Staff Memo to Council

City of Apache Junction — Work Study (2026-10-05)

View PDF Meeting page

Extracted text (via tesseract_tsv) 2614 characters
City of Apache Junction
Home of the Superstition Mountains
DATE: SEPTEMBER 23, 2026
TO: MAYOR AND CITY COUNCIL MEMBERS
THROUGH: BRYANT POWELL, CITY MANAGER
FROM: TRINA HARRISON, CIP PROGRAM MANAGER
SUBJECT: AGREEMENT FOR CITY SERVICES EXPANSION CONSTRUCTION MANAGER AT
RISK (CMAR) PRECONSTRUCTION SERVICES
Executive Summary
Staff respectfully requests approval to enter into an agreement with Willmeng
Construction Inc. to provide preconstruction design assistance for the City Services
Expansion project at Ironwood and Horton Drive. This project delivers multiple new
community assets, including a police substation, branch library, community park and
lake, and a park maintenance building and yard. Contractor involvement at this stage
will help ensure the design remains aligned with budget, schedule, and constructability
goals.
Background
The project site lies within the 6,600 acres annexed in October 2021 as part of the
Superstition Vistas area. Under the development agreement, D.R. Horton conveyed the
22-acre parcel to the City of Apache Junction for future municipal use. This
conveyance reduces the overall project cost expenditures by an estimated $7 million.
On August 20, 2026, Willmeng Construction Inc. was selected through a Request for
Qualifications process to support the City and its architectural and engineering team
throughout the design phase. With the master plan complete and the design team
under contract, the project is ready to advance into preparation of construction
documenis. This phase requires approval of a defined scope of work, schedule, and
fee. This preconstruction agreement is the first of at least two anticipated contracts;
additional smaller contracts may be needed for procurement of long-lead items to
maintain schedule once construction begins.

Analysis and Recommendation
Staff recommends approval of the preconstruction contract with Willmeng Construction
Inc. in an amount not to exceed $463,734, including allowances. This fee reflects
Willmeng’s involvement in design coordination, constructability review, cost estimating,
and materials and methods evaluation. Their participation will helo ensure the police
substation, branch library, maintenance building, and shared yard remain within
budget, and that the community park, lake, parking, and supporting infrastructure are
designed cohesively as one unified site. Staff recommends approval to maintain
project momentum and reduce cost and schedule risks.
Next Steps
This contract will be placed on the consent agenda for the October 20'h City Council
Meeting, unless otherwise directed by City Council.