CONSULTANT CHANGE ORDER - DOS APPROVAL
IViaricopa County Department of Transportation
Change Order Number: 4 _
Date: 411012018 Amount: $ 1,698,721.46 Agenda Item No.1 ,
Contract No: 2016.039 .Work Order Not I 710339
Consultant Name:( HDR Engineering, Inc
Project Name:I Gilbert Road Bridge at the Salt River
Initial Amount:) $2,688,144.44 Contract Award Date: 7/27/2016 Total Prior Change Orders: $308,670.38
By mutual agreement of the parties, the following contract change(s) are Incorporated into the above-Identiiied contract. All other contract terms and conditions
remain unchanged.
Change OrderNo. 4 shall increase the contract amount an additional $1,698,721.45 for a revised contract total of $4,786,536.27. This chan ge
cutler includes extendin g the main Gilbert Road Bridge from 1,445 feet to 3,685 feet; adding a new 450 foot bridge "Northern Reliever Bridge";
preparing new 60% plans, specifications, and cost estimate; additional effort to complete 95%, 100% sealed submittals with new project
definition; and providing Post Design services. All work shall be performed pursuant to the attached Scope of Services.
With this Change Order, the total amount of this contract has increased 55%.
By reason of this change 1547 days extension of time will be allowed. a5v, r 2
With inclusion of this change, this contract has a revised cumulative performance period of,20artfays.
The contract completion date is: August 3, 2023.
The following financial Information is submitted:
Initial Contract Amount $ 2,688,144.44
Amended Contract Amount w/ previous change orders $ 3,087,814.82
Current Change Order Request $ 1,698,721.45
Amended Contract Amount IV current change order $ 4,786,536,27
We, the undersigned Consultant, do hereby agree that upon execution of this Change Order that we will perform all work as identified above, end as may be described in
attach rn ent(s) and M./accept Ike above speetffed amount(s) as full payment thereof.
IN WITNESS E" the parties herein have executed this Contract Change Order:
Principal (Signature) Federal Tax ID Number: — 6( . 0 St. q
Printed Narrr • , ../ /-2
-1-111e:.44.,--,
Date:
CITY of APPROVAL
I certify that this change is required for this contract.
Project Manager: Date: , *
.. • • . ,
MARICOPA COUNTY DEPARTMENT OF TRANSPORTATION
certify that this change is required for this contract
./7
/
Praise M nager - ill Hahn Date Branch ( .na er-Ra d se Date
I cenq i a . re aval .13)6f, .... Ish this C nage Order
'''7/10 ..t Iiii5di
CIP Cash Flow M sager- Chuck Williams Date Division Manager- Nis, ITS 8,1 : ' Date
Hy that this cha sge Is within the limits authorized by the Maricopa f
nty Prer ureme ' lade
...4 ' It/ reifie
Article 5 C tracts 0 car ind Slaughter Date
COUNTY APPROVAL
RECOMMENDED_BY'_ ACCEPTED AND APPROVED:
,------ -
,—\,--- 4 (I 8 ZO ) 9)
Jennifer TOth, 11 .E, Date Chairman, Board of Supervisors Date
I
Transpo atVIrector/County Engineer
ATTEST:
LEGAL REVIEW
Approved as to form and within the powers and authority granted under the
laws of the State of Arizona to the Maricopa County Department of Clerk of the Board Date ,
Transportation.
Deputy County Counsel Date
Distribution: Originals- Consultant, Contracts Branch, Clerk of the Board Copies- Finance, Project Manager, Clly Partner (if applIcabie)
Revised 4111312018

Scope o ervices el
oad Bridge. at the: River
Chang .: Order No.. 4 for Final Dolga
Gilbert Road Bridge at the Salt River
Consultant: HDR Engineering
Project No: TT0339
Contract No.: 2015-039
Maricopa County
Department of Transportation
2901 W. Durango Street
Phoenix, AZ 85009
April 2018

Scope of Services
Project Specific
SCOPE OF SERVICES Table of Contents
Project Overview —PROJECT SPECIFIC
Project Location 3
3
Project Background 3
Project Purpose 3
Length of Services 3
100.3.3 Matrix of Responsibilities 4
100.3.4 Matrix of Deliverables 4
100.3.5 Communication Plan 5
200 Project Management, Meetings, and Coordination 5
200.1 Project Management 6
200.2 Progress/Coordination Meetings 6
300 Revised 60% Design Plans, Specifications, 6
300.1 Civil and Cost Estimate
300.2 Drainage 6
300.3 Structural 6
300.4 8
Geotechnical 11
400 Northern Reliever Bridge 14
400.1 Northern Reliever Bridge — Phase 1 16
400.2 Northern Reliever Bridge—Phase 2 16
400.3 Geotechnieal 17
500 Updated Cost Risk Assessment 18
500.1 CRA Workshop 18
600 Updated Technical Reports 18
600.1 Drainage Report 18
600.2 Scour Report 18
600.3 Geotechnical Report 18
700 Miscellaneous 18
700.1 Additional Alternative Analysis Memorandum 20
800 Post Design_ Services 20
800.1 Construction Phase Services 20
800.2 SRP Construction Phase Services 20
800.3 Letter Of Map Revision (LOMR) 21
1200.1 Project Submittals 22
List of Tables 22
Table 1 — Matrix of Responsibilities
Table 2 — Matrix of Deliverables
Table 3 — Contact Table 4
4
Appendices 5
Appendix A — ..12 Engineering
Appendix B — YE Fuller
Appendix C — Terracon
Appendix D — Lee Engineering
Project No.: 1T0339
Revised: April 2018 Contract No.: 2015-039
Page 2 of 22

Scope of Services
Project Specific
SCOPE OF SERVICES - PROJECT SPECIFIC
Project Overview
Project Location
The project will reconstruct Gilbert Road between Thomas Road and SR 87 (Beeline Highway) in
Maricopa County to provide an all-weather roadway over the Salt River and connection to SR 87.
Project Background
This change order accounts for the following scope items:
I. Extending the main Gilbert Road Bridge from 1,445 feet to 3,685 feet.
2. Adding a new 450 foot bridge "Northern Reliever Bridge".
3. Preparing new 60% Plans, Specifications, and Cost Estimate.
4. Additional effort to complete 95%, 100%, and Sealed submittals with new project definition.
5. Providing Post Design services.
Project Purpose
The purpose of the change order is as follows:
1. After completing additional hydraulic analysis, utilizing 2-D modeling (Change Order #3),
11DR developed numerous alternatives which focused on key objectives of not worsening
flooding of properties outside of the ROW, including along Roma Ave during a 100-year storm
event and keeping all proposed improvement within ROW. After considering all of the
information, MCDOT and project stakeholders selected an alternative (Alternative 3A) which
extended the main Gilbert Road Bridge over the Salt River from 1,445 feet to 3,685 feet. This
extension results in the northern abutment moving further to the north. The southern abutment
will remain in the same location as previously identified and the horizontal alignment will
remain the same.
1 As part of Alternative 3A, it was determined that a new bridge structure is needed
approximately 2,000 feet north of the main Gilbert Road Bridge. This new bridge "Northern
Reliever Bridge" allows for the conveyance of various flood water that is "pushed" up towards
Roma Avenue during a 100-year storm event to drain underneath Gilbert Road rather than
perpetuate flooding of the areas along Roma Avenue. Based on the analysis, a proposed bridge
(or equivalent hydraulic structure) with an opening length of 450 feet is needed to provide
adequate relief drainage.
3. With the changes to the main bridge, the addition of a completely new bridge structure, and the
associated changes with the roadway profile to accommodate these changes, a new 60% design
plan submittal is required. The critical path for this project is getting the Conditional Letter of
Map Revision (CLOMR) submitted and approved. The scope changes associated with
Alternative 3A directly impact the evaluation current design package and the CLOMR thus
requiring a completely new 60% submittal.
4. With the additional length of the main Gilbert Road Bridge and the new Northern Reliever
Bridge, additional efforts will be required in developing the 95%, 100%, and Sealed project
submittals as a function of the increase infrastructure and projects over design complexity.
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 3 of 22

Scope of Services
Project Specific
5. The roadway will be designed to provide an all-weather river
Profile to retain the 100-year river water surface crossing by designing the roadway
the upstream side of Gilbert Road. elevation below the roadway subgrade along
6. The original Scope of Work did not include Post Design services
has requested that this change order provide for Post Design during construction. MCDOT
Letter of Map Revision (LOMR) services as well as preparing the
documentation.
7. These scope changes are in addition to the original scope and previous
change orders .
Length of Services
Services will last the duration of design services schedule, and
estimated to be June 2023. throughout post design services,
100.3.3 Matrix of Responsibilities
Table 1 — Matrix of Responsibilities
Scope.
Section Description Consultant McDCIT _ OTHER OTHER OTHER - OTHER
200.1 Project Management • (.12) . CIE Fuller) , Terracon) (lee)
X
200.2 Progress/Coordination
Meetings X X X X
300.1 Civil X
300.2 Drainage X
300.3 Structural X X
X
300.4 Geotechnical X
400.1 Northern Reliever Bridge
- Phase 1 X
400.2 Northern Reliever Bridge
- Phase 2 X
500.1 CRA Workshop X X
600.1 Drainage Report X X
600.2 Scour Report X X X
600.3 Geotechnical Report X X
X
700.1 Additional Alternative X X
Analysis Memorandum X
Post Design —
800.1 Construction Phase X X
Services X
Post Design — SRP
800.2 Construction Phase X X
Services
800.3 Letter of Map Revision
(LOMR) X
Project No.: TT0339
Revised: April 2018 Contract No.: 2015-039
Page 4 of 22

Scope of Services
Project Specific
100.3.4 Matrix of Deliverables
Table 2 — Matrix of Deliverables
:.:Design Phase .
Item Deliverable 0,,A;i 95%. .100% Sealed
Design Design - . Design :Design
60% Submittal
Civil Plans Plans P D F S
Drainage Plans Plans P D F s
Bridge Plans—Main Bridge Plans P D F s
Bridge Plans — Reliever Bridge Plans P D F s
Traffic Plans Plans P D F s
MOT/Const. Sequence Plans Plans P D F s
Signage Plans Plans P 0 F s
SRP Waterline Plans Plans P D r s
Specifications Document P 0 F S
Cost Estimate Document P D F F
Hydraulic Report Report D D F S
Scour Report Report D D F s
Geotechnical Report Report 1) D F s
Final Bridge Selection Report Report 0 0 F s
Construction Schedule Document P D F F
100.3.5 Communication Plan
Table 3 — Contact Table
Nanne Roie gency Phone NUMber Email Address
Bill Hahn Project Manager MCDOT 602-506-4611 billhahn@mail.maricopa.gov
Scott Sikel Designer Consultant 602-522-4348 scott.sikel@hdrinc.com
(HDR) Project Manager
Jason Nauman Bridge Design Consultant 602-522-7708 jason.nauman@hdrinc.com
(HDR) Lead
Mark Fountain Drainage Design Consultant 602-522-7762 mark.fountain@hdrinc.com
(HDR) Lead
Ray Carranza Roadway Design Consultant 602-522-7722 raymond.carranza@hdrinc.com
(HDR) Lead
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 5 of 22

Scope of Services
Project Specific
200 Project Management, Meetings, and Coordination
200.1 Project Management
Due to the extension of the project schedule and with providing a revised 60% design plan submittal,
time has been included for the HDR project manager to manage the project, develop and regularly
review and update the design schedule, regularly review the design budget, monitor and control the
project progress, schedule and budget, and to develop invoices.
200.2 Progress/Coordination Meetings
Time has been included to prepare for, write agendas, attend meetings, travel to and from meetings and
document and distribute meeting notes for the project coordination meetings listed included in this task.
Time has been included to participate in additional agency and stakeholder coordination meeting to
share the findings and recommendations of this project. Additional time has been added to support
public outreach and public meetings to obtain community approval for the recommended alternatives.
In conjunction with mcDoT, HDR will hold approximately six (6) additional monthly progress
meetings where all stakeholders will be invited and project progress, issues and direction will be
discussed and documented. Time is also included for a new 60% comment resolution meeting.
300 Revised 60% Design Plans, Specifications, and Cost Estimate
Due to the significant level of change to the scope of the project, primarily more than doubling of the
main Gilbert Road Bridge and the addition of the new Northern Reliever Bridge, located slightly south
of Roma Avenue, a new 60% design plan submittal is required. While certain elements of the previous
60% submittal (submitted July 19, 2017) can be resubmitted without modification, the majority of plans
require re-work. A description of the modifications for each discipline are detail below.
300.1 Civil
This task consists of civil design efforts associated with updating the roadway layout, performing
additional design associated with the change in the bridge layout, performing additional design
associated with the addition of the northern reliever bridge, revising the drawings that were included in
the original 60% submittal, and resubmitting the 60% submittal. Unless noted herein, the scope
provisions for the civil final design and development of plans included in the original contract still
apply. This includes design specifications, design guidelines, construction specifications, and submittal
requirements.
The roadway design will follow the current MCDOT Roadway Design Manual, standards and
guidelines and utilize current MAG and MCDOT standard details as much as practical. Roadway cross
sections will be prepared at appropriate locations to provide accurate earthwork calculations at regular
intervals along the alignment. The design will rely on the topographic surveys, mapping and digital
terrain models (DTM) provided by MCDOT. The roadway will be designed using InRoads software.
Earthwork will be calculated using the average end area method.
The following is assumed for the new civil layout: (1) the roadway profile grade will be changed,
resulting in modifications to geometry; (2) roadway design coordination with other technical disciplines
is required to account for the extend bridge and the new reliever bridge; (3) the location of the south
abutment of the main Gilbert Road Bridge will remain unchanged; (4) the east maintenance road will be
combined with the drainage ditch/channel to reduce impacts to existing right-of-way; (5) maintenance
of traffic and construction sequence plans will need to be revised to account for the extended bridge and
the new reliever bridge.
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 6 of 22

Scope of Services
Project Specific
The following list of civil drawings identifies the existing drawings included as part of the original
scope of work (for the bridge length included in the original 60% submittal). For the existing drawings,
the list notes which drawings are assumed to required revisions and which drawings will not require
revisions.
Original New
Drawing Name # of CO 4 Revision
Drawings Drawings
Face Sheet 1 Revise key map to reflect extended
bridge and new reliever bridge.
General Notes, Design Data, Index 1 No revisions.
Quantity Summary Sheet 6 Revise six sheets to reflect updated
quantities, increase in materials.
Revise section layout and station limits
Typical Sections 3 for two sheets to reflect new bridge limits
and reconfiguration of the drainage
channels.
Revise geometric layout and callouts for
four sheets to reflect maintenance road
Geometric Control Sheets 4 re-alignment and any potential re-
alignment to the mainline construction
centerline.
Revise limits and callouts for two sheets
on the north end of the project to reflect
Roadway Removal Sheets 10 the change in construction limits due to
the new profile.
Revise design layout, callouts, profile,
and coordination with drainage design
Roadway Plan & Profile Sheets 20 layout for 20 sheets to reflect the new
profile (for 100-yr at subgrade), extended
bridge, reliever bridge, and drainage
improvements.
Revise the centerline geometry for six
sheets to reflect reconfiguration of the
Maintenance Road Profile Sheets 6 east maintenance road to be incorporated
with the east drainage channel and for the
west maintenance road to accommodate
the revised drainage basins.
Roadway Detail Sheets 4 No revisions.
TCE Details 1 Revise TCE locations due to extended
bridge.
Revise staking elevations for two sheets
Intersection Layout Detail Sheets 2 to reflect new profile, including revision
for Roma Ave.
Revise design layout, construction limits,
MOT/Construction Sequence Phase 1 2 and phases for two sheets to reflect
extend bridge limits.
Revise design layout, construction limits,
MOT/Construction Sequence Phase 2 2 and phases for two sheets to reflect new
relief bridge.
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 7 of 22

Scope of Services
Project Specific
Revise design layout and profile for two
Plan and Profile Detours Phase 1 3 sheets to reflect construction of the new
reliever bridge.
Signing/Marking Face Cover Sheet 1 Revise key map to reflect extended
bridge and new reliever bridge.
Signing/Marking Quantity Summary 3 Revise quantities for 3 sheets to reflect
Sheet extended bridge and new relief bridge.
Sign Format Sheet 1 No revisions.
Revise design layout and callouts for 3
Signing/Marking Plan Sheet 10 sheets to reflect extended bridge and new
reliever bridge.
Mass Diagram Sheet 1 Revise sheet to reflect new profile.
Total 80 0
300.2 Drainage
300.2.1 Hydrologic and Hydraulic Modeling
This task is comprised of the efforts related to the Hydrologic and Hydraulic modeling
associated with the new project configuration. The two-dimensional modeling previously
performed allowed for the recommendation of lengthening the main Gilbert Road bridge and
adding a new northern reliever bridge. With this direction, new one-dimensional modeling is
now required to be performed for submission to FEMA and for developing of the revised
Drainage Report. The majority of work associated with the original 1D modeling was
performed and completed as part of the original 60% submittal. With the new project
configuration, a large portion of the hydrologic and hydraulic modeling will recreated. The
following describes the detail of this work.
Drainage design shall be in accordance with the Drainage Policies and Standards for Maricopa
County, Arizona. Hydrology, hydraulics, and erosion control designs shall be consistent with
the current Drainage Design Manual issued by the Flood Control District of Maricopa County.
Both on and off site drainage design shall be in accordance with the Drainage Policies and
Standards for Maricopa County, Arizona. Hydrology, hydraulics, and erosion control designs
shall be consistent with the current Drainage Design Manual issued by the Flood Control
District of Maricopa County. The bridge and other pertinent apertures conveying the regulatory
floodwaters will be designed to be compliant with 44 CFR 60.3 and local floodplain ordinances
with regards to acceptable impacts to the floodway and floodplain water surface elevations.
Onsite
On site study limits are defined as the area along the Gilbert Road alignment (existing and
proposed) between Thomas Road and SR 87 (Beeline Highway) extending to the edge of right
of way limits.
The on site drainage and storm water pollution prevention plan (SWPPP) design will follow the
current MCDOT standards and guidelines and utilize current MAG and MCDOT standard
details. Where MCDOT and MAG standards do not address specific criteria or issues the
CONSULTANT (.12) will follow additional pertinent standards. Additional pertinent standards
include ADOT, FCDMC, FHWA, and SRPMIC.
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 8 of 22

Scope of Services
Project Specific
The Rational Equation shall be utilized for hydrologic analyses. The rainfall intensity shall be
based on the 10-year 10-minute storm utilizing current NOAA Atlas 14 precipitation intensities
and depths. Cross drainage facilities shall be designed for the 50-year storm event. The design
will rely on the topographic surveys, mapping and digital terrain models (DTM) provided by
MCDOT.
See CONSULTANT (J2) Scope for further details on criteria, analysis, and project deliverables.
Offsite
Off site study limits will be defined as extending from approximately 5 miles downstream of the
existing Gilbert Road alignment (Alma School Bridge) to 5 miles upstream of the alignment
near Granite Reef Dam..
Additional offsite analysis will include stormwater discharge determined to be an impact to the
Gilbert Road alignment (existing and proposed) as defined within the project limits of this scope
of work. Roadway Cross drainage facilities shall be designed for the 50- year storm event.
The off site drainage design will follow the current MCDOT standards and guidelines and
utilize current MAG and MCDOT standard details. Where MCDOT and MAG standards do not
address specific criteria or issues the CONSULTANT (J2) will follow additional pertinent
standards as directed by UDR. Additional pertinent standards include ADOT, FCDMC, FHWA,
and SRPMIC.
111)R will verify the assumptions made by the sub consultant in regards to design discharge
values to be utilized for the Salt River crossing. The values shall be based on the Post-
Roosevelt discharges developed by the U.S. Army Corps of Engineers. These values have been
utilized for design of the Salt River improvements through the metropolitan Phoenix area.
See CONSULTANT (12) Scope for further details on criteria, analysis, and project deliverables.
Drainage plans are to be accompanied by a sealed drainage report when submitted to MCDOT
for review. The drainage report will be comprehensive and include applicable: hydrology and
hydraulic calculations, documented computer modeling, maps, and other supporting data and
analyses.
Quality Assurance
HDR shall provide independent Quality Assurance for the all hydrologic and hydraulic analysis,
modeling approaches, computations, and associated work products prepared by the teaming
partner. Hydrology will be reviewed with respect to the Drainage Design Manual for Maricopa
County, as prepared by the Flood Control District of Maricopa County, release date 2013.
Hydraulics will be reviewed with respect to the Drainage Design Manual for Maricopa County,
as prepared by the Flood Control District of Maricopa County, release date 2013 along with
MCDOT Roadway Design Manual, Section 4, Update 2016.
300.2.2 Scour Evaluation
Similar to the hydraulic modeling, this task is comprised of the efforts related to the Scour
Evaluation associated with the new project configuration, and the new mapping. The majority
of work associated with this original task was performed and completed as part of the original
60% submittal. With the new project configuration, and the new mapping, the scour evaluation
will need to be reassessed. The following describes the detail of this work.
Proj ect No.: IT0339 Contract No.: 2015-039
Revised: April 2018 Page 9 of 22

Scope of Services
Project Specific
The scour assessment and revetment design will follow the current industry standards and
guidelines and utilize current MAO and mcDur standard details. Where MCDOT and MAO
standards do not address specific criteria or issues the CONSULTANT (JE Fuller) will follow
additional pertinent standards as directed by HDR. Additional pertinent standards include
AD 01, FCDMC, FHWA, and SRFMIC.
See CONSULTANT (JE Fuller) Scope for further details on criteria, analysis, and project
deliverables
Quality Assurance
HDR shall provide independent Quality Assurance for the scour computations and associated
revetment and scour protection design plans prepared by subconsultant. Detailed review of
scour assumptions, engineering approach, countermeasure design, conveyance features,
identification of potential impacts to right-of-way, and effects on the Salt River hydraulics will
be conducted. Scour and erosion control will be reviewed with respect to Chapter 11 of the —
Hydraulic Drainage Design Manual for Maricopa County, as prepared by the Flood Control
District of Maricopa County, release date 2013.
300.2.3 Drainage Meetings and Project Coordination
HDR shall conduct regular internal drainage coordination meetings to support project status and
action item reviews. HDR shall conduct weekly coordination calls and meetings with both J2
and JE Fuller, facilitate the exchange of information and approach between the drainage team,
identifying any challenges, opportunities, or recommendations with respect to the drainage
evaluation and associated design components. All drainage meetings and team conference calls
shall be documented as formal meetings using HDR standard templates. Standalone discussions
with the subconsultant teams, members of the team, or other will be necessary during this
project. A brief record of the discussion, the parties involved, and key notes will be documented
and added to project tracking with HDR standard templates.
HDR Drainage Lead shall participate in public meeting and stakeholder outreach in support of
communications with MCDOT for proactive messaging of project findings and
recommendations of potential FEMA outcomes.
300.2.4 Drainage Construction Plans (Revised 60%)
HDR shall facilitate the coordination and development of the construction plans, details, and
specification for the design package of the Revised 60% review of the project. The HDR
drainage lead shall be involved in ongoing discussions and review of plan components to
support the early identification of potential conflicts or challenges.
300.2.5 Conditional Letter of Map Revision
Based on the new project configuration, the Conditional Letter of Map Revision (CLOMR) will
require significantly more effort and coordination with Flood Control District of Maricopa
County (FCDMC), FEMA, and MCDOT than was originally scoped for the project.
In order to assist with the FEMA review and approval process, an in-person meeting with the
assigned FEMA reviewer is proposed. The purpose of this meeting is to provide a detailed
explanation of the project, the special conditions associated with the CLOMR, and to answer
questions early to prevent a project review stall out. The location of this meeting will not be
known until FEMA has assigned the case to a specific review. It is anticipated that the meeting
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 10 of 22

Scope of Services
Project Specific
will require travel out of state. This scope provides for travel, including airfare, with per diem.
For two I-LDR staff and one representative from subconsultant J2. Additional representation
from MCDOT and FCDMC will be required as well. This scope and budget does not include
recovery costs for mcDorr and FCDMC, it is understood those services will be funded
separately by others.
300.3 Structural
300.3.1 Bridge Final Design and Plans
The layout of the Main River Bridge will be revised from nine spans to an assumed layout of
twenty-three spans. This task consists of bridge design efforts associated with updating the
bridge layout, performing additional design associated with the change in the bridge layout,
revising the drawings that were included in the original 60% submittal, generating new
drawings required for the new bridge layout, and resubmitting the 60% submittal. Unless noted
herein, the scope provisions for the bridge final design and development of plans included in the
original contract still apply. This includes design specifications, design guidelines, construction
specifications, and submittal requirements. Contrary to the scope of work in the original
contract, but as shown in the original 60% submittal, the bridge will consist of a precast
concrete Bulb Tee girder superstructure supported on 2-column piers founded on drilled shafts.
Due to the possibility that the hydraulic design conditions (i.e. flow, velocity, scour, etc.) for the
north half of the proposed bridge may not be as severe, and that designing to meet these
conditions will reduce cost, it is assumed that a new/separate pier design is included.
The following is assumed for the new twenty-three span bridge layout:
(1) An updated Bridge Selection Report will not be required;
(2) The bridge horizontal alignment and skew of the piers and abutments will match
the original 60% submittal;
(3) The span lengths will match the original 60% submittal;
(4) The profile grade will be changed, resulting in modifications to geometry;
(5) The size and spacing of columns at all piers will not change and will match the
original 60% submittal;
(6) The size and depth of the pier drilled shafts for the spans included with the
original 60% submittal will not change;
(7) A new drilled shaft size and depth will be required for the piers within the
extended limits of the bridge;
(8) The size and spacing of the drilled shafts at Abutment 1(south end) will remain
unchanged;
(9) The size and spacing of the drilled shafts at the new Abutment 2 (north end) will
match Abutment 1;
(10) The wing walls at both abutments will be similar in length as shown on the
original 60% plans, thus wing wall redesign will not be required. However,
during the original 60% design, it was determined that retaining walls will be
necessary beyond each abutment wing wall (not feasible to extend wing walls
past the slope catch point). The layout/design of these retaining walls (1 sheet) is
included with this change order since it was not included in the original scope of
work and fee proposal;
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 11 of 22

Scope of Services
Project Specific
(11) The new twenty-three span layout will consist of 7 three-span frames and 1 two-
span frame, thus requiring consideration of design and details for a two-span
frame (the original 60% submittal only consisted of three-span frames);
(12) A deck drainage system will not be required.
The following list of bridge drawings identifies the existing drawings included as part of the
original scope of work (for the bridge length included in the original 60% submittal) and new
drawings required for the new bridge layout. For the existing drawings, the list notes which
drawings are assumed to required revisions and which drawings will not require revisions.
Original New
Drawing Name # of CO .4 Revision
Drawings Drawings
General Plan, Typical Section & 1 Revise north end of General Plan and
Index Index to Bridge Sheets.
General Plan I New Sheet (for remaining spans that
didn't fit on previous sheet).
Revise quantities table for new bridge
General Notes And Quantities 1 length and additional drilled shaft size
for the northern piers.
Revise elevation view on both sheets
Bridge Plan & Elevation 2 due to revised profile and add two spans
to the second sheet.
Bridge Plan & Elevation 2 New Sheets (for remaining spans that
didn't fit on previous two sheets).
Existing Bridge Removal 2 No revisions.
ExcfBackfill Payment Limits 1 No revisions.
Foundation Layout 1 Revise north end of lower plan view.
Foundation Layout 2 New Sheets (for remaining spans that
didn't fit on previous sheet).
Revise Drilled Shaft Data Table, and
Drilled Shaft Details 1 changes to dimensions/reinforcing may
by necessary for the abutment shaft
details.
Drilled Shaft Details 1 New Sheet (for new shaft size for the
northern piers).
Abutment 1 Plan & Elevation 1 No revisions.
Revise geometry for new location
Abutment 2 Plan & Elevation I (ground elevation, cap elevation,
wingwall lengths, etc).
Abutment Details 2 No revisions.
Wing Wall Details 1 No revisions.
Retaining Wall 1 New Sheet
Pier Plan & Elevation 2 Revise tables and titles on both sheets;
revise pier geometry due to new profile.
Pier Details 1 Revise pier design and analysis model
(due to revised geometry).
Pier Details 1 New Sheet (for second pier design)
Revise span numbering for each girder
Girder Details 2 length; may need a third girder length
depending on where the 2-span frame is
located.
Project No.: TI0339 Contract No.: 2015-039
Revised: April 2018 Page 12 of 22

Scope of Services
Project Specific
Deck Plan 2 Revise second sheet to add one span.
Deck Plan 3 New Sheets (for remaining spans that
didn't fit onTrevious sheets).
Deck Section And Deck 4 Modify fourth sheet so deck sequence is
Reinforcing for a single 3-span frame.
Deck Section And Deck New Sheet (for longitudinal reinforcing
Reinforcing and deck sequence for 2-span frame).
Precast Deck Panel Details 4 Minor changes to span layout/callouts
on first sheet.
Abutment Diaphragm Details I No revisions.
Pier Diaphragm Details 2 Minor revisions to notes and titles on
both sheets.
Revise joint table on first sheet; check
Miscellaneous Details 3 bearing design (shown on third sheet)
for 2-span frame and revise as
necessary.
Aesthetic Details 2 No revisions.
New Sheet (for longer bridge railing and
Aesthetic Details 1 possibly a different layout for the 2-span
frame).
Camber Details 1 Revise deflection tables and account for
the 2-span frame.
Screed Elevations 2 Revise screed calculations due to new
profile and the 2-span frame.
Screed Elevation 3 New Sheets (for remaining spans that
didn't fit on previous two sheets).
TOTAL 40 16
300.3.2 Bridge Special Provisions and Cost Estimate
This task includes modifications to the 60% Special Provisions and cost estimates resulting
from the changed layout of the Main River Bridge. The remainder of the effort associated with
Special Provisions and the cost estimates is included in the original contract.
300.3.3 Bridge Coordination with Other Technical Disciplines
This task includes additional coordination resulting from changing the layout of the Main River
Bridge and resubmitting the 60% submittal. The coordination will be with other design team
and MCDOT discipline leads/contacts (Bridge, Roadway, Drainage, Traffic, Geotechnical,
Roadside, Right-of-way, Environmental, and Utility) during the development of the revised
bridge layout. The remainder of the effort associated with coordination with other technical
disciplines is included in the original contract.
300.3.4 Bridge Coordination with External Stakeholders
This task assumes 2 additional bridge-only coordination meetings with external stakeholders
(SRPMIC, SRP, and ADOT) as a result of changing the layout of the Main River Bridge.
Agendas will be prepared and meeting notes will be distributed after each meeting. The
remainder of the effort associated with coordination with external stakeholders is included in
the original contract.
Project No.: Tr0339 Contract No.: 2015-039
Revised: April 2018 Page 13 of 22

Scope of Services
Project Specific
300.4 Geotechnical
With the length of the main bridge expanding from 1,445 feet to 3,685 feet, a significant amount of
geotechnical investigation will be required to account for the increased number of bridge foundations.
The following descriptions accounts for geotechnical investigation of both the main bridge, the new
northern reliever bridge, and the roadway embankment segment between the two bridges.
300.4.1 Exploration & Access Plan Preparation
Terracon, accompanied by MR, will perform a site visit to evaluate the prospective boring
locations, site and access constraints, traffic control requirements, and other logistics of the field
investigation which require consideration. HDR will prepare a draft Geotechnical Investigation
and Boring Plan which will depict the boring locations and depths, proposed access routes, and
estimated areas of ground surface disturbance, and include a description of the drilling
equipment and methods, and will submit the draft Plan to MCDOT (including to MCDOT
Materials Group), and the HDR Design Team. The Plan will be a modification of the boring
plan developed for the investigation of the original (60 Percent Design Phase) nine-span main
river bridge layout. HDR will revise the draft Plan in response to review comments from
MCDOT Materials Group and the team, and submit a final Plan to MCDOT and the design
team.
300.4.2 Environmental & Encroachment/Access Permits Coordination
Environmental Review & Clearances: The Geotechnical Investigation and Boring Plan prepared
by HDR will be submitted to MCDOT Engineering Division, Environmental Program Branch
planners for their use in obtaining environmental permits for geotechnical field work, including
for the MCDOT environmental clearance and applying for the SRPMIC Environmental Review
and clearance. Communications and coordination with MCDOT Environmental Program
Branch will be required during the permitting process for the geotechnical field investigation.
Further, HDR will coordinate with MCDOT and the SRPMIC to determine if SRPMIC
representative(s) need to be present during the geotechnical field work. It is assumed that
advance notification of SPRMIC by HDR will be required prior to initiation of the field work.
An estimate of the area of disturbance due to the field investigation will be prepared by
Terracon and submitted as part of the environmental clearance package. The area of disturbance
estimate will include the boring locations themselves, access route to each boring location
(travel off of existing roadways), and each boring work zone including drill spoils.
All project field personnel will have completed the required cultural sensitivity training course
administered by SRPMIC.
Encroachment Permits: Terracon will apply for and secure an encroachment permit from
MCDOT for work within the Gilbert Road right-of-way, and an access permit from SRPMIC
for work within the Community's right-of-way, including preparing and submitting a traffic
control plan for proposed borings adjacent to the existing roadway. Traffic lane closures are not
anticipated to be needed for this field investigation. Borings along the existing Gilbert Road will
be located on or adjacent to the existing roadway shoulder and include shoulder closures and
"shoulder work ahead" signage. No borings are anticipated to be located within existing
MCDOT or SRPMIC paved roadways.
ADWR Permits & Boring Backfill/Abandonment: For the 60 Percent Design field
investigation, it was determined by Terracon that ADWR permits for borings which encounter
groundwater were not needed, as ADWR indicated they have no permit jurisdiction on SRPMIC
lands. Regardless, the top 20 feet of all bridge borings will be backfilled with cement-bentonite
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 14 of 22

Scope of Services
Project Specific
grout in accordance with ADWR abandonment
of groundwater pavement will will be be backfilled with drill cuttings, requirements. and borings Borings which do not reach
backfilled with 1/2-sack CLSM. located within 20 feet of the edge
(provided Utility Clearances: by 1VICDOT) Borings will be located in the field by Terracon
may be adjusted depending and upon surface features. The depth and specific based locations on project staking
contact Arizona 811 to locate and actual Blue-stake subsurface conditions encountered. Terracon of the borings
work. public underground utilities prior to start will of field
areas Access by to rubber-tired Boring Locations: Access to boring locations within
Gilbert Road using existing drill rigs and support trucks will be via the the existing Salt River bed and adjacent
Grading of access roads is not unimproved planned for roads and by crossing channel ground northbound surfaces. (NB)
this investigation.
300.43 Field Investigation & Laboratory
Field investigation for the main bridge extension, Testing
embankments will consist of the following explorations: the north reliever bridge, and the roadway fill
• planned Main bridge depth extension borings - Boring Nos. BB-11
• Northern reliever of 175 feet each below existing site grade. through BB-24, inclusive, to
of 100 feet each below bridge existing borings site - Boring Nos. BB-25 through BB-30 to planned
• Roadway fill embankment borings grade. depth
depths of 20 to 30 feet each below existing - Boring Nos. BR-9 through BR-15, to planned
The field investigation site grade.
developed by the design detailed team, see in this Terracon scope of work is based on the most current
Scope of Work. bridge layout
will Standard be performed penetration at testing and sampling, or open-end drive
fluids are not anticipated approximate to be required 5-foot intervals throughout the (modified depth of California) the sampling
Terracon field engineer or geologist will to advance the borings. During drilling borings. Drilling
laboratory record the results of penetration tests, and continuously package supervise the activities, log operations, the borings, a
evaluation. individual, representative samples for further
Laboratory Field investigation will be performed by Terracon
attached scope testing of work of soil samples also will be performed Consultants by and drilling subcontractors.
provide coordination and for details of the field investigation and Terracon. laboratory Refer to Terracon's
assign laboratory soils tests oversight based on of the field and laboratory work by Terracon, testing. HDR will
actual samples recovered. and will
300.4.4 Preliminary
HDR will prepare and submit a Geotechnical/Foundation Preliminary Design Recommendations
ongoing. enable the The design team to proceed with bridge Foundation and roadway Design Technical Memorandum to
submitted during tech the memo 60 Percent will constitute an update of the preliminary design while laboratory testing is
Design Phase and will include the following tech memo which was
• Logs of all completed borings information:
• Results intervals, and depth to groundwater accompanied level data. by subsurface soil descriptions, sampling
test results. of completed to-date laboratory soils tests (as available),
Project No.: and summary tables of
Revised: April TT0339 2018
Contract No.: 2015-039
Page 15 of 22

Scope of Services
Project Specific
• Description of the subsurface geotechnical profile.
• design Preliminary parameters foundation for recommendations, including drilled shaft capacity charts and
• Preliminary geotechnical laterally-loaded design shaft analysis.
• Preliminary recommendations parameters for use in bridge scour evaluation.
embankments and slopes, drainage for roadway structures, design, including roadway subgrade, fill
elements. earthwork factors, and other project
a embankments Preliminary evaluation of construction considerations for drilled shaft foundations, fill
and slopes, retaining walls and drainage structures.
be Review responded comments to and on incorporated the Tech Memo from MCDOT Materials Group and the design team will
in the final foundation design report
400 Northern Reliever Bridge
required As a result to of allow the for additional drainage hydraulic modeling, it was determined that a new bridge structure would be
Roma Avenue during al00-year of storm the northern event. segment of Gilbert Road between the Salt River and
water impounds the area north of the Salt River Without which a includes "reliever" outlet, during a 100-year storm event,
Avenue. By adding a new bridge to allow for drainage of this area, the the housing project community along Roma
flooding impacts to the residents along Roma Avenue; which was one of the stipulations does not worsen the
of this project.
400.1 Northern Reliever Bridge— Phase 1
400.111 Evaluation of Bridge Alternatives
which MDR will will evaluate include a three precast (3) multi-span bridge alternatives for the new 450-foot long crossing,
on standalone piers, and a cast-in-place concrete voided concrete slab, a cast-in-place concrete slab bridge supported
similar span length capabilities, so a 10-span bridge superbox. is assumed All three for all structure alternatives have
are three not alternatives, full-height abutments are assumed and therefore channel three and alternatives. bank armoring For all
will be investigated; required/included. spread For footings the first two alternatives, a pier wall versus a multi-column pier
bridge design will follow the ADOT versus Bridge deep Group foundations will also be investigated. All
include developing span lengths and pier locations, determining Design Guidelines. The evaluation will
2-D models, and developing approximate quantities and cost estimates main member depths based on
Consideration of any other girder/bridge type is not included in this scope for of each work. alternative.
decorative It is assumed, like the main river bridge, that the bridge will need to accommodate a sidewalk,
However, it railing is not and feasible utilities to attach (ITS and the Saddleback Communications) on the west side.
assumed that it will be buried at this location). 36-inch diameter SRP irrigation pipe on this bridge (it is
400.1.2 Bridge Selection Report (BSR)
submitted This task includes to MCDOT preparation of a Draft BSR and a Final BSR. The Draft BSR will be
BSR will be prepared in Bridge general Group conformance for review and comment prior to full distribution. The
The BSR will include conceptual drawings of the with bridge ADOT's Bridge Group Design Guidelines.
show the bridge plan, elevation and typical section for each alternatives. alternative. These drawings will
x 17" drawings will be required for each alternative (six total bridge drawings) I-IDR estimates two 11"
distributing show the conceptual information of the reliever bridge. This task will include assembling to adequately
meeting, and the distributing BSR, assembling review comments, conducting one comment resolution and
the final comment resolutions.
Project No.: TT0339
Revised: April 2018 Contract No.: 2015-039
Page 16 of 22

Scope of Services
Project Specific
400.1.3 Bridge Coordination with Other Technical Disciplines
This task includes coordination with other design team and MCDOT discipline leads/contacts
(Roadway, Drainage, Traffic, Geoteehnical, Roadside, Right-of-way, Environmental, and
Utility) during the development of the Bridge Selection Report.
400.1.4 Bridge Coordination with External Stakeholders
This task assumes 2 bridge-only coordination meetings with external stakeholders. Agendas
will be prepared and meeting notes will be distributed after each meeting.
400.2 Northern Reliever Bridge — Phase 2
400.2.1 Bridge Final Design and Plans
This task consists of performing the required structural design for the new bridge structure,
developing the bridge construction plans, calculations and quantities. The bridge will be
designed in accordance with the current AASHTO LRFD Bridge Design Specifications as
modified by the ADOT Bridge Group Design Guidelines. ADOT Standard Specifications for
Road and Bridge Construction and ADOT Standard Drawings will also be used for the bridge.
This task assumes the new bridge will be a 10-span precast concrete voided slab bridge
supported on multi-column piers and drilled shaft foundations with no skew and no deck drains.
It is assumed that the only retaining walls required for this bridge are the integral wingwalls at
the ends of the bridge abutments. No other retaining walls will be needed. It is assumed that
due to the different span configuration and bridge length, the aesthetic railing will be different
than the Main River Bridge. This scope of work assumes one submittal at the 60%, 95%, 100%
and PS&E stages. It is assumed that structural calculations will be submitted for review at the
60%, 95% and 100% stages. The bridge drawings will consist of:
• General plan, typical section and index 1 drawing
6 General notes and quantities 1 drawing
• Bridge plan and elevation 1 drawing
• Excavation/Backtill Pay Limits 1 drawing
• Foundation layout I drawing
• Drilled shaft details drawing
• Abutment details 5 drawings
• Pier details 3 drawings
• Superstructure details 8 drawings
• Miscellaneous details 3 drawings
• Aesthetic details 2 drawings
• Camber and screed elevations 3 drawings
Total = 30 drawings
400.2.2 Special Provisions and Cost Estimate
This task includes preparation of Special Provisions and cost estimates related to the bridge
design for the new reliever bridge. This scope of work assumes one submittal at the 60%, 95%,
100% and PS&E stages.
400.2.3 Bridge Coordination with Other Technical Disciplines
This task includes coordination with other design team and MCDOT discipline leads/contacts
(Roadway, Drainage, Traffic, Geotechnical, Roadside, Right-of-way, Environmental, and
Utility) during the development of the design, plans, Special Provisions and cost estimate.
Project No.: IT0339 Contract No.: 2015-039
Revised: April 2018 Page 17 of 22

Scope of Services
Project Specific
400.2.4 Bridge Coordination with External Stakeholders
This task assumes 3 bridge-only coordination meetings with external stakeholders. Agendas
will be prepared and meeting notes will be distributed after each meeting.
400.3 Geotechnical
See Geotechnical description Section 300.4
500 Updated Cost Risk Assessment
With the significant change in scope for the project, the Cost Risk Assessment and associated Risk
Register will need to be updated. Some risks might no longer be valid, while new risks will need to be
identified and included in updated Risk Register.
500.1 CRA Workshop
The initial CPA workshop spanned over a length of 3-days. It is anticipated that a follow-up workshop
to analyze and incorporate the changes in the project can be accomplished in a one day session. It is
anticipated that the workshop will occur directly following the completion of the revised 60%
submittal.
An updated risk model will be developed and summary results will be transmitted to MCDOT. The Risk
Report will not be updated.
600 Updated Technical Reports
600.1 Drainage Report
Based on the new project configuration, a completely new Drainage Report will be required. HDR shall
provide independent Quality Assurance and Quality Control for the onsite and offsite Hydrologic and
Hydraulic Report prepared by the teaming partner.
See CONSULTANT (f2) Scope for further details on report, and project deliverables.
600.2 Scour Report
Based on the new project configuration, a completely new Scour Report will be required. HDR shall
provide independent Quality Assurance and Quality Control for the Scour Report prepared by the
teaming partner.
See CONSULTANT (SE Fuller) Scope for further details on report, and project deliverables.
600.3 Geotechnical Report
600.3.1 Final Bridge Foundation Report
HDR will prepare and submit draft and final versions of the Bridge Foundation Report, which
will include complete results of the field investigations and laboratory testing, including the
following information:
• Project description and general site conditions.
• Site plan of boring locations
• Summary of existing data.
• Description of drilling equipment and procedures used in the subsurface investigation,
and photographs of the site conditions and field investigation.
• Summary of geologic conditions along the alignment, including a photographic log.
Project No.: T1'0339 Contract No.: 2015-039
Revised: April 2018 Page 18 of 22

Scope of Services
Project Specific
• Logs of all completed borings and backhoe test pits with subsurface soil descriptions,
sampling intervals, and depth to groundwater levels, including all 60 Percent Design
Phase data.
• Description of the subsurface geotechnical profile.
• Results of laboratory tests, summary tables of test results and test data sheets including
all 60 Percent Design Phase data.
• General description of foundation conditions and discussion of suitability of spread
footings and drilled shafts for structure support.
• Deep foundation recommendations, including drilled shaft capacity charts, estimated
settlements, and design parameters for laterally-loaded shaft analysis.
• Shallow foundation recommendations, including bearing resistance/settlement charts,
lateral earth pressure parameters, and recommendations for resistance to lateral loads.
• Geotechnical design parameters for use in bridge scour evaluation.
▪ Recommendations for scour protection.
• Recommendations for roadway design, including roadway subgrade, fill embankments
and slopes, retaining walls, drainage structures, earthwork factors, and other project
elements.
• Evaluation of construction considerations for drilled shaft foundations, shallow
foundations, fill embankments and slopes, and drainage structures.
• Pavement design for Gilbert Road, including a description of the existing pavement
structural section (based on as-builts and borings through the pavement) and records of
the pavement maintenance and rehabilitation.
Review comments from the MCDOT Materials Group and the MR Design Team on the draft
report will be responded to and resolved, and a final report prepared and submitted.
600.3.2 Foundation Data Sheets
HDR will prepare foundation data sheets for inclusion in the Plans. The foundation data sheets
will present logs of the bridge borings
600.3.3 Quality Assurance Reviews
Quality assurance reviews of the Preliminary Foundation Design Technical Memorandum and
the draft and final Bridge Foundation Reports will be completed by an HDR Senior
Geotechnical Engineer not directly involved with the project.
600.3.4 Basis of Design & Assumptions
The geotechnical investigation will be in substantial conformance with the requirements of the
MCDOT Roadway Design Manual, ADOT Guidelines for Geotechnical Investigation and
Geotechnical Report Preparation, and applicable AASHTO and FHWA specifications and
guidance for geotechnical investigation.
The geotechnical field investigations as scoped herein are based on the current bridge layout
developed by the design team.
MCDOT Engineering Division, Environmental Program Branch will obtain the applicable
environmental permits for field geotechnical work, including the MCDOT environmental
clearance and the SRPMIC Environmental Review and Clearance, utilizing information
provided by HDR and Terracon.
Communications and coordination with MCDOT Environmental Program Branch will be
required during the permitting process for the geotechnical field investigation.
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 19 of 22

Scope of Services
Project Specific
HDR will coordinate with MCDOT and the SRPMIC to determine if SRPMIC representative(s)
need to be present during geotechnical field investigations. At minimum, advance notification
of SPRMIC by HDR will be required prior to initiation of any field work.
Terracon (subconsultant to FIDR) will apply for and obtain encroachment permits from
MCDOT and the SRPMIC for work in their rights-of-way.
MCDOT will perform field staking and surveying of geotechnical boring locations using
location coordinates provided by HDR/Terracon.
HDR will coordinate with MCDOT and the SRPMG to determine future impacts of mining in
the pit downstream of the proposed bridge alignment and within the vicinity of the northern
reliever bridge.
HDR will coordinate with MCDOT for the development of a revised IGA for identification of
protected and restricted areas in the vicinity of the proposed bridges.
700 Miscellaneous
700.1 Additional Alternative Analysis Memorandum
At the direction of MCDOT, UDR will investigate an additional HEC-RAS 2D modeling alternative and
prepare and engineering opinion of probable cost for a scenario with constructing a levee system
upstream of the bridge on the right bank of the Salt River. This scenario would not need to maintain
previous constraints such as maintaining existing Right-of-Way (ROW) limits, and would still be based
on the same bridge length as designed in the initial 60% submittal. This scenario will identify potential
project risks, environmental and cultural challenges, impacts to schedule, and contain an opinion of
probable schedule for construction.
800 Post Design Services
800.1 Construction Phase Services
During construction HDR will provide construction phase services comprised of attending the pre-
construction meeting, select weekly contractor construction meetings, periodic site visits, responding to
Requests For Information (RFIS) issued by the contractor, review and approval of contractor submitted
shop drawings, and general project management throughout construction. These items are detailed
below:
Meetings
HDR will attend the pre-construction meeting, expected to occur at MCDOT office. HDR will provide
all technical leads for the pre-construction meeting including PM, Roadway Lead, Drainage Lead,
Bridge Lead, and Geotechnical Lead.
MR will also attend weekly contractor construction meetings, expected to be held at the project site.
HDR will provide one attendee to these meetings for the first 8 weeks of the project. Thereafter,
attendance will be by request of MCDOT; for estimating purposes, HDR will attend approximately 35%
of weekly construction meetings.
Field Visits
HDR will provide monthly field visits consisting of the Roadway Lead and Bridge Lead. Field Visit
reports, consisting of narrative and photographs, will be provided within 3 days of field visit.
Request for Information (RFD
HDR will provide official response of contractor issued RFIs throughout construction. For estimating
purposes, it is planned that there will approximately 12 Bridge/Structural RFIs and 10 Civil RFIs.
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 20 of 22

Scope of Services
Project Specific
Shop Drawing Submittals
UDR will review contractor shop drawings for both the main Gilbert Road bridge and the Northern
Reliever bridge. This task includes reviewing shop drawings as listed below, including 1 resubmittal:
1. Girder shop drawings
2. Joint shop drawings
3. Bearing shop drawings
4. Stay-in-place deck form (or precast deck panel) shop drawings
5. Deck overhang falsework shop drawings
6. Pier cap formwork calculations and shop drawings
7. Reinforcing shop drawings (2 substructure packages, 2 superstructure packages)
8. Fence/Aesthetic details shop drawings
9. Miscellaneous shop drawing
10. Drilled shaft installation plan
11. Concrete mix
12. Screeds at 2.5' intervals
13. Miscellaneous construction submittal
General Project Management
This task includes the preparation of monthly invoices and project management throughout
construction.
800.2 SRP Construction Phase Services
During construction HDR will provide construction phase services for the installation of the Salt River
Project (SEP) waterline and be comprised of attending the pre-construction meeting, select weekly
contractor construction meetings, periodic site visits, responding to Requests For Information (RFIs)
issued by the contractor, review and approval of contractor submitted shop drawings. The services
identified in 800.2 will be a pass-through to SRP for approval and payment. These items are detailed
below:
Meetings
HDR will attend the pre-construction meeting, expected to occur at MCDOT office. HDR will provide
the Technical Lead responsible for the waterline design..
HDR will also periodically attend weekly contractor construction meetings, expected to be held at the
project site. HDR will provide one attendee, upon request by MCDOT. For estimating purposes, HDR
will attend approximately 4 of weekly construction meetings.
Field Visits
HDR will provide monthly field visits consisting of the Technical Lead, during construction of the SRP
water line. Field Visit reports, consisting of narrative and photographs, will be provided within 3 days of
field visit. For estimating purposes, 4 field visits are anticipated.
Request for Information (RFI)
HDR will provide official response of contractor issued RFIs throughout construction. For estimating
purposes, it is planned that there will approximately 4 SRP waterline RFT&
Shop Drawing Submittals
HDR will review contractor shop drawings for specialty water line items.
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 21 of 22

Scope of Services
Project Specific
800.3 Letter Of Map Revision (LOMR)
UDR will prepare a Letter of Map Revision request and submit to FEMA. The purpose of the LOMR is
to update the effective FEMA FIRM to reflect the modifications due to the construction of the Gilbert
Road Bridge project. HDR will provide the following:
O Pre-Project Hydraulic Model
o Inclusion of approved Existing Conditions HEC-RAS model
• Post-Project Hydraulic Model
o Revisions to the Proposed Conditions HEC-RAS model to represent as-built survey
• Floodplain Mapping
o Delineation of 100-year and 500-year floodplain
o Delineation of floodway
O FIS Updates
o Updates to floodway table and profiles
• Public Notifications
o Prepare notifications for floodplain and floodway changes
• LOMR Report
o Project report describing project
o Compilation of required LOMR data
o FEMA MT-2 Forms
• Review Coordination
o HDR will respond to FEMA review comments
ASSUMPTIONS:
• FEMA LOMR review fee will be provided by MCDOT
• LOMR will be submitted via FEMA's online LOMC site
• As-built survey will be provided by the MCDOT and meets the FEMA requirements
O Assumes no more than two rounds of FEMA review comments
O No major changes from the CLOMR which would affect the hydraulic model or mapping
• No change in approach from the CLO1VIR
1200.1 Project Submittals
The revised 60% submittal will comprise of plans, specifications and construction cost estimate, as well
as technical reports. All submitted items will be distributed electronically along with one (1) hard copy.
Project No.: TT0339 Contract No.: 2015-039
Revised: April 2018 Page 22 of 22

FEE PROPOSAL - TABLE A
CONSULTANT
COST PROPOSAL SUMMARY
CONSULTANT: I-IDR Engineering CONTRACT NO.: 2015-039
PROJECT NAME: Gilbert Road Bridge at the Salt River
CIissiIieatioñs
Principal 45.0 $99.31 $4,468.95
Project Manager 658.0 $73.00 $48,034.00
Senior Project Engineer 1277.0 $76.14 $97,230.78
Project Engineer 1715.0 $55.43 $95,062.45
Senior Engineer 1230,0 $44.99 $55,337.70
Engineer 1276.0 $40.72 $51,958.72
Designer 892.0 $29.90 $26,670.80
Technician 1276.0 $43.45 $55,442.20
Project Administrator 105.0 $38.47 $4,039.35
Secretary/Clerical 117.0 $30.36 $3,552.12
Consultant's Subtotal Direct Labor $441,797.07
Consultant's Overhead @ 155.49% of Direct Labor $686,950.26
Consultant's Profit @ 10% of Direct Labor + Overhead $112,874.73
Consultant's Total Direct Labor $1,241,622.07
DIRECT AND OUTSIDE EXPENSES
egeiipti4n ExpenSe:.AnnAin
CLOAIR Coordination with FEMA Reviewer
Airfare - 2 staff @ $700/trip $1,400.00
Hotel Accommodations - 2 staff, 1 room each, 1 night @ $125/night $250.00
Per Diem - 2 staff, 2 days @ $60/day $240.00
Mileage
Meetings at MCDOT - 24 mi RT x 10 meetings @ $0.54/mile $129.60
Post Design - Mileage
Meetings at MCDOT - 24 rni RT x 4 meetings @ $0.54/mile $51.84
Con. Meeting at Site - 40 mi RT x 60 meetings @ $0.54/mile $1,296.00
Consultant's Total Direct and Outside Expenses $3,367.44

SUBCONSTILT.ANT(s)
Total :Cost
Hydraulic modeling and
J2 Engineering and Environmental onsite drainage $110,188.47
Sediment transport and
JE Fuller scour protection $64,703.72
Geotechnical field investigation
Terracon and lab testing $269,368.57
Traffic and ITS
Lee Engineering Post Design Services $9,471.18
Total Subconsultant(s) $453,731.94
Consultant's Total Direct Labor $1,241,622.07
Consultant's Total Direct and Outside Expenses $3,367.44
Total: $1,244,989.51
Consultant's Totals of Direct Labor and Direct and Outside Expenses $1,244,989.51
TOTAL PROPOSED FEE $1,698,721.45
(Inclusive of Consultant and Subconsultant[s] total proposed fee.)
UDR Engineering
Firm
17-44. avid SWi Apr18,2018) 2—
Signature
Area Operations Manager, Senior Vice President
Title
4/18/2018
Date