Administration Building
The current Administration Building is functionally inefficient and in need of updating. The project will
renovate and refresh approximately 280,000 SF of office, lobby, conference room space, and reconfigure
space vacated by the County Attorney who will be relocated to 225 W. Madison when construction is
complete. Renovation work will occur on all floors of the Administration Building. Offsite departments that
offer permitting services will be moved into the building to provide a centralized location for the public's
needs.
East Valley Animal Care & Control Facility
The Animal Care and Control project in the East Valley will replace the current shelter located in Mesa.
The structure will be constructed on the current site of the PNI Warehouse after demolition of the existing
warehouse. The new shelter will offer an interior area of 42,330 SF and covered exterior area of 20,610
SF. The existing facility will be closed after opening of the new building. Areas include space for the
public, admissions, sheltering, shelter support, veterinary, field operations, utility, and administration staff.
Funding continues this project which began in FY 2019
MCSO Substation at Avondale Campus
The project includes the construction of a new Maricopa County Sheriff's Office (MCSO) substation with
space for Environmental Services and Equipment Services. The new facility will be 26,000 SF substation
and house MCSO, Environmental Services, and Equipment Services. Environmental Services will be
relocated from leased space eliminating the monthly lease costs. The new facility will be built on the
Avondale campus that neighbors the new Equipment Services vehicle repair shop and fueling stations.
The site is the vacant land north of the existing Southwest Regional Justice Center. The existing structure
will either be demolished or put up for sale.
Southeast Regional Justice Center at Mesa
The project will be for the construction of a new consolidated Justice Court and Adult Probation facility to
house both departments. The total building will be 106,000 SF with 61,000 SF dedicated to Courts and
45,000 SF committed to Adult Probation. Funding continues this project which began in FY 2019.

Project FY 2020 FY 2021 Total
301 ‐ Administration Building Renovation 58,900,000 58,900,000
East Valley Animal Care and Control Facility 4,376,921 18,523,079 22,900,000
MCSO Substation at Avondale Campus 21,000,000 21,000,000
Southeast Regional Justice Center at Mesa 4,000,000 47,641,833 51,641,833
Total 29,376,921 125,064,912 154,441,833
Proposed debt issuance 140,000,000
Cash to be covered in FY 2021 14,441,833