CONSTRUCTION CONTRACT - STIPULATED SUM
(DESIGN-BID BUILD PROJECT)
East Courts Building Renovation, 1st & 2nd Floors
Office of Procurement Services
Serial # 180031-DBB
Contract # 180031-DBB
C-
Project # 180031-DBB
Facilities Management Department
1VIARICOPA COUNTY, ARIZONA

CONTRACT AGREEMENT
THIS AGREEMENT, is made and entered into this 29th day of November, 2017, by and between
MARICOPA COUNTY, hereinafter called the COUNTY, acting by and through its BOARD OF
SUPERVISORS, and
Caliente Construction, Inc. hereinafter referred to as CONTRACTOR.
The CONTRACTOR, for and in the consideration of the sum of
One Million, Two Hundred Thirty Thousand Dollars, and No Cents ($1,230,000.00)
Unit prices, if any, are as follows:
N/A
to be paid to him by the COUNTY, in the manner and at the times hereinafter provided, and in
consideration of the other covenants and agreements herein contained, hereby agrees for itself, its heirs,
executors, administrators, successors, and assigns as follows:
ARTICLE I - SCOPE OF WORK: CONTRACTOR shall construct, and complete in a workmanlike
manner and to the satisfaction of the Facilities Management Department Director, a project for the
Maricopa County Facilities Management Department, designated as Serial # Facilities Management
Department, East Courts Building Renovation, 1st & 2nd Floors, and furnish at its own cost and
expense all necessary machinery, equipment, tools, apparatus, materials, and labor to complete the work
in the most workmanlike manner according to the Plans and Specifications on file with the Maricopa
County Facilities Management Department, and listed herein, together with modi -fications of the same
and other directions that may be made by the Maricopa County Facilities Management Department as
provided herein.
ARTICLE II - CONTRACT DOCUMENTS: The Contract Documents (Invitation to Bid, Plans,
Construction Special Provisions, Addenda issued prior to the execution of this Agreement, if any, General
Conditions, General Requirements, Specifications, Maricopa Association of Governments (MAG)
Standard Specifications and Uniform Standard Details, and the latest revisions thereto, Maricopa County
Supplement to M.A.G. Uniform Standard Specifications for Public Works Construction, Bid, Affidavits,
Performance Bond, Payment Bond, Certificates of Insurance, and Change Orders, if any,) are by this
reference made a part of this Contract and shall have the same effect as though all of the same were fully
inserted herein. This Contract, including the Contract Documents, represents the entire and integrated
agreement between the parties and supersedes any prior negotiations, representations, or agreements,
either written or oral.
All amendments to this Contract shall be in writing and approved/signed by both parties.
ARTICLE III - TIME FOR COMPLETION: CONTRACTOR further covenants and agrees at its
own cost and expense, to do all work as aforesaid for the construction of said improvements and to
completely construct the same and install the material therein, as called for by this agreement free and
clear of all claims, liens, and charges whatsoever, in the manner and under the conditions specified and
within the time, or times, stated in the Bid pamphlet and this Contract. The date for the commencement
of the work will be set by a Notice to Proceed issued by the Owner. The time for completion will be
measured from the date of commencement.
East Courts Building Renovation, 1st & 2nd Floors Serial # 180031-DBB
Request for Bids - Design Bid Build Pg. # 2

ARTICLE IV - SUBSTANTIAL COMPLETION: The CONTRACTOR shall achieve Substantial
Completion of the work not later than _120 days from the date of commencement subject to adjustments
to the Contract Time as provided for herein. Final Completion shall be achieved in 30 days after
SubstRntial Completion, subject to adjustments to the Contract Time as provided for herein.
ARTICLE V - PAYMENTS: For and in consideration of the satisfactory performance of the work as
set forth in the Contract Documents, which are a part hereof, and in accordance with the directions of the
COUNTY, through its Design Professional, the COUNTY agrees to pay the said CONTRACTOR the
amount earned, (and, if unit prices are applicable the sum due as computed from actual quantities of work
performed and accepted, or materials furnished at the unit bid price on the Bid made a part hereof) and to
make such payment in accordance with the requirements of A.R.S. § 34-221, as amended.
CONTRACTOR agrees to discharge its obligations and to make payments to its subcontractors and
suppliers in accordance with A.R.S. § 32-1129, the Prompt Pay Act.
ARTICLE VI- LIQUIDATED DAMAGES:
Liquidated damages are provided for in this Contract, as explained in the General Conditions to this
Contract.
Upon failure of Contractor to substantially complete the Project within the specified period of time, plus
approved time extensions, Contractor shall pay to OWNER the maximum sum of Eight Hundred Sixteen
Dollars and No Cents Dollars ($816.00) for each calendar day after the time specified in Article IV above.
The actual liquidated damages cost, including back-up will be forwarded to the Contractor. In any case
the actual liquidated damages amount shall not exceed the maximum sum indicated above. After
Substantial Completion, should Contractor fail to complete the remaining work within the time specified
in Article IV above, plus approved time extensions thereof, for completion and readiness for Final
Completion, Contractor shall pay to OWNER the maximum sum of Eight Hundred Sixteen Dollars and
No Cents ($816.00) for each calendar day after the time specified in Article IV above. The actual
liquidated damages cost, including back-up will be forwarded to the Contractor. In any case the actual
liquidated damages amount shall not exceed the maximum sum indicated above. These amounts are not
penalties but are liquidated damages to OWNER for its inability to obtain full beneficial occupancy of the
Project.
ARTICLE VII - TERMINATION: The COUNTY hereby gives notice that pursuant to A.R.S. §
38-511 A, this contract may be canceled without penalty or further obligation within three years after
execution if any person significantly involved in initiation, negotiation, securing, drafting or creating the
contract on behalf of the COUNTY is, at any time while the contract or any extension of the contract is in
effect, an employee or agent of any other party to the contract in any capacity or a Contractor to any other
party of the contract with respect to the subject matter of the contract. Cancellation under this section
shall be effective when written notice from the COUNTY is received by all of the parties to the contract.
In addition, the COUNTY may recoup any fee or commission paid or due to any person significantly
involved in initiation, negotiation, securing, drafting or creating the contract on behalf of the COUNTY
from any other party to the contract arising as a result of the contract.
ARTICLE VIII - TERMINATION FOR DEFAULT: If the CONTRACTOR should be adjudged
bankrupt or should make a general assignment for the benefit of its creditors, or if a receiver should be
appointed on account of its insolvency, the COUNTY may terminate the Contract. If the
CONTRACTOR should repeatedly refuse or should fail, except in cases for which extension of time is
provided, to provide enough properly skilled workers or proper materials, or repeatedly disregard laws
and ordinances, or fail to meet deadlines or not proceed with work, or otherwise be guilty of a material
breach of any provision of this Contract, then the COUNTY may terminate the Contract. Prior to
termination of the Contract, the COUNTY shall give the Contractor fourteen (14) calendar day's written
notice. Upon receipt of such termination notice, the Contractor shall be allowed fourteen (14) calendar
days to cure such deficiencies. In the event of termination under this paragraph, all documents, data, and
reports prepared by the CONTRACTOR under this Contract shall become the property of and be
East Courts Building Renovation, 1st & 2nd Floors Serial # 180031-DBB
Request for Bids - Design Bid Build Pg. # 3

delivered to the COUNTY upon demand. Sums claimed due by the CONTRACTOR shall not be paid
until the Work has been completed and such payment shall only be made after deduction damages caused
by the default. In the event a termination for default is determined to be without cause, it shall be deemed
to be a termination for convenience.
ARTICLE IX - TERMINATION FOR CONVENIENCE: The COUNTY reserves the right to terminate
the Contract, in whole or in part at any time, when in the best interests of the COUNTY without penalty
or recourse. Upon receipt of the written notice, the CONTRACTOR shall immediately stop all work, as
directed in the notice, notify all subcontractors of the effective date of the termination and minimize all
further costs to the COUNTY. In the event of termination under this paragraph, all documents, data and
reports prepared by the CONTRACTOR under the Contract shall become the property of and be
delivered to the COUNTY upon demand. The CONTRACTOR shall be entitled to receive just and
equitable compensation for work in progress, work completed and materials accepted before the effective
date of the termination. No lost "future profits" will be paid to the CONTRACTOR.
ARTICLE X - SUSPENSION OF WORK: The Owner may order the CONTRACTOR, in writing, to
suspend, delay, or interrupt all or any part of the work of this Contract for the period of time that the
Owner determines appropriate for the convenience of the COUNTY.
If the performance of all or any part of the work is, for an unreasonable period of time, suspended,
delayed, or interrupted (1) by an act of the Owner in the administration of this Contract, or (2) by the
Owner's failure to act within the time specified in this Contract (or within a reasonable time if not
specified), an adjustment shall be made for any increase in the cost of performance of the Contract
(excluding profit) caused by the unreasonable suspension, delay, or interruption, and the contract will be
modified in writing accordingly. However, no adjustment shall be made under this provision for any
suspension, delay, or interruption to the extent that performance would have been so suspended, delayed,
or interrupted by any other cause, including the fault of negligence of the Contractor, or for which an
equitable adjustment is provided (or excluded) under any other term or condition of this Contract.
A claim under this provision shall not be allowed:
For any costs incurred more than 14 days before the CONTRACTOR has notified the Owner in writing
of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a
suspension order); and unless the claim, in an amount stated, is made in writing as soon as practicable
after the termination of the suspension, delay, or interruption, but not later than the date of final payment
under the Contract.
ARTICLE XI - NEGOTIATION CLAUSE: Recovery of damages related to expenses incurred by
CONTRACTOR for a delay for which the COUNTY is responsible, which is unreasonable under the
circumstances and which was not within the contemplation of the parties to the contract, shall be
negotiated between CONTRACTOR and the COUNTY. This provision shall be construed so as to give
fall effect to any provision in the contract which requires notice of delays, provides for neutral evaluation
and arbitration or other procedure for settlement, or provides for liquidated damages.
ARTICLE XII - COMPLIANCE WITH LAWS: CONTRACTOR is required to comply with all
Federal, State and local ordinances and regulations. CONTRACTOR'S signature on this contract
certifies compliance with the provisions of the 1-9 requirements of the Immigration Reform Control Act
of 1986 for all personnel that CONTRACTOR and any subcontractors employ to complete this project.
The COUNTY will perform in accordance with the provisions of the Maricopa County Procurement
Code.
The CONTRACTOR warrants that it is in compliance with A.R.S. §41-4401 (regarding immigration)
and further acknowledges:
(1) The CONTRACTOR and its sub-contractors, if any, warrant their compliance with all
federal immigration laws and regulations that relate to their employees and their
compliance with A.R.S. §23-214, subsection A; (on e-verification, etc.). After December
31, 2007, every employer, after hiring an employee, shall verify the employment
East Courts Building Renovation, 1st & 2nd Floors Serial # 180031-DBB
Request for Bids - Design Bid Build Pg. # 4

eligibility of the employee through the e-verify program and shall keep a record of the
verification for the duration of the employee's employment or at least three years,
whichever is longer.
(2) A breach of a warranty under subsection 1 above, shall be deemed a material breach of
the contract that is subject to penalties up to and including termination of the Contract;
(3) The COUNTY retains the legal right to inspect the papers of any CONTRACTOR or
sub-contractor employee who works on the contract to ensure that the CONTRACTOR
or sub-contractor is complying with the warranty provided under subsection 1 above and
that the CONTRACTOR agrees to make all papers and employment records of said
employee(s) available during normal working hours in order to facilitate such an
inspection.
(4) Nothing herein shall make any CONTRACTOR or sub-contractor an agent or employee
of the COUNTY.
ARTICLE XIII - SBE PROGRAM: It is Maricopa County's policy to endeavor to ensure in every way
possible that small business participation firms shall have the opportunity to provide professional
services, materials, and contractual services to the County in a nondiscriminatory manner.
ARTICLE XTV — SBE PARTICIPATION PAY FORM: This form (copy attached) is to be submitted
with each pay application or invoice. Any pay application or invoice without this form attached is subject
to rejection as not being a completed pay application or invoice pursuant to the terms of the contract.
ARTICLE XV - ANTI-DISCRIMINATION PROVISION: CONTRACTOR agrees not to
discriminate against any employee or applicant for employment because of race, age, color, religion, sex,
disability, or national origin, and further agrees not to engage in any unlawful employment practices.
CONTRACTOR further agrees to insert the foregoing provision in all subcontracts hereunder.
CONTRACTOR agrees to comply with all provisions and requirements of Arizona Executive Order
2009-09 including flow down of all provisions and requirements to any subcontractors. Executive Order
2009-09 supersedes Executive order 99-4 and amends Executive order 75-5 and may be viewed and
downloaded at the Governor of the State of Arizona's website
http://www.azgovemor.govidms/upload/E0_2009_09.pdf which is hereby incorporated into this contract
as if set forth in full herein. During the performance of this contract, CONTRACTOR shall not
discriminate against any employee, client or any or any other individual in any way because of that
person's age, race, creed, color, religion, sex, disability or national origin.
ARTICLE X'VI — INFLUENCE: As prescribed in MC1-1203 of the Maricopa County Procurement
Code, any effort to influence an employee or agent to breach the Maricopa County Ethical Code of
Conduct, or any unethical conduct, may be grounds for Disbarment or Suspension under MC1-902.
An attempt to influence includes, but is not limited to:
(1) A Person offering or providing a gratuity, gift, tip, present, donation, money,
entertainment or educational passes or tickets, or any type valuable contribution or
subsidy;
(2) That is offered or given with the intent to influence a decision, obtain a contract, garner
favorable treatment, or gain favorable consideration of any kind.
If a Person attempts to influence any employee or agent of Maricopa County, the Chief Procurement
Officer, or his designee, reserves the right to seek any remedy provided by the Maricopa County
Procurement Code, any remedy in equity or in the law, or any remedy provided by this contract.
East Courts Building Renovation, 1st & 2nd Floors Serial # 180031-DBB
Request for Bids - Design Bid Build Pg. #5

ARTICLE XVII — AMENDMENTS: All amendments to this Contract shall be in writing and
approved/signed by both parties. Maricopa County Office of Procurement Services shall be responsible
for approving all amendments for Maricopa County.
ARTICLE XVIII ISRAEL BOYCOTT: By submitting this proposal the Contractor certifies that they
are in compliance with Article 9, Arizona Revised Statutes Section 35-393 et seg.
ARTICLE );IX — ALTERNATIVE DISPUTE RESOLUTION
Scope. Notwithstanding anything to the contrary provided elsewhere in the Contract, the alternative
dispute resolution ("ADR") process provided herein shall be the exclusive means for resolution of claims
or disputes arising under or related to the Contract, the interpretation thereof or the performance or breach
by any party thereto, including but not limited to original claims or disputes asserted as cross claims,
counterclaims, third party claims or claims for indemnity or subrogation, in any threatened or ongoing
litigation or arbitration with third parties, if such disputes involve parties to contracts containing this ADR
provision. No changes can be made to this process without the mutual assent of the County and the
claimant. The parties have structured this procedure with the goal of providing for the prompt, efficient
and final resolution of all disputes falling within the purview of this ADR process.
Meeting of Principals. When a claim is made or a dispute (hereafter "dispute") as described in Paragraph
1.1 arises, senior representatives of the County and the claimant will meet personally within ten (10)
business days to discuss the dispute and attempt to resolve it. If; after good faith efforts, resolution is not
achieved, the dispute will proceed to mediation.
Qualifications of Mediator and Arbitrators. Any person selected as mediator or arbitrator, either as single
arbitrator as a member or Chair of the arbitration panel, shall be a member of the State Bar of Arizona and
have experience in construction law.
Mediation. If the parties have been unable to resolve the dispute after a meeting of principals, the parties
may enter into mediation. The parties shall jointly select a mediator. The parties may mutually agree to
waive mediation and proceed directly to arbitration. If the mediation process is requested by either party,
the mediation period shall be informal and shall not exceed sixty (60) calendar days from the selection of
the mediator. During the mediation process either party may terminate mediation on written notice to the
other party and the mediator.
Binding Arbitration Procedure. The following binding arbitration procedure shall serve as the exclusive
method to resolve a dispute if mediation is unsuccessful, if mediation has been waived by the parties, or if
a party requests arbitration during the mediation process. Except as provided in Section 1.7.5 and 1.7.9,
the decision of the arbitrator or arbitrator panel is final and binding on the parties and not subject to
further judicial review.
A party requesting binding arbitration shall notify the other party of their demand for arbitration in
writing within seven (7) calendar days of (1) the failure of mediation; (2) waiver of mediation; or (3) of
the party's demand to terminate mediation.
If the Contractor requests arbitration it shall post a cash bond with the arbitrator in an amount agreed upon
by the parties or, in the event of no agreement, the arbitrator shall establish the amount of the cash bond to
deflay the cost of the arbitration and the proceeds from the bond shall be allocated in accordance with
paragraph 1.7.7. The bond must be in the full amount agreed upon or as established by the Arbitrator to
pay the potential cost of the full arbitration proceeding. The bond must be posted with and received by
the arbitrator within five (5) calendar days after the demand for arbitration.
East Courts Building Renovation, 1st & 2nd Floors Serial # 180031-DBB
Request for Bids - Design Bid Build Pg. # 6

Disputes involving less than $200,000 shall be heard by one single arbitrator chosen by agreement of the
parties. If the parties cannot agree on the single arbitrator, then the parties shall each submit two names to
a Judge designated by Maricopa County who shall select the single arbitrator.
For disputes in excess of $200,000, the arbitration panel shall consist of three arbitrators: the County's
appointed arbitrator, the Contractor's appointed arbitrator and a third arbitrator who shall be selected by
the parties' arbitrators and serve as the Chair of the arbitration panel.
The arbitration is to be convened and administered under the Revised Uniform Arbitration Act ("RUAA")
(A.R.S. § 12-3001 et seq.) and the American Arbitration Association Construction Rules shall serve as a
guideline for proceedings, thus as a supplement to the RUAA.
Expedited Hearing. Any party can request the single arbitrator or the Chair of the arbitration panel to set
an expedited hearing. If the single arbitrator or the Chair of the arbitration panel determines that the
circumstances justify it, the single arbitrator or the Chair of the arbitration panel will arrange for
scheduling of the arbitration at the earliest possible date. In any event, the hearing of any dispute not
expedited will commence as soon as practical but in no event later than thirty (30) calendar days after
notification of request for arbitration having been received. This deadline can be extended only with the
consent of all the parties to the dispute, or by decision of the single arbitrator or the Chair of the
arbitration panel upon a showing of good cause.
Procedure. The single arbitrator or the arbitration panel will conduct the hearing in such a manner that
will resolve disputes in a prompt, cost efficient manner giving regard to the rights of all parties. Each
party shall supply to the single arbitrator or arbitration panel a written pre-hearing statement which shall
contain a brief statement of the nature of the claim or defense, a list of witnesses and exhibits, a brief
description of the subject matter of the testimony of each witness who will be called to testify, and an
estimate as to the length of time that will be required for the arbitration hearing. The single arbitrator or
the Chair of the arbitration panel shall determine the nature and scope of discovery, if any, and the
manner of presentation of relevant evidence consistent with deadlines provided herein, and the parties'
objective that disputes be resolved in a prompt and efficient manner. No discovery may be had of any
materials or information for which a privilege is recognized by Arizona law. The single arbitrator or the
Chair upon proper application shall issue such orders as may be necessary and permissible under law to
protect confidential, proprietary or sensitive materials or information from public disclosure or other
misuse. Any party may make application to the Maricopa County Superior Court to have a protective
order entered as may be appropriate to confirm or enforce such orders of the Chair.
Hearing Days. In order to effectuate parties' goals, the hearing once commenced, will proceed from
working day to working day until concluded, absent a showing of good cause.
Award. The single arbitrator shall within ten (10) calendar days of the conclusion of a hearing issue an
award. The arbitration panel shall, within ten (10) calendar days from the conclusion of any hearing, by
majority vote, issue its award. The award shall include an allocation of fees and costs pursuant to 1.7.7
herein. The award is to be in accordance with the Contract and the law of the State of Arizona.
Scope of Award. Regardless of the provisions of the RUAA, the arbitration panel shall be without
authority to award punitive damages, and any such punitive damage award shall be void. If an award is
made against any party in excess of one hundred thousand dollars ($100,000), exclusive of interest,
arbitration fees, costs and attorneys' fees, it shall be supported by written findings of fact, conclusions of
law and a statement as to how damages were calculated.
Jurisdiction. The arbitration panel shall not be bound for jurisdictional purposes by the amount asserted
in any party's claim, but shall conduct a preliminary hearing into the question of jurisdiction over the
East Courts Building Renovation, 1st & 2nd Floors Serial # 180031-DBB
Request for Bids - Design Bid Build Pg. #7

claim as regards its amount upon application of any party at the earliest convenient time, but not later than
the commencement of the arbitration hearing. If the dispute is determined to involve less than $200,000,
the arbitration shall continue before the Neutral Arbitrator as a single arbitrator, with the party appointed
arbitrators being excused.
Entry of Judgment. As provided in the RUAA, any party can make application to the Maricopa County
Superior Court for confirmation of an award, and for entry ofjudgment on it.
Severance and Joinder. To reduce the possibility of inconsistent adjudications, the Mediator or the single
arbitrator or arbitration panel, may: (i) at the request of any party, join and/or sever parties, and/or claims
arising under other contracts containing this ADR provision, and (ii) the Mediator, on his own authority,
or the single arbitrator or arbitration panel may, on its own authority, join or sever parties and/or claims
subject to this ADR process as deemed necessary for a just resolution of the dispute, consistent with the
parties' goal of the prompt and efficient resolution of disputes, provided; however, that the A/E, OWNER
and Project Professionals shall not be joined as a party to any claim made by a Contractor. Nothing
herein shall create the right by any party to assert claims against another party not arising under or related
to the Contract or not recognized under the substantive law as applicable to the dispute. Neither the
Mediator nor the single arbitrator or arbitration panel is authorized to join to the proceeding parties not in
privity with the County. The Contractor cannot be joined to any pending arbitration proceeding, without
Contractor's express written consent and unless Contractor is given the opportunity to participate in the
selection of the single arbitrator or non-County appointed arbitrator.
Fees and Costs. Each party shall bear its own fees and costs in connection with any informal hearing
before the mediation. All fees and costs associated with any arbitration before the single panel or
arbitration panel, including without limitation the arbitrator fees, and the prevailing party's reasonable
attorneys' fees, expert witness fees and costs, will be paid by the non-prevailing party, except as provided
for herein. In the event that Contractor is the non-prevailing party, all fees and costs as noted above shall
first be paid out of the bond posted with the arbitrator. In no event shall the Contractor's obligation to
pay fees and costs be limited to the amount of the bond posted herein. In no event shall any arbitrator's
hourly fees be awarded in an amount in excess of $250 per hour and (i) costs shall not include any travel
expenses in excess of mileage at the rate paid by Maricopa County, not to exceed a one way trip of 150
miles, and (ii) all travel expenses, including meals, shall be reimbursed pursuant to the travel policy of
Maricopa County in effect at the time of the hearing. The determination of prevailing and non-prevailing
parties, and the appropriate allocation of fees and costs, will be included in the award by the single
arbitrator or arbitration panel.
Confidentiality. Any proceeding initiated under this ADR provision shall be deemed confidential to the
maximum extent allowed by Arizona law and, except for disclosures to a party's attorneys or accountants,
no party shall make any disclosure related to the disputed matter or to the outcome of any proceeding
except to the extent required by law, or to seek interim equitable relief, or to enforce an agreement
reached by the parties or an award made hereunder. This provision does not affect the County's right to
inform the County Supervisors of the dispute.
Equitable Litigation. Notwithstanding any other provision of ADR to the contrary, any party can petition
the Maricopa County Superior Court for interim equitable relief as may become necessary to preserve the
status quo and prevent immediate and irreparable harm to a party or to the Project pending resolution of a
dispute pursuant to ADR provided herein. No court may order any permanent injunctive relief except as
may be necessary to enforce an order entered by the arbitration panel. The fees and costs incurred in
connection with any such equitable proceeding shall be determined and assessed in ADR.
East Courts Building Renovation, 1st & 2nd Floors Serial # 180031-DBB
Request for Bids - Design Bid Build Pg. # 8

Change Order. Any award in favor of the Contractor against the County or in favor of the County against
the Contractor shall be reduced to a Change Order and executed by the parties in accordance with the
award and the provisions of the Contract or a settlement agreement as appropriate.
Merger and Bar. Any claim asserted pursuant to this ADR process shall be deemed to include all claims,
demands, and requests for compensation for costs and losses or other relief, including the extension of the
Contract performance period which reasonably should or could have been brought against any party that
was or could have been brought into this ADR process, with respect to the subject claim. The arbitration
panel shall apply legal principles commonly known as merger and bar to deny any claim or claims against
any party regarding which claim or claims recovery has been sought or should have been sought in a
previously adjudicated claim for an alleged cost, loss, breach, error, or omission.
Inclusion in Other Contracts. The Contractor shall cooperate with the County in efforts to include this
ADR provision in all other Project contracts.
30C. UNIFORM ADMINISTRATIVE REQUIREMENTS:
When applicable and by entering into this Contract the Contractor agrees to comply with all applicable
provisions of Title 2, Subtitle A, Chapter II, PART 200—UNIFORM ADMINISTRATIVE
REQUIREMENTS, COST PRINCIPLES, AND AUDIT REQUIREMENTS FOR FEDERAL AWARDS
contained in Title 2 C.F.R. § 200 et seq.
East Courts Building Renovation, 1st & 2nd Floors Serial # 180031-DBB
Request for Bids - Design Bid Build Pg. # 9

IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the day and date
first above written, in counterparts, each of which shall, without proof or accounting for the other
counterparts, be deemed an original contract.
East Courts Building Renovation, 1st & 2nd Floors
Lorraine Bergman 860697201
Printed Name Federal Tax Identification Number
President/CEO 091625
Title Arizona Contractor's License Number
/1/ 90924
Vendor Terms NIGP Commodity Code (Advantage)
COUNTY OF MARICOPA, ARIZONA
RECOMMENDED BY: ACCEPTED AND APPROVED:
Department Head Date Chairman, Board of Supervisors Date
Clerk of the Board Date
LEGAL REVIEW
Approved as to form and within the powers and
authority granted under the laws of the State of
Arizona to Maricopa County.
By:
Deputy County Attorney
Date:
East Courts Building Renovation, 1st & 2nd Floors Serial # 180031-DBB
Request for Bids - Design Bid Build Pg. # 10