CMAR PRECONSTRUCTION SERVICES
AGREEMENT
City Services Expansion Project
October 5, 2026

Purpose
• Present the contract for preconstruction
services to support the design of the City
Services Expansion project at Ironwood &
Horton Drive.

Project Location

Project Description
• Preconstruction Services:
Police Substation
Branch Library
Maintenance Building & Yard
Associated site parking, landscaping, irrigation, and
hardscape
Off-site improvements
Park and Fishing Lake

Scope of Work
• Actively attend design meetings.
• Review all plans/concept ideas and provide
constructability input.
• Provide value engineering/provide estimates at
each milestone to ensure project remains on
budget.
• Develop construction phasing plans.
• Assist City in coordination with utility companies.
• Identify and procure long-lead items.

Solicitation
• June 18, 2026 Request for Qualifications 26-04
Released
• June 29, 2026 Presubmittal Meeting
• July 20, 2026 Statements of Qualification (SOQ)
Due
• Received 12 SOQ’s
• August 17 & 18, 2026 Interviews (5)
• Chasse Team Building, CORE Construction, FCI
Constructors Inc, Okland Construction, Willmeng
Construction Inc

Solicitation
• August 19, 2026 Selection Committee
• Willmeng Construction, Inc
• A.R.S. Title 34 based on qualifications, not price
• Arizona based company
• 200+ Municipal and Public Safety Projects
• City of Mesa Gateway Library
• City of Buckeye 911 Communications Center
• City of Mesa Police Property and Evidence Facility
• City of Surprise Police Substation No. 1

Total Estimated Project

Next Steps
• Staff recommends approval of the contract in the
amount of $463,734 with Willmeng Construction,
Inc.
• Contract will be placed on the October 20, 2026
City Council Meeting consent agenda, unless
otherwise directed by City Council.
• Upcoming
• Fall 2027 – Construction Contract