DP’s work or services and as evidenced by annual Certificates of Insurance. Durango Juvenile Courts Demolition Page | 24 CMR Professional Services Contract Serial # 260056-ROQ 8.5.2 If a policy does expire during the life of the Agreement, a renewal certificate must be sent to Owner within fifteen (15) calendar days prior to the expiration date. 8.6 CANCELLATION AND EXPIRATION NOTICES: Insurance required herein shall not expire, be cancelled, or materially changed without thirty (30) calendar day’s prior written notice to Owner. ARTICLE 9: PERFORMANCE 9.1 PERFORMANCE AND DELEGATION: 9.1.1 DP services to be performed hereunder shall be performed by DP's own staff, unless otherwise approved in writing by Owner. Said approval shall not be construed as constituting an agreement between Owner and said other person or firm. DP’s services shall be performed in all respects in a manner consistent with that degree of skill and care ordinarily exercised by practicing design professionals performing such services in Maricopa County under the same or similar circumstances and conditions and in a reasonable and non-negligent way. 9.1.2 DP agrees, within fourteen (14) calendar days of receipt of a written request from Owner, to promptly remove and replace any personnel employed or retained by DP, any Sub- consultants or subcontractors or any personnel of any such Sub-consultants or subcontractors engaged by DP, to provide and perform services or work pursuant to the requirements of this Agreement, whom Owner shall request in writing to be removed, which request may be made by Owner with or without cause. 9.2 TIME FOR PERFORMANCE: 9.2.1 DP agrees to start all work hereunder upon receipt of an Authorization to Proceed issued by the Director or Director’s designee and to complete each Phase within the time stipulated in the Authorization to Proceed. Time is of the essence with respect to Performance of this Agreement. 9.2.2 The Project schedule establishes the critical time limit of DP’s services. DP shall not, except for cause beyond the reasonable control of DP, exceed time limits established by this Agreement. Any adjustments in the schedule must be approved in writing by Owner and must be requested in writing by DP within ten (10) days after the occurrence upon which DP’s request for adjustment is based. 9.3 NO WAIVER OF PERFORMANCE: The failure of the Owner to insist, in any one or more instances, on the performance of any of the terms, covenants or conditions of this Agreement or to exercise any of its rights hereunder, shall not be construed as a waiver or relinquishment of such term, covenant, condition or right with respect to further performance. 9.4 Any failure of Owner to make a decision within the time limits set forth herein shall not be construed as acquiescence in all or any part of a subsequent DP claim for relief or remedy. ARTICLE 10: OWNERSHIP OF DOCUMENTS 10.1 OWNERSHIP OF DOCUMENTS: Durango Juvenile Courts Demolition Page | 25 CMR Professional Services Contract Serial # 260056-ROQ 10.1.1 By execution of this Agreement, DP assigns all copyright ownership and other intellectual property interest in the Design Documents and Construction Documents prepared by DP and further agrees to execute and to cause any Sub-consultant to execute any separate assignment agreement necessary to implement such assignment. 10.1.2 The Drawings and Project Specifications as instruments of service are and shall become the property of Owner whether the Project for which they are made is executed or not. DP shall be permitted to retain copies of the Drawings and Project Specifications for information and reference in connection with Owner's use and occupancy of the Project. 10.1.3 Submission or distribution of Contract Documents to meet official regulatory requirements or for other purposes in connection with the Project is not to be construed as publication in derogation of DP's rights. 10.1.4 To extent allowed by law, DP agrees not to divulge, furnish or make available to any third person, firm or organization, without Owner’s prior written consent, or unless incidental to the proper performance of DP’s obligations hereunder, or in the course of judicial or legislative proceedings where such information has been properly subpoenaed, any non- public information concerning the services to be rendered by DP hereunder, and DP shall require all of its employees, agents and Sub-consultants to comply with the provisions of this paragraph. 10.1.5 In the event of future reuse of the Construction Documents by Owner, DP’s name and seal shall be removed and DP shall not be liable to Owner or third parties in their reuse. 10.1.6 DP shall not use, or allow to be used, the Contract Documents, Drawings, Project Specifications and reports or the unique aspects of this Project in any other project without the prior written approval of Owner. DP’s use of standard specifications texts and details are specifically excluded from the provisions of this paragraph. ARTICLE 11: ALTERNATIVE DISPUTE RESOLUTION 11.1 Scope. Notwithstanding anything to the contrary provided elsewhere in the Contract, the alternative dispute resolution (“ADR”) process provided herein shall be the exclusive means for resolution of claims or disputes arising under or related to the Contract, the interpretation thereof or the performance or breach by any party thereto, including but not limited to original claims or disputes asserted as cross claims, counterclaims, third party claims or claims for indemnity or subrogation, in any threatened or ongoing litigation or arbitration with third parties, if such disputes involve parties to contracts containing this ADR provision. No changes can be made to this process without the mutual assent of the County and the claimant. The parties have structured this procedure with the goal of providing for the prompt, efficient and final resolution of all disputes falling within the purview of this ADR process. 11.2 Meeting of Principals. When a claim is made or a dispute (hereafter “dispute”) as described in Paragraph 11.1 arises, senior representatives of the County and the claimant will meet personally within ten (10) business days to discuss the dispute and attempt to resolve it. If, after good faith efforts, resolution is not achieved, the dispute will proceed to mediation. 11.3 Qualifications of Mediator and Arbitrators. Any person selected as mediator or arbitrator, either as single arbitrator as a member or Chair of the arbitration panel, shall be a member of the State Bar of Arizona and have experience in construction law. 11.4 Mediation. If the parties have been unable to resolve the dispute after a meeting of principals, the parties may enter into mediation. The parties shall jointly select a mediator. The parties may Durango Juvenile Courts Demolition Page | 26 CMR Professional Services Contract Serial # 260056-ROQ mutually agree to waive mediation and proceed directly to arbitration. If the mediation process is requested by either party, the mediation period shall be informal and shall not exceed sixty (60) calendar days from the selection of the mediator. During the mediation process either party may terminate mediation on written notice to the other party and the mediator. 11.5 Binding Arbitration Procedure. The following binding arbitration procedure shall serve as the exclusive method to resolve a dispute if mediation is unsuccessful, if mediation has been waived by the parties, or if a party requests arbitration during the mediation process. Except as provided in Section 11.7.5 and 11.7.9, the decision of the arbitrator or arbitrator panel is final and binding on the parties and not subject to further judicial review. 11.5.1 A party requesting binding arbitration shall notify the other party of their demand for arbitration in writing within seven (7) calendar days of (1) the failure of mediation; (2) waiver of mediation; or (3) of the party’s demand to terminate mediation. 11.5.2 If the Architect requests arbitration it shall post a cash bond with the arbitrator in an amount agreed upon by the parties or, in the event of no agreement, the arbitrator shall establish the amount of the cash bond to defray the cost of the arbitration and the proceeds from the bond shall be allocated in accordance with paragraph 11.7.7. The bond must be in the full amount agreed upon or as established by the Arbitrator to pay the potential cost of the full arbitration proceeding. The bond must be posted with and received by the arbitrator within five (5) calendar days after the demand for arbitration. 11.5.3 Disputes involving less than $200,000 shall be heard by one single arbitrator chosen by agreement of the parties. If the parties cannot agree on the single arbitrator, then the parties shall each submit two names to a Judge designated by Maricopa County who shall select the single arbitrator. 11.5.4 For disputes in excess of $200,000, the arbitration panel shall consist of three arbitrators: the Architect’s appointed arbitrator, the CMR's appointed arbitrator and a third arbitrator who shall be selected by the parties' arbitrators and serve as the Chair of the arbitration panel. 11.5.5 The arbitration is to be convened and administered under the Revised Uniform Arbitration Act (“RUAA”) (A.R.S. § 12-3001 et seq.) and the American Arbitration Association Construction Rules shall serve as a guideline for proceedings, thus as a supplement to the RUAA. 11.6 Expedited Hearing. Any party can request the single arbitrator or the Chair of the arbitration panel to set an expedited hearing. If the single arbitrator or the Chair of the arbitration panel determines that the circumstances justify it, the single arbitrator or the Chair of the arbitration panel will arrange for scheduling of the arbitration at the earliest possible date. In any event, the hearing of any dispute not expedited will commence as soon as practical but in no event later than thirty (30) calendar days after notification of request for arbitration having been received. This deadline can be extended only with the consent of all the parties to the dispute, or by decision of the single arbitrator or the Chair of the arbitration panel upon a showing of good cause. 11.7 Procedure. The single arbitrator or the arbitration panel will conduct the hearing in such a manner that will resolve disputes in a prompt, cost efficient manner giving regard to the rights of all parties. Each party shall supply to the single arbitrator or arbitration panel a written pre-hearing statement which shall contain a brief statement of the nature of the claim or defense, a list of witnesses and exhibits, a brief description of the subject matter of the testimony of each witness who will be called to testify, and an estimate as to the length of time that will be required for the arbitration hearing The single arbitrator or the Chair of the arbitration panel shall determine the nature and scope of Durango Juvenile Courts Demolition Page | 27 CMR Professional Services Contract Serial # 260056-ROQ discovery, if any, and the manner of presentation of relevant evidence consistent with deadlines provided herein, and the parties’ objective that disputes be resolved in a prompt and efficient manner. No discovery may be had of any materials or information for which a privilege is recognized by Arizona law. The single arbitrator or the Chair upon proper application shall issue such orders as may be necessary and permissible under law to protect confidential, proprietary or sensitive materials or information from public disclosure or other misuse. Any party may make application to the Maricopa County Superior Court to have a protective order entered as may be appropriate to confirm or enforce such orders of the Chair. 11.7.1 Hearing Days. In order to effectuate parties’ goals, the hearing once commenced, will proceed from working day to working day until concluded, absent a showing of good cause. 11.7.2 Award. The single arbitrator shall within ten (10) calendar days of the conclusion of a hearing issue an award. The arbitration panel shall, within ten (10) calendar days from the conclusion of any hearing, by majority vote, issue its award. The award shall include an allocation of fees and costs pursuant to 11.7.7 herein. The award is to be in accordance with the Contract and the law of the State of Arizona. 11.7.3 Scope of Award. Regardless of the provisions of the RUAA, the arbitration panel shall be without authority to award punitive damages, and any such punitive damage award shall be void. If an award is made against any party in excess of one hundred thousand dollars ($100,000), exclusive of interest, arbitration fees, costs and attorneys’ fees, it shall be supported by written findings of fact, conclusions of law and a statement as to how damages were calculated. 11.7.4 Jurisdiction. The arbitration panel shall not be bound for jurisdictional purposes by the amount asserted in any party’s claim, but shall conduct a preliminary hearing into the question of jurisdiction over the claim as regards its amount upon application of any party at the earliest convenient time, but not later than the commencement of the arbitration hearing. If the dispute is determined to involve less than $200,000, the arbitration shall continue before the Neutral Arbitrator as a single arbitrator, with the party appointed arbitrators being excused. 11.7.5 Entry of Judgment. As provided in the RUAA, any party can make application to the Maricopa County Superior Court for confirmation of an award, and for entry of judgment on it. 11.7.6 Severance and Joinder. To reduce the possibility of inconsistent adjudications, the Mediator or the single arbitrator or arbitration panel, may: (i) at the request of any party, join and/or sever parties, and/or claims arising under other contracts containing this ADR provision, and (ii) the Mediator, on his own authority, or the single arbitrator or arbitration panel may, on its own authority, join or sever parties and/or claims subject to this ADR process as deemed necessary for a just resolution of the dispute, consistent with the parties’ goal of the prompt and efficient resolution of disputes, provided; however, that the A/E, OWNER and Project Professionals shall not be joined as a party to any claim made by an Architect. Nothing herein shall create the right by any party to assert claims against another party not arising under or related to the Contract or not recognized under the substantive law as applicable to the dispute. Neither the Mediator nor the single arbitrator or arbitration panel is authorized to join to the proceeding parties not in privity with the County. The Architect cannot be joined to any pending arbitration proceeding, without Architect’s express written consent and unless Architect is given the opportunity to participate in the selection of the single arbitrator or non-County appointed arbitrator. Durango Juvenile Courts Demolition Page | 28 CMR Professional Services Contract Serial # 260056-ROQ 11.7.7 Fees and Costs. Each party shall bear its own fees and costs in connection with any informal hearing before the mediation. All fees and costs associated with any arbitration before the single panel or arbitration panel, including without limitation the arbitrator fees, and the prevailing party’s reasonable attorneys’ fees, expert witness fees and costs, will be paid by the non-prevailing party, except as provided for herein. In the event that Architect is the non-prevailing party, all fees and costs as noted above shall first be paid out of the bond posted with the arbitrator. In no event shall the Architect’s obligation to pay fees and costs be limited to the amount of the bond posted herein. In no event shall any arbitrator’s hourly fees be awarded in an amount in excess of $250 per hour and (i) costs shall not include any travel expenses in excess of mileage at the rate paid by Maricopa County, not to exceed a one way trip of 150 miles, and (ii) all travel expenses, including meals, shall be reimbursed pursuant to the travel policy of Maricopa County in effect at the time of the hearing. The determination of prevailing and non-prevailing parties, and the appropriate allocation of fees and costs, will be included in the award by the single arbitrator or arbitration panel. 11.7.8 Confidentiality. Any proceeding initiated under this ADR provision shall be deemed confidential to the maximum extent allowed by Arizona law and, except for disclosures to a party’s attorneys or accountants, no party shall make any disclosure related to the disputed matter or to the outcome of any proceeding except to the extent required by law, or to seek interim equitable relief, or to enforce an agreement reached by the parties or an award made hereunder. This provision does not affect the County’s right to inform the County Supervisors of the dispute. 11.7.9 Equitable Litigation. Notwithstanding any other provision of ADR to the contrary, any party can petition the Maricopa County Superior Court for interim equitable relief as may become necessary to preserve the status quo and prevent immediate and irreparable harm to a party or to the Project pending resolution of a dispute pursuant to ADR provided herein. No court may order any permanent injunctive relief except as may be necessary to enforce an order entered by the arbitration panel. The fees and costs incurred in connection with any such equitable proceeding shall be determined and assessed in ADR. 11.7.10 Change Order. Any award in favor of the Architect against the County or in favor of the County against the Architect shall be reduced to a Change Order and executed by the parties in accordance with the award and the provisions of the Contract or a settlement agreement as appropriate. 11.7.11 Merger and Bar. Any claim asserted pursuant to this ADR process shall be deemed to include all claims, demands, and requests for compensation for costs and losses or other relief, including the extension of the Contract performance period which reasonably should or could have been brought against any party that was or could have been brought into this ADR process, with respect to the subject claim. The arbitration panel shall apply legal principles commonly known as merger and bar to deny any claim or claims against any party regarding which claim or claims recovery has been sought or should have been sought in a previously adjudicated claim for an alleged cost, loss, breach, error, or omission. 11.8 Inclusion in Other Contracts. The Architect shall cooperate with the County in efforts to include this ADR provision in all other Project contracts. ARTICLE 12: SUSPENSION AND TERMINATION 12.1 PROJECT SUSPENSION: Durango Juvenile Courts Demolition Page | 29 CMR Professional Services Contract Serial # 260056-ROQ Owner may suspend the Project and DP’s services without cause but if the Project is suspended for more than one-hundred eighty (180) days, DP shall be paid for all Basic Services and Reimbursables that have been authorized by an Authorization to Proceed and that were performed by DP and accepted by Owner prior to the date of such suspension. If the Project is resumed after having been suspended for more than 180 days, DP’s further compensation shall be subject to renegotiation. 12.2 TERMINATION OF AGREEMENT: 12.2.1 Owner has the right to terminate this Agreement for its convenience upon seven (7) days written notice to DP. Upon such termination, all charts, sketches, studies, drawings, models and other documents related to services performed under this Agreement, whether finished or not, shall be turned over to Owner within ten (10) days of notice of termination provided that DP has been paid in full for services rendered and approved by Owner as of the date of termination and reasonable termination costs supported by documentation. 12.2.2 Owner has the right to terminate this Agreement for default upon seven (7) days written notice stating the grounds for default or material breach. If DP has not cured the default or breach to the satisfaction of Owner, Owner shall receive ownership of all design documents upon request of Owner and Owner has the right to use, renovate and to make derivative works of the design documents in order to complete the Project. 12.2.3 Termination, for whatever cause or on whatever basis, shall not result in DP’s being entitled to claim any lost profits as a result of the termination. ARTICLE 13: MISCELLANEOUS 13.1 MAINTENANCE OF RECORDS: DP shall maintain and require Sub-consultant to retain adequate records and supporting documentation which concern or reflect its services hereunder. The records and documentation will be retained by DP for a minimum of six (6) years from the date of termination of this Agreement or the date the Project is completed, whichever is later. Owner, or any duly authorized agents or representatives of Owner, shall have the right to audit, inspect, and copy all such records and documentation as often as they deem necessary during the period of this Agreement and during the six (6) year period noted above. Refusal of DP to comply with the provisions of this section shall be grounds for termination for cause of this Agreement by Owner. 13.2 CANCELLATION: Owner may cancel this Agreement without penalty or further obligation under A.R.S. § 38-511 if any person significantly involved with this Agreement on behalf of Owner is or becomes a consultant to DP or a Sub-consultant with respect to the subject matter of the Agreement or an employee of DP does so. 13.3 PAYMENT OBLIGATIONS: All payment obligations of Owner are conditioned on the availability of funds which are approved and allocated for such obligation. If funds are not allocated and available for continuation of DP’s services, this Agreement may be terminated or suspended at the end of the time period for which funds are available. No liability or penalty shall accrue or be attributable to Owner in the event it becomes necessary to exercise rights under this provision. Durango Juvenile Courts Demolition Page | 30 CMR Professional Services Contract Serial # 260056-ROQ 13.4 NON-DEFINED TERMS: If not specifically defined herein, terms, words and phrases will have their ordinary and common meaning and they, together with abbreviations, shall be interpreted consistent with the design professional industry standards and technical and trade meanings. 13.5 NON-WAIVER PROVISIONS: The failure of the Owner to insist, in any one or more instances, on the performance of any of the terms, covenants or conditions of the Agreement, or to exercise any of its rights hereunder, shall not be construed as a waiver or relinquishment of such terms, covenant, conditions or right with respect to further performance. 13.6 NO HAZARDOUS SUBSTANCES OR PRODUCTS: DP shall use reasonable care not to specify for use in the Project any product known by DP to contain hazardous substances as deemed in 42 U.S.C 9601, et seq., unless no reasonable alternative is available and in that case Owner consent to sue shall first be obtained. 13.7 ENVIRONMENTAL CONTAMINATION: DP shall immediately notify Owner both verbally and in writing of the presence of and location of any environmental contamination of the site which it becomes aware of or reasonably should become aware, including, but not limited to, hazardous substances and petroleum releases. 13.8 ADA REQUIREMENTS: The Americans with Disabilities Act (“ADA”) is applicable to the Project. DP will use its skill and training as a design professional and exercise the applicable standard of care to design the Project in compliance with ADA requirements. 13.9 SUCCESSORS AND ASSIGNS: 13.9.1 The performance of this Agreement shall not be transferred, pledged, sold, delegated or assigned, in whole or in part, by DP without the written consent of Owner. 13.9.2 DP and Owner each binds one another, their partners, successors, legal representatives and authorized assigns to the other party of this Agreement and to the partners, successors, legal representatives and assigns of such party in respect to all covenants of this Agreement. 13.10 CERTIFICATION OF WAGE RATES AND UNIT COSTS: For any Authorization to Proceed for a project to be compensated under the Lump Sum method, DP shall certify that wage rates and other factual unit costs supporting the compensation are accurate, complete, and current at the time of said Authorization to Proceed. The original Project price and any addition thereto will be adjusted to exclude any significant sums by which Owner determines the project price was increased due to inaccurate, incomplete or noncurrent wage rates and other factual unit costs. All such price adjustments will be made within one (1) year following the end of the Project. 13.11 NOTICES: Whenever any party is required to give notice unto the other, such notice must be in writing, sent by registered United States mail, return receipt requested, addressed to the party for whom it is intended at the place last specified; and the place for giving of notice shall remain such until it shall Durango Juvenile Courts Demolition Page | 31 CMR Professional Services Contract Serial # 260056-ROQ have been changed by written notice in compliance with the provisions of this paragraph. For the present, the parties designate the following as the respective places for giving of notice: FOR OWNER: Director, Maricopa County Facilities Management Department 401 W. Jefferson Street Phoenix, Arizona 85003 FOR DP: Ted Schmidt Shive-Hattery 407 W. Osborn Road, Suite 200, Phoenix, AZ 85013 13.12 SEVERABILITY: If any term, covenant, condition or provision of this Agreement (or the application thereof to any circumstance or person) shall be invalid or unenforceable to any extent, the remaining terms, covenants, conditions and provisions of this Agreement shall not be affected thereby; and each remaining term, covenant, condition and provision of this Agreement shall be valid and shall be enforceable to the fullest extent permitted by law unless the enforcement of the remaining terms, covenants, conditions and provisions of this Agreement would prevent the accomplishment of the original intent of the agreement between the parties. 13.13 SURVIVAL OF PROVISIONS: All terms, conditions, covenants and obligations of Owner and DP hereunder shall survive the termination or expiration of this Agreement as necessary and appropriate for such parties to fulfill their obligations that accrued during the Term of this Agreement. 13.14 EXTENT OF AGREEMENT: This Agreement represents the entire and integrated agreement between Owner and DP and supersedes all prior negotiations, representations or agreements, written or oral. This Agreement may not be amended, changed, modified, or otherwise altered in any way, at any time after the execution hereof, except by a written document executed with the same formality and equal dignity herewith. Waiver by either party of a breach of any provision of this Agreement shall not be deemed to be a waiver of any other breach of any provision of this Agreement. 13.15 NO CONTINGENT FEE: DP (or registered surveyor and mapper or professional engineer, as applicable) warrants that he or she has not employed or retained any company or person, other than a bona fide employee working solely for DP (or registered surveyor and mapper, or professional engineer, as applicable) to solicit or secure this Agreement and that he or she has not paid or agreed to pay any person, company, corporation, individual, or firm, other than a bona fide employee working solely for DP (or registered surveyor and mapper or professional engineer, as applicable) any fee, commission, percentage, gift, or other consideration contingent upon or resulting from the award or making of this Agreement. For the breach or violation of this provision, Owner shall have the right to terminate the Agreement without liability and, at its discretion, to deduct from the contract price, or otherwise recover, the full amount of such fee, commission, percentage, gift, or consideration. 13.16 APPLICABLE LAW AND VENUE OF LITIGATION: This Agreement shall be enforced, interpreted, and construed in accordance with and governed by the laws of the State of Arizona, including the Revised Uniform Arbitration Act (A.R.S. § 12-3001 et Durango Juvenile Courts Demolition Page | 32 CMR Professional Services Contract Serial # 260056-ROQ seq.), which is applicable hereto. Any suit or action brought by any party concerning this Agreement, or arising out of this Agreement, shall be brought in Maricopa County, Arizona. 13.17 INTERPRETATION: The language of this Agreement has been agreed to by both parties to express their mutual intent and no rule of strict construction shall be applied against either party hereto. The headings contained in this Agreement are for reference purposes only and shall not affect in any way the meaning or interpretation of this Agreement. All personal pronouns used in this Agreement shall include the other gender, and the singular shall include the plural, and vice versa, unless the context otherwise requires. Terms such as “herein,” ‘hereof,” “hereunder,” and “hereinafter” refer to this Agreement as a whole and not to any particular sentence, paragraph, or section where they appear, unless the context otherwise requires. Whenever reference is made to a Section or Article of this Agreement, such reference is to the Section or Article as a whole, including all of the subsections of such Section, unless the reference is made to a particular subsection or subparagraph of such Section or Article. 13.18 PRIORITY OF PROVISIONS: If there is a conflict or inconsistency between any term, statement, requirement, or provision of any exhibit attached hereto, any document or events referred to herein, or any document incorporated into this Agreement by reference and a term, statement, requirement, or provision of this Agreement, the term, statement, requirement, or provision contained in this Agreement shall prevail and be given effect. 13.19 COMPLIANCE WITH LAWS: DP shall comply with all applicable laws, codes, ordinances, rules, regulations and resolutions in performing its duties, responsibilities and obligations related to this Agreement. 13.20 PRIOR AGREEMENTS: This document incorporates and includes all prior negotiations, correspondence, conversations, agreements and understandings applicable to the matters contained herein and the parties agree that there are no commitments, agreements or understandings concerning the subject matter of this Agreement that are not contained in this document. Accordingly, the parties agree that no deviation from the terms hereof shall be predicated upon any prior representations or agreements, whether oral or written. It is further agreed that no modification, amendment or alternation in the terms or conditions contained herein shall be effective unless set forth in writing. 13.21 LEGAL WORKER REQUIREMENTS: As required by A.R.S. § 41-4401, Owner is prohibited after September 30, 2008 from awarding a contract to any service or construction contractor who fails, or whose subcontractors fail, to comply with A.R.S. § 23-214-A. CMR warrants that it complies fully with all federal immigration laws and regulations that relate to its employees, that it shall verify, through the employment verification pilot program as jointly administrated by the U.S. Department of Homeland Security and the Social Security Administration or any of its successor programs, the employment eligibility of each employee hired after December 31, 2007, and that it shall require its subcontractors and sub- subcontractors to provide the same warranties to CMR. CMR acknowledges that a breach of this warranty by CMR or by any subcontractor or sub-subcontractor under this Agreement shall be deemed a material breach of this Agreement, and is grounds for penalties, including termination of this Agreement by Owner. Owner retains the right to inspect the records of any DP, subcontractor and sub-subcontractor employee who performs work under this Agreement, and to conduct random verification of the employment records of CMR any subcontractor and sub-subcontractor who works on this Contract, to ensure that CMR and each subcontractor and sub-subcontractor is complying with the warranties set forth above. CMR shall be responsible for all costs associated with compliance with this requirement. Durango Juvenile Courts Demolition Page | 33 CMR Professional Services Contract Serial # 260056-ROQ 13.22 INFLUENCE: As prescribed in MC1-1203 of the Maricopa County Procurement Code, any effort to influence an employee or agent to breach the Maricopa County Ethical Code of Conduct or any ethical conduct, may be grounds for Disbarment or Suspension under MC1-902. An attempt to influence includes, but is not limited to: 13.22.1 A person offering or providing a gratuity, gift, tip, present, donation, money, entertainment, educational passes, tickets, or any type of valuable contribution or subsidy, 13.22.2 That is offered or given with the intent to influence a decision, obtain a contract, garner favorable treatment, or gain favorable consideration of any kind. 13.23 AMENDMENTS: All amendments to this Contract shall be in writing and approved/signed by both parties. Maricopa County Office of Procurement Services shall be responsible for approving all amendments for Maricopa County. 13.24 NON-DISCRIMINATION: CONTRACTOR agrees to comply with all provisions and requirements of Arizona Executive Order 2009-09 including flow down of all provisions and requirements to any subcontractors. Executive Order 2009-09 supersedes Executive order 99-4 and amends Executive order 75-5 and may be viewed and downloaded at the Governor of the State of Arizona’s website https://apps.azsos.gov/public_services/register/2009/46/governor.pdf which is hereby incorporated into this contract as if set forth in full herein. During the performance of this contract, CONTRACTOR shall not discriminate against any employee, client or any or any other individual in any way because of that person’s age, race, creed, color, religion, sex, disability or national origin. 13.25 UNIFORM ADMINISTRATIVE REQUIREMENTS: When applicable and by entering into this Contract the Contractor agrees to comply with all applicable provisions of Title 2, Subtitle A, Chapter II, PART 200—UNIFORM ADMINISTRATIVE REQUIREMENTS, COST PRINCIPLES, AND AUDIT REQUIREMENTS FOR FEDERAL AWARDS contained in Title 2 C.F.R. § 200 et seq. 13.26 FORCED LABOR 13.26.1 By submitting a bid for this solicitation and/or entering into a contract as a result of this solicitation, contractor agrees to comply with all applicable portions of Arizona Revised Statutes Section 35-394. Contracting; procurement; prohibition; written certification; remedy; termination; exception; definitions. 13.26.2 Contractor certifies that it does not currently, and agrees for the duration of the contract, that it will not use: 13.26.2.1 The forced labor of ethnic Uyghurs in the People’s Republic of China. 13.26.2.2 Any goods or services produced by the forced labor of ethnic Uyghurs in the People’s Republic of China. Durango Juvenile Courts Demolition Page | 34 CMR Professional Services Contract Serial # 260056-ROQ 13.26.2.3 Any contractors, subcontractors or suppliers that use the forced labor or any good or services produced by the forced labor of ethnic Uyghurs in the People’s Republic of China. 13.26.3 If contractor becomes aware during the term of the agreement that contractor is not in compliance with this paragraph, the contractor shall notify the County within five business days after becoming aware of the noncompliance. If the contractor fails to provide a written certification to the County that the contractor has remedied the noncompliance within 180 days after notifying the County of its noncompliance, then the agreement terminates, except that if the agreement termination date occurs before the end the 180 day period, the agreement terminates on the agreement termination date. 13.27 WRITTEN CERTIFICATION PURSUANT TO A.R.S. § 35-393.01 If vendor engages in for-profit activity and has 10 or more employees, and if this agreement has a value of $100,000 or more, vendor certifies it is not currently engaged in, and agrees for the duration of this agreement to not engage in, a boycott of goods or services from Israel. This certification does not apply to a boycott prohibited by 50 U.S.C. § 4842 or a regulation issued pursuant to 50 U.S.C. § 4842. 13.28 COMPLIANCE WITH WEB CONTENT ACCESSIBILITY GUIDELINES (WCAG) Contractor agrees and warrants that all of its web content services and products and all of its mobile apps services and products, covered under this contract, and in all languages provided, comply with Level A and Level AA success criteria and conformance requirements specified in the Web Content Accessibility Guidelines (WCAG) 2.1(AA) or will be modified to be compliant prior to delivery or installation to County. Contractor further agrees and warrants that all web content services and products and all mobile apps services and products, in all languages provided, shall remain in full compliance with the above WCAG success criteria and conformance requirements during the term of the contract. Contractor agrees to immediately notify County in the event it becomes aware that any web content services and products or any mobile apps services and products provided under this Contract become non-compliant with the above WCAG success criteria and conformance requirements, if applicable. In such an event, Contractor agrees it will work to remediate any identified compliance deficiencies and will notify County concerning the estimated remediation completion date. Upon request, Contractor shall provide County with documentation, including but not limited to a third-party assessment certificate, substantiating compliance of the services or products with the above WCAG success criteria and conformance requirements and any other applicable governmental regulations regarding accessibility. Non- compliance with the above WCAG success criteria and conformance requirements will be deemed a material breach of the contract and the County may immediately terminate the contract or impose other legal remedies at the County’s discretion, including suspension of services and/or products. The County reserves the right to audit Contractor’s compliance with the above WCAG success criteria and conformance requirements. The Contractor will indemnify, defend, and hold harmless the County against any third-party claims arising from the Contractor’s non-compliance with the above WCAG success criteria and conformance requirements. . Durango Juvenile Courts Demolition Page | 35 CMR Professional Services Contract Serial # 260056-ROQ IN WITNESS WHEREOF, this agreement shall be in full force and effect only when the Board of Supervisors of Maricopa County, Arizona has approved it, and when executed by the Chairman of the Board of Supervisors or when applicable, the Chief Procurement Officer. Shive-Hattery, Inc. 42-0870172 Design Professional Firm Name Federal Tax Identification Number 15427 Arizona State Board of Technical Registration # 09/08/2026 Principal (Signature) Date Ted W. Schmidt, PE Project Manager Printed Name Title Net 30 Vendor’s/Firm’s Payment Terms COUNTY OF MARICOPA, ARIZONA ATTEST: RECOMMENDED BY: ___________________________________ ___________________________________ Department Head Date Clerk of the Board Date ACCEPTED AND APPROVED: LEGAL REVIEW: _n/a_________________________________ Approved as to form and within the powers and Kevin Tyne, Date authority granted under the laws of the State of Chief Procurement Officer Arizona to Maricopa County. By: ______________________________________ ___________________________________ Deputy County Attorney Date Chair, Date Board of Supervisors _906-07_____________________________ NIGP Commodity Code (Advantage) Durango Juvenile Courts Demolition Page | 36 CMR Professional Services Contract Serial # 260056-ROQ EXHIBIT “A”: HOURLY RATES AND HOURS and EXHIBIT “B”: LUMP SUM AMOUNT Durango Juvenile Courts Demolition Page | 37 CMR Professional Services Contract Serial # 260056-ROQ August 21, 2026 Mr. Donald Bump Maricopa County, AZ Capital Project Manager Facilities Management 401 W. Jefferson Street Phoenix, AZ 85003 RE: Proposal Scope Letter for MC Durango Juvenile Courts Demolition – Buildings 17-05 & 17-06, Serial # 260056-ROQ Mr. Bump: This proposal outlines the design services for the Durango Juvenile Courts Demolition Project, Buildings 17-05 and 17-06. It is based on the original RFP solicitation, along with information provided during the Maricopa County Facilities Management pre-proposal conference and site visit on August 10, 2026. We understand the design professional will provide architectural and engineering design services, construction administration, and post-construction services. The project is anticipated to use a Construction Manager at Risk (CMR) delivery method. The scope includes building demolition design and the reconfiguration of site utilities and MEP infrastructure needed to maintain service continuity to adjacent buildings. Site landscaping, fencing, lighting, and cameras will also be reconfigured. Services will include, but are not limited to, architectural, structural, mechanical, fire protection, plumbing, electrical, civil, landscape, and security disciplines, as well as survey, utility locate, and cost estimating specialty consultants. SCOPE OF WORK Shive-Hattery will provide design and construction administration services for the demolition of a vacated portion of the Durango Juvenile Detention Facility, Buildings 17-05 and 17-06, on the Maricopa County Durango Campus. Services include site investigation, preparation of demolition plans and specifications, permitting support, cost estimating, bidding assistance, and construction administration. Existing conditions will be confirmed for site utilities and infrastructure, including all connections to adjacent facilities. Work will also include identifying, mapping and developing strategies for safe disconnection, isolation, and protection of active systems to ensure continuity of operations and avoid service disruptions. Shive-Hattery will use the following subconsultants for this project: CSQ Associates for estimating, Pearson Engineering Associates for MEP design, SAM for topographic survey and utility locates, and Broderick Engineering for structural design. Phases that are anticipated include: Schematic Design, Design Development, 50% Construction Documents, 100% Construction Documents, Construction Administration and Post Construction. We are not expecting an early Programming phase. SD/CA – SCHEMATIC DESIGN THROUGH & CONSTRUCTION ADMINISTRATION Part - Schematic Design Services: A. Schematic Design will include majority of the existing conditions investigations and research, topographic survey, utility locates and building scanning. B. Shive-Hattery will review with the Owner information pertaining to site utilities Project 2260011550 Page 2 of 4 requirements, criteria and Owner provided items. C. Shive-Hattery will meet with AHJ's officials to discuss project requirements. Currently, we are anticipating two permitting reviews. One after investigations at the completion of schematic design, and the other at the completion of technical Construction Documents. D. Shive-Hattery will prepare Building Code Analysis. E. Modify the site and utility layouts based on owner comments and provide updated design development documents to owner for approval. F. Provide updated estimate of probable costs, based on schematic design directions obtained from client meetings. Part - Design Development Documents. A. Based on the Owner’s approval of the Schematic Design Documents, and on the Owner’s authorization of any adjustments in the Project requirements and the budget for the Cost of the Work, the Architect shall prepare Design Development Documents for the Owner’s approval. The Design Development Documents shall illustrate and describe the development of the approved Schematic Design Documents and shall consist of drawings and other documents including plans, sections, elevations, typical construction details, and diagrammatic layouts of building systems to fix and describe the size and character of the Project as to architectural, civil, structural, mechanical and electrical systems, and such other elements as may be appropriate. The Design Development Documents shall also include product specifications that identify major materials and systems and establish in general their quality levels. B. The Architect shall update the estimate of the Cost of the Work. C. The Architect shall submit the Design Development Documents to the Owner, advise the Owner of any adjustments to the estimate of the Cost of the Work, and request the Owner’s approval. Part - Construction Documents. A. The documents will include Architectural, Structural, Mechanical, Electrical and Civil technical documents and bid specifications. 1). Site Plan/Construction Documents: 1. Based on design developed site layout, review with the owner to obtain comments, finalize site demo, utility relocations, earthwork, and site restoration documents. 2. Prepare construction documents for approved layout in accordance with the local standards. 2). Construction documents to include the following sheets: 1. Site demolition plan following the design requirements. 2. Site layout plan following the design requirements. 3. Site grading plan providing finish grade information. 4. Site utility plan to include any site utility relocations around the building site. 5. Architectural plans including but not limited to, reflected ceiling, elevations, details, schedules, and code plans. 6. Engineering plans including but not limited to, foundation, framing, HVAC, plumbing, fire protection, electrical power and lighting, and special systems Project 2260011550 | August 21, 2026 Page 3 of 4 for data, communication, and security. 7. Permitting and Building Code review activities. B. Provide general construction notes and construction details of proposed improvements in concert with FMD Standards, project requirements, as well as integration of Construction Manager as Risk (CMR) considerations. C. Provide specifications for improvements that shall reference local standards with any deviations noted on the drawings. Part - Construction Administration (CA). Based on ‘Technical’ Construction documents prepared by Shive-Hattery (drawings and specifications) for the building and site components for the purposes of bidding or establishing as guaranteed maximum price (GMP) construction contract. Bidding & Negotiation (within the CA Phase): A. Shive-Hattery will administer issuance of the Bid Documents and Specification in accordance with public bid requirements, for a prime GMP combined construction contract. It is anticipated that the project will be bid in a single issuance. 1). Bid Document printing, applicable fees and permits by owner. Construction Administration: A. Shive-Hattery will respond to questions from the Client and the Contractors. B. Shive-Hattery will review shop drawing and product data submittals from the Contractor. Reviewing submittals more than twice will be handled as an additional service, at the expense of the Contractor. C. Shive-Hattery will review and certify Contractor application for payments monthly. D. Shive-Hattery will administer construction modification procedures working within FMD standards and requirements. Owner directed change orders and construction change directives will be administered accordingly. E. Shive-Hattery will perform site visits during the construction period. These visits include preconstruction conference(s), a minimum of once-a-month progress meetings and field inspections during construction, specific topic field inspections, one substantial completion review and one final inspection. Part – Post Construction A. Shive-Hattery will provide record documents per FMD standards and requirements. Contractor will provide redline as-builts during construction to assist in record documents process. PRELIMINARY DESIGN SCHEDULE The services will be completed in accordance with the schedule developed with the Owner and the CMR for this project. A preliminary project schedule is noted below: Schematic Design – September 2026 – November 2026 Design Development – November 2026 – January 2027 50% Construction Documents – January 2027 – March 2027 100% Construction Documents – March 2027 – June 2027 Bidding and Construction Start – July 2027 Project 2260011550 | August 21, 2026 Page 4 of 4 DESIGN FEE SERVICES Design scope services for the project are based on pre-proposal meeting and site visit on August 10, 2026. Basic design service fees, modifications to the stipulated services, FMD Allowance, are as follows (see detailed work sheet for further breakdown): Basic Services Total Fee for Phase Programming $ (Not Applicable) Schematic Design $214,785.00 Design Development $152,310.00 50% Construction Documents $118,118.00 100% Construction Documents $116,528.00 Construction Administration $109,816.00 Post Construction $ 27,403.00 SUB TOTAL – Basic Services $738,960.00 Stipulated Services (If Necessary) FMD Allowance $45,000.00 SUB TOTAL – Stipulated Services $45,000.00 Reimbursable Expenses None Total Summary Design Fee Service Totals $783,960.00 Please let us know if you have any questions or comments at this time. Sincerely, SHIVE-HATTERY, INC. Ted Schmidt, PE Principal / Project Manager tschmidt@shive-hattery.com TWS/mas Encs.: Durango – CSQ Proposal dated 08-21-2026.pdf (2 pages) Durango – Pearson MEP Proposal dated 08-20-2026.pdf (7 pages) Durango – SAM Survey Proposal dated 08-13-2026 (5 pages) Durango – Broderick Fees Document dated 08-19-2026 (1 page) Fee Proposal Breakdown Excel file Copy: Liam Larkin, Shive-Hattery Michael Lewis, Shive-Hattery Project 2260011550 | August 21, 2026 8/21/26 Mr. Liam Larkin, AIA, NCARB, LEED AP BD+C Shive-Hattery 209 W 19th Terrace Suite 200 Kansas City, MO 64108 Re: Maricopa County Facilities Management Maricopa County Durango Campus 1705 & 1706 Juvenile Detention Demolition Dear Mr. Larkin, We are pleased to provide a proposal for the above referenced project. Scope of Project The scope of services is based on the following program: > Razing of existing buildings 1705 & 1706 > New utilities for each of the existing to remain > Building Envelope enclosures at removed portions (2) locations. > New Supplemental additions to support new MEP equipment and Vestibules. > Sitework is limited, area to be surfaced with aggregate at removal areas. Base Cost Opinion Development Services Schematic Stage (1) “ Hard Cost” Opinion Study for up to (2) Design Schemes Schematic Stage The following allowances are included in the Schematic Design Stage Study: • (6) hours for scope discussions, Team meetings and reviews based on Teleconferences • (2) hours for cost opinion revisions based on review discussions base option • (6) hours for Preliminary Phasing approach 50% Design Development Phase Update (1) “Hard Cost” Opinion study update based on one of the schemes selected in the schematic design phase. The following allowances are included in the Schematic Design Stage Study: • (4) hours for scope discussions, Team meetings and reviews based on Teleconferences • (6) hours for peer review comparative analysis of the selected CmC’s cost estimate The study will be organized by the customary 16 UCI trade categories in our corporate standard format. The study will also include Clarifications/Assumptions and Graphic Illustrations of scope of work assumptions for critical elements. The proposal is based on receiving scalable drawings of the option layout, existing facility construction documents and images of the facility existing conditions. Maricopa County to provide any environmental abatement costing or associated work. Fee Schedule > (1) Schematic Stage Cost Opinion Study, up to (2) Schemes; Lump sum of $ $13,490.00. > (1) 50% Design Development Cost Opinion Update for the Selected Scheme costed during schematic stage Lump sum of $11,210.00 Please note that the 50% DD stage estimate fee is based on the complete services being performed in the concept design stage. Timeline for Delivery: Please allow a minimum of (2-3) weeks from Receipt of complete set of Documents as outlined above and Notice to Proceed. Payment Terms: Net 10 Working days after issuance of invoice Available Additional Services • Options beyond (2) Schemes • Any work Beyond 50% design Stage • Sitework development beyond utilities or aggregate surfacing • Detailed Cost/Phasing Analysis C • Alternative Energy or LEED Strategy analysis • Hours that exceed the stated allowances above • Any On-Site Meetings or Site Walk-thru • Additional Post estimate issuance Cost Reduction Studies and/or Value Analysis Studies • Detailed CPM Development for Construction Timeline Scheduling • Project “Soft Cost” Cost Analysis or Assembly Additional Services will be invoiced at a rate of $190.00 per hour on a quarter hour basis. CSQ is not responsible and will not be liable for any budget changes, additions or constraints requiring a Project redesign either prior to or after bidding. After bidding, if the Project comes in over the estimate, CSQ will provide additional estimating support upon request to assist the Design Team in its efforts to bring the Project within budget. Unless specifically included in the fees described above, additional fees may apply for such support. CSQ shall perform its services to the standard of professional skill and care ordinarily provided by cost estimators practicing in the same or similar locality under the same or similar circumstances. CSQ has no control over the cost of labor, materials, or equipment, or over market conditions or factors that affect contractor bidding or negotiations. CSQ makes no warranty, guarantee, or representation that CSQ’s cost estimates or contractor bids will come in under the budget for the work. CSQ appreciates the opportunity to be part of the Project Team and look forward to your favorable consideration. Sincerely, CSQ ASSOCIATES, INC William S. Gorski, Jr CPE, LEED AP, President C Delivery Method: Email Email: tschmidt@shive-hattery.com August 13, 2026 Ted W. Schmidt Civil Engineer | Managing Director Shive Hattery 407 W Osborn Rd. Suite 200 Phoenix, AZ 85013 RE: Shive Hattery – MCC Durango Demolition Topographic Survey Maricopa County, Arizona SAM Project Number: 1026113900 Dear Ted, Surveying And Mapping, LLC (SAM) is pleased to provide Shive-Hattery with this proposal for professional surveying services in connection with the project located in Maricopa County, Arizona. Based upon the information provided to SAM and our discussions concerning the project, we have prepared the following Scope of Services. After you have reviewed the proposed Scope of Services and Fee Estimate, please do not hesitate to contact us if you have any questions or comments. All work within the Scope of Work provided below will be billed based on a Lump Sum Pricing Schedule. Thank you for the opportunity to serve you. We are looking forward to working with you on this project and future projects. Sincerely, Erick Welch, PLS, CFedS Phoenix Area Leader CC: Jared Litton, LSIT Project Coordinator SAM COMPANIES 4801 Southwest Parkway / Bldg. 2 Suite 100 / Austin, Texas 78735 512.447.0575 Office / 512.326.3029 Fax / TBPELS #10064300 sam.biz Scope of Services Shive Hattery – MCC Durango Demolition Topographic Survey Project Overview Shive Hattery description for this project is as follows: • The Maricopa County Durango Detention Demolition building is planning to demo the building and remove the building utility services back to the mains. • The total size of the project area is approximately 200,000 SQ FT. • Shive-Hattery is requesting a topographic survey within the area outlined in red per Exhibit A, located in Phoenix, Arizona. Topographic Survey SAM LLC will provide survey services for the following: • A topographic survey of the area provided and shown in Exhibit A. The topographic survey will include: o Planimetric drawing o Surface drawing • Features to be included in the planimetric drawing are (but not limited to): o Paint stripes o Curb/gutter and sidewalks o Trees and other vegetation o Fences o Edge of building • All visible above ground utilities marked (blue staked) utilities, and inverts of manhole structures. Additional Services – Survey In addition to the services outlined above, SAM will provide additional services as requested by the client on a time and materials basis, based upon our Contract Rate Schedule. If requested, a scope of work and estimated fee will be provided in writing prior to SAM proceeding with any additional service. Private Utility Locate SAM will provide utility locating services as follows: Page 2 of 5 • SAM will perform a utility plan search for all utilities in the project area. These include: o Arizona Public Service o City of Phoenix Water Department o Cox Communications o Lumen o Forged Fiber 37 o Roosevelt Irrigation District o Verizon/MCI o Southwest Gas • SAM team members will locate the existing utilities in the area shown in Exhibit A using geophysical equipment and techniques. The utility locations will be marked using the appropriate color as prescribed by Arizona Statute with pink and white modifications to make clear that these lines are private locates not an Arizona 811 response. Project Deliverables – Survey SAM will provide the following project deliverables: • Survey coordinate point data in comma-delimited text (txt) file format (point, north, east, elevation, description), including feature codes and legend. • CAD base map with all survey points. • XML surface of existing features. Project Schedule Based on a written agreement and notice to proceed, we will mobilize within 5 days and complete the survey work in a safe and efficient manner pending no weather delays or conditions beyond our control. Weather conditions that are conducive to conducting the field work will be paramount to the successful completion of any field services and changing weather conditions may lengthen the schedule. SAM’s Project Manager will keep the client updated of the progress and any delays that occur. SAM to provide Client final deliverables: Within 2-3 weeks of NTP. Assumptions The following assumptions were made for the preparation of this Scope of Services. If these assumptions do not prove correct, a modification to the scope and budget for this project may be required. • SAM will not begin work until written Notice-To-Proceed is received. • Client will provide right-of-entry for any areas requiring access to perform and complete surveying and mapping efforts, prior to deployment of SAM field crew. • Project area is representative of that area shown on Exhibit A, below. • Survey field staff will be able to perform weekend work if necessary. SAM does not assume any weather delays that would impact proposed schedule. If we encounter weather related delays, SAM will notify client of any impacts to the schedule. Page 3 of 5 • This survey will be referenced to the Arizona State Plane, Central Zone, International Foot, Horizontal Datum and the NAVD 88, Geoid 18 - US Survey Feet Vertical Datum, or Shive Hattery-approved local datum as the vertical datum and International foot as the unit of measurement, as long as Client communicates datum details prior to survey. • All survey work will be performed under the direction of a licensed Arizona Land Surveyor. • SAM assumes no permit documents are required as part of this SOW. • SAM will not survey boundary monuments, as client is not requesting a boundary survey. Fees Price Breakdown 2 Man Survey Crew $235 x 30 hours $7,050 Senior Office Technician $150 x 20 hours $3,000 Topographic Survey and Deliverables $10,050 Price Breakdown Sr. Project Manager $275 x 4 hours $1,100 Senior Office Technician $150 x 4 hours $600 SUE Field Technician III $200 x 24 hours $4,800 SUE Field Technician II $135 x 24 hours $3,240 Equipment Charges $2,000 Subsurface Private Utility Locate $11,740 Total Cost of Site Survey $21,790 Additional Services will be communicated to Client and will require authorization prior to proceeding with work and will be billed based on the SAM hourly rate schedule. Page 4 of 5 Project Location Exhibit “A” Page 5 of 5 $180.00 $150.00 $220.00 $1,050.00 $1,600.00 Construction Fee $40,000.00 Post 1.00 1.00 2.00 10.00 14.00 Fee Construction Total Hours Post Structural $180.00 $4,950.00 $220.00 $1,050.00 $6,400.00 Fee CA 1.00 33.00 2.00 10.00 46.00 Hours CA $360.00 $9,900.00 $440.00 $2,100.00 $12,800.00 Fee CD Hours 2.00 66.00 4.00 20.00 CD $0.00 $6,450.00 $0.00 $3,150.00 $9,600.00 Fee DD Hours 0.00 43.00 0.00 30.00 73.00 DD $180.00 $6,000.00 $1,320.00 $2,100.00 $9,600.00 Fee SD Hours 1.00 40.00 12.00 20.00 73.00 SD Fee $0.00 $0.00 $0.00 $0.00 $0.00 Programming 0.00 0.00 0.00 0.00 0.00 Programming Hours Rate $180.00 $150.00 $110.00 $105.00 Totals Hourly Phase Summary Fee Engineer Designer Drafter Structural Principal Senior Project Senior EXHIBIT ‘C’: Record Drawing Procedures Introduction These guidelines are issued to promote the development of electronic drawings suitable for use in the Maricopa County Facilities Management Department CAD environment. Consistency and compatibility with existing Maricopa County documents can only be achieved when these standards are strictly adhered to. Electronic drawings produced and submitted in accordance with these standards have significantly greater value to Maricopa County. Design Professionals (DP), their Sub-consultants, CMR's delivering documentation to Maricopa County must ensure these standards are reviewed, understood and followed by those people responsible for preparing electronic drawings. Renovations and Space Change Projects Requirements For typical Renovation and Space Planning projects, the DP is responsible for submitting a complete set of Construction Documents (CDs) to Maricopa County prior to the beginning of construction. Upon completion of construction, CMRs are responsible for submitting complete As-Built documentation (per definitions included in the Agreement Between The County of Maricopa, Arizona and Design Professional) to the Owner (in both electronic and hardcopy formats) and DP is responsible for submitting the Record Drawings to the Owner based on this As-Built documentation. Construction Documents and Record Drawings submitted to the Owner need to adhere the criteria outlined in this document. All “DWG” files and AutoCAD drawing entities submitted at the end of a project must be able to be manipulated using standard AutoCAD drafting procedures. Non-compliance with this policy may result in the rejection of AutoCAD files submitted at project closeout, in addition to delayed rendering of final project payment. “DXF” files will not be accepted at project closeout as a substitution for “DWG” AutoCAD file deliverables. Projects using Building Information Modeling (BIM) software are still required to submit “DWG” formats for their projects. Electronic File Format CAD drawings must be submitted in full compliance with AutoCAD software 2007 drawing file format (file extension = .DWG). All Construction and Record Document project drawings must be submitted to Maricopa County Facilities Management Department in all file formats listed below; other formats are not acceptable without the prior consent of Maricopa County Facilities Management Department. • AutoCAD® 2007 or higher – DWG format only. • Adobe® PDF version 6.0 or higher. Scale, Units, Coordinate System and Orientation AutoCAD drawings should be drafted at full scale in architectural or engineering units, such that one drawing unit equals one inch. The User Coordinate System (UCS) for all AutoCAD drawings should be set to “World”. Tolerances When projects require creation of new AutoCAD floor plans from field measurements, exterior building dimensions should reconcile to within one (1) inch of actual building dimensions as measured in the field. Interior building dimensions must reconcile to within half (1/2) inch of actual field dimensions. However, individual project requirements may vary. Please confirm requirements with the Project Manager designated by Maricopa County. Blocks The following rules must be employed when handling block entities: 1. All entities within a block must be created on layer 0. Durango Juvenile Courts Demolition Page | 39 CMR Professional Services Contract Serial # 260056-ROQ 2. Drawing entities translated into AutoCAD blocks from non-AutoCAD systems must revert to layer 0 when exploded within AutoCAD. Policy on External Reference Files (XREFs) Maricopa County will not accept the submission of any AutoCAD drawing deliverable which contains unbound references to external source drawing files. All externally referenced data sources that were used during the AutoCAD drawing production phase should be incorporated as a block within a single drawing file, including the title block and all identifying information visible in the printed image, upon project completion and prior to submission to Maricopa County. Layers contained in XREF’s inserted as blocks should conform to Maricopa County guidelines. The resulting self-contained drawing file is an acceptable deliverable to Maricopa County. Owner Supplied CAD Files Prior to commencement of design and construction services, Maricopa County will provide past Record Drawings in AutoCAD per the Contract Agreement that can be used as the background for space documentation projects. These have been generated using a variety of methods and may require field verification. When no pre-existing Record Drawings in AutoCAD are available, consultants will be required to produce drawings entirely from field measurements. AutoCAD files are transmitted for the convenience and expediency of the DP, their Sub-consultants and the CMR but bear no implicit or explicit guarantee of accuracy, reliability or correctness”. It is recommended to all recipients of Owner-supplied drawing files to perform their own verifications as necessary to develop drawings for each phase of the project. Layers for CAD Files All AutoCAD Files shall include but not be limited to the following building features that define the physical boundaries necessary to define space, such as: 1) exterior walls; 2) vertical elevations & sections; 3) details; 4) schedules; 5) doors; 6) glazing; 7) elevator shafts; 8) stair wells and other changes in floor elevation; 9) built-in furniture and/or modular systems. The DP, their Sub-consultants and the CMR shall adhere to these layer standards as much as possible, although additional layers, conforming to standard formats, may be necessary, while some layers may not be applicable to every space documentation project (furniture, roof lines, etc.). AutoCAD layers should be named in accordance with the latest U.S. National CAD Standard (NCS) which can be obtained from the National Institute of Building Sciences. Custom layers added by Maricopa County begin with MC-. The specific name of custom layers may vary slightly by Maricopa County owner. AIA CAD Layer Guidelines See U.S. National CAD Standard Version 3 (attached). USE OF BUILDING INFORMATION MODELING (BIM) Although projects may utilize Building Information Modeling (BIM) for conveying three-dimensional design, two-dimensional deliverables are still required as outlined in this guideline and as specified in Maricopa County Agreements with the DP, their Sub-consultants and CMRs. BIM Execution Plan Projects utilizing BIM are required to provide a BIM Execution Plan to document modeling practices. This document declares what is being modeled, the accuracy of the models, the intent of the models, and how project teams work within the models. BIM Standards Modeling practices and standards should be declared and agreed upon in the Project’s BIM Execution Plan. BIM Models and Deliverables Durango Juvenile Courts Demolition Page | 40 CMR Professional Services Contract Serial # 260056-ROQ Models turned over to Maricopa County as a deliverable must meet the requirements of the agreed upon BIM Execution Plan. Use of Revit Models are to be created in the most current version of Autodesk Revit. Modeling practices are to be declared in the project’s BIM Execution Plan. Durango Juvenile Courts Demolition Page | 41 CMR Professional Services Contract Serial # 260056-ROQ