INFRASTRUCTURE FUNDING AGREEMENT FOR THE WORKFORCE DEVELOPMENT ONE-STOP SYSTEM.PDF

Maricopa County — Formal (2017-09-20)

View PDF Item 61 Meeting page

Extracted text (via pymupdf_layout) 28757 characters
ARIZONA@WORK Infrastructure Funding Agreement
Infrastructure Funding Agreement (IFA):
Local Workforce Development Area __Maricopa County_______________________________________________
Date Submitted________________________________________________________
1. The period of time this agreement is effective
July 1, 2017 to June 30, 2020__________________________
2. Identification of all ARIZONA@WORK Job Center partners, Chief Executive Official(s), and the
Local Workforce Development Board (LWDB) participating in the IFA (See Attachment A)
3. Steps the LWDB, Chief Elected Official (CEO), and ARIZONA@WORK Job Center partners took to reach
consensus and/or an assurance that the Local Workforce Development Area followed guidance for the state
infrastructure funding mechanism
4. The process ARIZONA@WORK Job Center partners will use to resolve issues related to infrastructure funding
during the MOU duration period when consensus cannot be reached
5. A description of the periodic modification and review process to ensure equitable benefit among
ARIZONA@WORK Job Center partners
IFA Attachments
1

ARIZONA@WORK Infrastructure Funding Agreement
A. ARIZONA@WORK Job Center Partners, Chief Executive Official(s), and the LWDB Participating in the IFA
B. ARIZONA@WORK Operating Budget: Infrastructure Costs
C. Signatures of Co-located ARIZONA@WORK Job Center Partners Agreeing to Share Infrastructure Costs
D. Signatures of Non-Co-located ARIZONA@WORK Job Center Partners Agreeing to Negotiate the Sharing of
Infrastructure Costs When Sufficient Data is Available to Determine Relative Benefit and Proportionate Share
E. ARIZONA@WORK Operating Budget: Additional Costs (Applicable Career Services)
F. OPTIONAL:
ARIZONA@WORK Operating Budget: Additional Costs (Shared Operating Costs and Shared Services) and
Signature of ARIZONA@WORK Job Center Partners Agreeing to Share Identified Operating Costs/Shared Services
2

ARIZONA@WORK Infrastructure Funding Agreement
Attachment A:
Identification of all ARIZONA@WORK Job Center Partners, Chief Elected Official(s), and the Local
Workforce Development Board (LWDB) participating in the IFA
Local Workforce Development Board:
Maricopa County Workforce Development Board (MCWDB)
Marie Sullivan, Acting Chair and 1st Vice-Chair
234 N Central Avenue 3rd Floor, Phoenix AZ, 85004
(602) 576-4333
mariesullivan@hotmail.com
Patricia Wallace, MCWDB Executive Director
234 N Central Avenue 3rd Floor, Phoenix AZ, 85004
(602) 506-4146
WALLACEP001@mail.maricopa.gov
Chief Elected Official(s):
Denny Barney
Chairman, District 1
Maricopa County Board of Supervisors
301 W. Jefferson, 10th Fl.
Phoenix, AZ 85003
Office: (602) 506-1776
barneyd@mail.maricopa.gov
3

ARIZONA@WORK Infrastructure Funding Agreement
Steve Chucri
Supervisor, District 2
Maricopa County Board of Supervisors
301 W. Jefferson, 10th Fl.
Phoenix, AZ 85003
Phone: 602-506-7431
chucris@mail.maricopa.gov
Bill Gates
Supervisor, District 3
Maricopa County Board of Supervisors
301 W. Jefferson, 10th Fl.
Phoenix, AZ 85003
Phone: 602-506-7562
district3@mail.maricopa.gov
Clint Hickman
Supervisor, District 4
Maricopa County Board of Supervisors
301 W. Jefferson, 10th Fl.
Phoenix, AZ 85003
Phone: 602-506-7642
chickman@mail.maricopa.gov
Steve Gallardo
Supervisor, District 5
Maricopa County Board of Supervisors
301 W. Jefferson, 10th Fl.
Phoenix, AZ 85003
Phone: 602-506-7092
district5@mail.maricopa.gov
4

ARIZONA@WORK Infrastructure Funding Agreement
Required WIOA and ARIZONA@WORK Job Point of Contact Information
ARIZONA@WORK Job Center Partner Center Partner Name, Title, Address, Telephone, Email
Serves Local Area?
Adult, Dislocated Worker (DW), and Youth X Marie Sullivan, Acting Chair and 1st Vice-Chair
Programs under Title I-B of WIOA 234 N Central Avenue 3rd Floor, Phoenix AZ, 85004
602-576-4333
mariesullivan@hotmail.com
Job Corps under Title I of WIOA X Reid E Graser, Arizona Admissions Project Director
518 S. 3rd Street Phoenix, Arizona 85004
602-322-2887
rgraser@csiteamonline.com
YouthBuild under Title I of WIOA N/A
Indian and Native American Programs X Ron Trousley
(INAP) under WIOA Title I Note: Per DES directive, Maricopa County Workforce
Development Executive Director attempted contact.
No response received.
Migrant and Seasonal Farmworker X Kari Hogan
Programs (MSFW) under Title I of WIOA 520-770-2500
khogan@ppep.org
Adult Education and Family Literacy Act X Sheryl Hart, Deputy Associate Superintendent
programs under Title II of WIOA Arizona Department of Education and Adult
Education Services
1535 W Jefferson Street, Bin 26 Phoenix, AZ 85007
602-258.2410
sheryl.hart@azed.gov
Wagner-Peyser under Title III of WIOA X Chevera Trillo, Workforce Administrator
Arizona Department of Economic Security
1789 West Jefferson, Mail Drop 5111 Phoenix,
Arizona 85007
O: 602-542-4910
M: 480-487-7806
CTrillo@azdes.gov
5

ARIZONA@WORK Infrastructure Funding Agreement
State Unemployment Insurance (UI) X Chevera Trillo, Workforce Administrator
Arizona Department of Economic Security
1789 West Jefferson, Mail Drop 5111 Phoenix,
Arizona 85007
O: 602-542.4910
M: 480-487.7806
CTrillo@azdes.gov
Trade Adjustment Assistance (TAA) under X Chevera Trillo, Workforce Administrator
Title II of Trade Act Arizona Department of Economic Security
1789 West Jefferson, Mail Drop 5111 Phoenix,
Arizona 85007
O: 602-542.4910
M: 480-487.7806CTrillo@azdes.gov
Jobs for Veterans State Grants (Vets) under X Chevera Trillo, Workforce Administrator
Title 38, U.S.C. Arizona Department of Economic Security
1789 West Jefferson, Mail Drop 5111 Phoenix,
Arizona 85007
O: 602-542.4910
M: 480-487.7806
CTrillo@azdes.gov
Vocational Rehabilitation under Title IV of X Jon Ellerston, Region I Program Manager (RPM)
WIOA Region I Office
3221 N. 16th Street, Suite 200
Phoenix, AZ 85016
602-266-9206
jellerston@azdes.gov
Senior Community Service Employment X Darrell Reagan, Mature Worker Program
Programs (SCSEP) under Title V of Older Coordinator
Americans Act--State of Arizona Arizona Department of Economic Security
Division of Aging and Adult Services
1789 West Jefferson Phoenix, AZ 85007
Direct: 602- 542-6335/Main: 602- 542-4446
Senior Community Service Employment X Easter Seals (Grantee)/AARP(sub-grantee)
6

ARIZONA@WORK Infrastructure Funding Agreement
Programs (SCSEP)—National Grantees Alexia Torres
under Title V of Older Americans Act 4520 N Central Ave Ste 575
Phoenix, AZ 85012
602-841-0403
National Indian Council on Aging
Theresa Salazar
10501 Montogemery Blvd. NE Suite 210
Albuquerque, NM 87111
Career and Technical Education programs X Marilyn Gardner
at the postsecondary level (CTE) under (602) 542-5137
Perkins Career and Technical Education Act marilyn.gardner@azed.gov
Housing and Urban Development--- X Tammy Frazee
Employment and Training Programs Note: Per DES directive, Maricopa County Workforce
Development Executive Director attempted contact.
No response received.
Community Services Block Grants (CSBG)— X Bruce Liggett
Employment and Training Activities Maricopa County Human Services Director
234 N Central Avenue, 3rd Floor Phoenix, AZ 85004
(602) 506-0066
LiggettB@mail.maricopa.gov
Re-entry Employment Opportunities (REO) N/A
under Second Chance Act
Additional ARIZONA@WORK Job Center Partners Approved by the LWDB and CEO(s)---If Any
Temporary Assistance for Needy Families N/A
(TANF) employment & training under part A
of Title IV of Social Security Act*
* Workforce Arizona Council, 03-2016: “The Governor notified the Secretaries of the U.S. Departments of Labor and Health and
Human Services in writing that TANF will not be a required partner in Arizona, or within some specific local areas in the State.
Local TANF programs may still opt to be a one-stop partner, or to work in collaboration with the ARIZONA@WORK Job Center.”
7

ARIZONA@WORK Infrastructure Funding Agreement
Attachment B1: ARIZONA@WORK Job Center and Affiliate Site Locations
Local Workforce Development Area: ______Maricopa County________________________________________
ARIZONA@WORK Job Center Locations ARIZONA@WORK Affiliate Site Locations
(Name, Address, Contact Name, Phone Number) (Name, Address, Contact Name, Phone Number)
ARIZONA@WORK Job Center Location #1: Affiliate Site Location #1:
Maricopa – East One-Stop Arizona Department of Economic Security
735 North Gilbert Road Suite 134 Employment Services
Gilbert, AZ 858234 120 W. 1st Ave.
Contact: Tom Colombo Mesa, AZ 85210
602.372.4200 Contact: Marla Lazere
602.542.4910
ARIZONA@WORK Job Center Location #2: Affiliate Site Location #2:
Maricopa – West One-Stop Wickenburg Public Library
1840 North 95th Avenue Suite 160 164 E. Apache St.
Phoenix, AZ 85037 Wickenburg, AZ 85390
Contact: Tom Colombo Contact: Tom Colombo
602.372.4200 602.372.4200
ARIZONA@WORK Job Center Location #3: Affiliate Site Location #3:
8

ARIZONA@WORK Infrastructure Funding Agreement
Attachment B2: ARIZONA@WORK Job Center Partners Co-located in Each ARIZONA@WORK Job Center Location
Local Workforce Development Area: ___Maricopa County ____________________
(Place an “X” If the ARIZONA@WORK Job Center Partner is Co-located in the Identified ARIZONA@WORK Job Center or Affiliate Site)
ARIZONA@WORK ARIZONA@WORK ARIZONA@WORK ARIZONA@WORK Affiliate Affiliate Site Affiliate Site
Job Ctr Partner Job Ctr #1 Job Ctr #2 Job Ctr#3 Site #1 #2 #3
East One Stop West One Stop N/A Mesa Wickenburg N/A
Adult/DW x X x x
Youth x x x
Job Corps x
Native Amer
MSFW
Adult Ed x
Wagner-Peyser x x x
Trade
Veterans x x
SCSEP--State
SCSEP-National
Career/Tech Ed
HUD E&T
CSBG E&T
Second Chance
YouthBuild
Other: Veterans x x
Other: Vocational x
9

ARIZONA@WORK Infrastructure Funding Agreement
Rehabilitation
Attachment B3: Annual Infrastructure Budget for Each ARIZONA@WORK Job Center and Affiliate Site
ARIZONA@WORK Job Center: East One Stop________________________ (Name/Location)
Or
Affiliate Site/Specialized Center:______________________________ (Name/Location)
Cost Category/Line Item Line Item Cost Detail Cost
Rent
Rental of Facilities East Valley location (23,500 sq. ft.) $283,645
Subtotal: Rental Costs $283,645
Utilities and Maintenance
Electric $52,011.46
Gas $344.86
Water 684.79
Sewer Connections $0
High-Speed Internet $0
Telephones (Landlines) $0
Facility Maintenance Contract $19,272.76
Security Contract $43,362.08
Subtotal: Utilities and Maintenance Costs $115,676
Equipment
Assessment-related products Software licenses $11,408
Assistive technology for individuals with Software and hardware $3,500
disabilities
(“Access and Accommodation”)
10

ARIZONA@WORK Infrastructure Funding Agreement
Copiers 6 copiers $30,000
Fax Machines Included with copiers $0
Computers 36 staff computers (WIOA only) $54,000
Other tangible equipment used to serve all 28 computer in public computer lab $33,600
center customers (not specific to an
individual program partner)
Specify Other Tangible Equipment
Subtotal: Equipment Costs $132,508
Technology to Facilitate Access to the ARIZONA@WORK Job Center
Technology used for the center’s planning Email Software for sending email $480
and outreach activities distribution lists
Specify the Technology
Cost of creation and maintenance of a $0
center website (not specific to an individual
program partner) that provides outreach to
customers by providing information on
ARIZONA@WORK Job Center services
and/or provides direct service access to the
ARIZONA@WORK Job Center
Website Address:________________________
(Does not include data systems or case
management systems specific to individual
program partners.)
Subtotal: Technology to Facilitate Access Costs $480
Supplies to Support the General Operation of the ARIZONA@WORK Job Center (Local Option, If Agreed By All Co-located
ARIZONA@WORK Job Center Partners)
11

ARIZONA@WORK Infrastructure Funding Agreement
Supplies, as defined in Uniform Guidance at N/A $15,367
2 CFR 200.94, to support the general
operation of the ARIZONA@WORK Job
Center
Specify Supplies to Support General
Operation and Not Specific to a Co-located
Partner (e.g., Printing; Postage, Office
Supplies)
Subtotal: Supplies to Support the General Operation of the ARIZONA@WORK Job $15,367
Center
Common Identifier Costs (Local Option, If Agreed By All Co-located ARIZONA@WORK Job Center Partners)
Creating New Signage Building Sign $0 (no agreed upon pricing)
Updating Templates/Materials Letterhead and other documents $0
Subtotal: Common Identifier $0
SUMMARY OF TOTAL INFRASTRUCTURE COSTS TO BE SHARED BY CO-LOCATED ARIZONA@WORK Job Center PARTNERS
Cost Category Total Cost
Subtotal: Rental Costs $283,645
Subtotal: Utilities and Maintenance Costs $115,676
Subtotal: Equipment Costs $132,508
Subtotal: Technology to Facilitate Access Costs $480
Subtotal: Supplies to Support the General Operation of the ARIZONA@WORK Job $15,367
Center
Subtotal: Common Identifier Costs $0
TOTAL INFRASTRUCTURE COSTS FOR THIS LOCATION $547,676
12

ARIZONA@WORK Infrastructure Funding Agreement
Attachment B4: Percentage of Co-located ARIZONA@WORK Job Center Partner’s Occupancy in Each
Center
ARIZONA@WORK Job Center Location: _East One Stop______________________________
Total Square Footage of the ARIZONA@WORK Job Center: __23,500 Square Feet
Total Square Footage of Dedicated/Assigned Space For All Co-located
ARIZONA@WORK Partners: _12,986 Square Feet
Co-located ARIZONA@WORK Job Center Square Footage of the ARIZONA@WORK Job Center Partner’s
Partners ARIZONA@WORK Job Center Dedicated Space as a % of
Partner’s All Co-located ARIZONA@WORK Job
Dedicated/Assigned Space Center Partners’ Space
WIOA Title I-B Adult/Dislocated Worker 11,220 .86
WIOA Title I-B Youth 322 .03
Wagner-Peyser 1,259 .10
Trade 0 0
Veterans 85 .006
MSFW 0 0
Adult Education 0 0
Vocational Rehabilitation 100 .008
Other Co-located Partner: 0 0
Other Co-located Partner: 0 0
Other Co-located Partner: 0 0
Total Percentage of the Designated/Assigned Space of All Co-located 100%
ARIZONA@WORK Job Center Partners
13

ARIZONA@WORK Infrastructure Funding Agreement
Attachment B5:
Initial Proportionate Share of Infrastructure Costs Allocated to Each Co-located ARIZONA@WORK Job
Center Partner
ARIZONA@WORK Job Center Location: _East One Stop_____________________________
Total Infrastructure Costs for This ARIZONA@WORK Job Center: $647,676_ (See Attachment B3)
Co-located ARIZONA@WORK Proportionate Share $ Share to Be $ Share to Be Paid
ARIZONA@WORK Job Job Center Partner’s Paid In Non-Cash
Center Dedicated Space as a (% of ARIZONA@WORK In Cash
Partner % of Job Center Partner Space
All Co-located X Total Infrastructure
ARIZONA@WORK Cost =ARIZONA@WORK
Job Center Partners’ Job Center Partner
Space Share)
DES 11% 11% $60,244 $0
WIOA 89% 89% $487,432
Total Infrastructure Costs to Be Shared by ARIZONA@WORK Job Center $547,676 $0
Partners in Cash/Non-Cash
(Must Equal the Total Infrastructure Costs for This ARIZONA@WORK Job
Center
14

ARIZONA@WORK Infrastructure Funding Agreement
Attachment B3: Annual Infrastructure Budget for Each ARIZONA@WORK Job Center and Affiliate Site
ARIZONA@WORK Job Center: West One Stop (Name/Location)
Or
Affiliate Site/Specialized Center:______________________________ (Name/Location)
Cost Category/Line Item Line Item Cost Detail Cost
Rent
Rental of Facilities West Valley location (32,710 sq. ft.) $688,546
Subtotal: Rental Costs $688,546
Utilities and Maintenance
Electric $68,811
Gas Included in rent $0
Water Included in rent $0
Sewer Connections Included in rent $0
High-Speed Internet $0
Telephones (Landlines) $0
Facility Maintenance Contract $22,480
Security Contract $43,145
Subtotal: Utilities and Maintenance Costs $134,436
Equipment
Assessment-related products Software licenses $11,408
Assistive technology for individuals with Software and hardware $3,500
disabilities
(“Access and Accommodation”)
Copiers 6 copiers $30,000
15

ARIZONA@WORK Infrastructure Funding Agreement
Fax Machines Included with copiers $0
Computers 42 staff computers(WIOA only) $67,200
Other tangible equipment used to serve all 40 computer in public computer lab $48,000
center customers (not specific to an
individual program partner)
Specify Other Tangible Equipment
Subtotal: Equipment Costs $160,108
Technology to Facilitate Access to the ARIZONA@WORK Job Center
Technology used for the center’s planning Email Software for sending email $480
and outreach activities distribution lists
Specify the Technology
Cost of creation and maintenance of a N/A $0
center website (not specific to an individual
program partner) that provides outreach to
customers by providing information on
ARIZONA@WORK Job Center services
and/or provides direct service access to the
ARIZONA@WORK Job Center
Website Address:________________________
(Does not include data systems or case
management systems specific to individual
program partners.)
Subtotal: Technology to Facilitate Access Costs $480
Supplies to Support the General Operation of the ARIZONA@WORK Job Center (Local Option, If Agreed By All Co-located
ARIZONA@WORK Job Center Partners)
16

ARIZONA@WORK Infrastructure Funding Agreement
Supplies, as defined in Uniform Guidance at N/A $18,512
2 CFR 200.94, to support the general
operation of the ARIZONA@WORK Job
Center
Specify Supplies to Support General
Operation and Not Specific to a Co-located
Partner (e.g., Printing; Postage, Office
Supplies)
Subtotal: Supplies to Support the General Operation of the ARIZONA@WORK Job $18,512
Center
Common Identifier Costs (Local Option, If Agreed By All Co-located ARIZONA@WORK Job Center Partners)
Creating New Signage Building Sign $0
Updating Templates/Materials Letterhead and other documents $0
Subtotal: Common Identifier $0
SUMMARY OF TOTAL INFRASTRUCTURE COSTS TO BE SHARED BY CO-LOCATED ARIZONA@WORK Job Center PARTNERS
Cost Category Total Cost
Subtotal: Rental Costs $688,546
Subtotal: Utilities and Maintenance Costs $134,436
Subtotal: Equipment Costs $160,108
Subtotal: Technology to Facilitate Access Costs $480
Subtotal: Supplies to Support the General Operation of the ARIZONA@WORK Job $18,512
Center
Subtotal: Common Identifier Costs $0
TOTAL INFRASTRUCTURE COSTS FOR THIS LOCATION $1,002,082
17

ARIZONA@WORK Infrastructure Funding Agreement
Attachment B4: Percentage of Co-located ARIZONA@WORK Job Center Partner’s Occupancy in Each
Center
ARIZONA@WORK Job Center Location: West One Stop
Total Square Footage of the ARIZONA@WORK Job Center: 32,710 Square Feet
Total Square Footage of Dedicated/Assigned Space For All Co-located
ARIZONA@WORK Partners: __15,015__Square Feet
Co-located ARIZONA@WORK Job Center Square Footage of the ARIZONA@WORK Job Center Partner’s
Partners ARIZONA@WORK Job Center Dedicated Space as a % of
Partner’s All Co-located ARIZONA@WORK Job
Dedicated/Assigned Space Center Partners’ Space
WIOA Title I-B Adult/Dislocated Worker 11,712 .78
WIOA Title I-B Youth 472 .03
Wagner-Peyser 1,973 .13
Trade 0 0
Veterans 408 .03
MSFW 0 0
Adult Education 0 0
Vocational Rehabilitation 66 .004
Other Co-located Partner: (Job Corps) 64 .004
Other Co-located Partner: Early Education 320 .02
Other Co-located Partner: 0 0
Total Percentage of the Designated/Assigned Space of All Co-located 100%
ARIZONA@WORK Job Center Partners
18

ARIZONA@WORK Infrastructure Funding Agreement
Attachment B5:
Initial Proportionate Share of Infrastructure Costs Allocated to Each Co-located ARIZONA@WORK Job
Center Partner
ARIZONA@WORK Job Center Location: West One Stop
Total Infrastructure Costs for This ARIZONA@WORK Job Center: $________$1,002,082______ (See Attachment B3)
Co-located ARIZONA@WORK Proportionate Share $ Share to Be $ Share to Be Paid
ARIZONA@WORK Job Job Center Partner’s Paid In Non-Cash
Center Dedicated Space as a (% of ARIZONA@WORK In Cash
Partner % of Job Center Partner Space
All Co-located X Total Infrastructure
ARIZONA@WORK Cost =ARIZONA@WORK
Job Center Partners’ Job Center Partner
Space Share)
DES 16% 16% $160,333 $0
Job Corps .4% .4% $4,008
WIOA 83.6% 83.6% $837,741
Total Infrastructure Costs to Be Shared by ARIZONA@WORK Job Center $1,002,082 $0
Partners in Cash/Non-Cash
(Must Equal the Total Infrastructure Costs for This ARIZONA@WORK Job
Center
19

ARIZONA@WORK Infrastructure Funding Agreement
Attachment C:
Signatures of Co-located ARIZONA@WORK Job Center Partners Agreeing to Share Infrastructure
Costs
By signing below, all parties agree to the terms prescribed in the Infrastructure Funding Agreement
(Chief Elected Official) (Co-located Partner Entity)
Denny Barney, Chairman Board of Supervisors _____________________________________________________
Printed Name and Title Printed Name and Title
_____________________________________________________ _____________________________________________________
Signature and Date Signature and Date
(LWDB Chairperson) (Co-located Partner Entity)
_____________________________________________________ _____________________________________________________
Printed Name and Title Printed Name and Title
_____________________________________________________ _____________________________________________________
Signature and Date Signature and Date
20

ARIZONA@WORK Infrastructure Funding Agreement
Attachment D:
Signatures of Non-Co-located ARIZONA@WORK Job Center Partners Agreeing to Negotiate the
Sharing of Infrastructure Costs as When Sufficient Data Are Available to Determine Relative Benefit
and Proportionate Share
By signing below, all parties agree that when data are available to determine the benefit of
ARIZONA@WORK Job Centers to non-co-located ARIZONA@WORK Job Center partners, the
infrastructure cost sharing agreement will be renegotiated to include their proportionate share of
contributions.
(Non-Co-located Partner Entity) (Non-Co-located Partner Entity)
_____________________________________________________ _____________________________________________________
Printed Name and Title Printed Name and Title
_____________________________________________________ _____________________________________________________
Signature and Date Signature and Date
(Non-Co-located Partner Entity) (Non-Co-located Partner Entity)
_____________________________________________________ _____________________________________________________
Printed Name and Title Printed Name and Title
_____________________________________________________ _____________________________________________________
Signature and Date Signature and Date
21

ARIZONA@WORK Infrastructure Funding Agreement
Attachment E1: Career Services Applicable to Each ARIZONA@WORK System Partner
Basic Career Services T-I Adult T-I DW T-I Youth T-II AEL T-III WP T-IV VR TANF
T-I Program Eligibility   
Outreach, Intake, Orient     
Initial Assessment      
Labor Exch/Job Search    
Referrals to Partners     
LMI    
Performance/Cost Info   
Support Service Info    
UI Info/Assistance   
Financial Aid Info     
Basic Career Services Tech Ed SCSEP Job Corps Native Am MSF YouthBuild TAA
T-I Program Eligibility 
Outreach, Intake, Orient   
Initial Assessment   
Labor Exch/Job Search   
Referrals to Partners   
LMI   
Performance/Cost Info 
Support Service Info   
UI Info/Assistance   
Financial Aid Info  
22

ARIZONA@WORK Infrastructure Funding Agreement
Basic Career Services Comm Act Housing UI Native Am Other Part Other Part Other Part
T-I Program Eligibility
Outreach, Intake, Orient
Initial Assessment
Labor Exch/Job Search
Referrals to Partners
LMI
Performance/Cost Info
Support Service Info
UI Info/Assistance 
Financial Aid Info
Individ Career Services T-I Adult T-I DW T-I Youth T-II AEL T-III WP T-IV VR TANF
Comp Assessment   
Employment Plan   
Career Plan/Counsel   
Short-Term Prevoc   
Internships/Wk Exper   
Out-of-Area Job Search   
Financial Literacy   
ELA/Integ Education    
Workforce Preparation    
23

ARIZONA@WORK Infrastructure Funding Agreement
Individ Career Services Tech Ed SCSEP Job Corps Native Am MSF YouthBuild TAA
Comp Assessment   
Employment Plan  
Career Plan/Counsel  
Short-Term Prevoc 
Internships/Wk Exper 
Out-of-Area Job Search 
Financial Literacy 
ELA/Integ Education 
Workforce Preparation  
Individ Career Services Comm Act Housing UI Native Am Other Part Other Part Other Part
Comp Assessment 
IEP 
Career Plan/Counsel 
Short-Term Prevoc 
Internships/Wk Exper 
Out-of-Area Job Search
Financial Literacy
ELA/Integ Education
Workforce Preparation
24

ARIZONA@WORK Infrastructure Funding Agreement
Attachment E2: Consolidated System Budget for the Delivery of Applicable Career Services
The “Consolidated System Budget for the Delivery of Applicable Career Services” is the total actual or reasonably estimated
amount of funds budgeted by the required ARIZONA@WORK Job Center partners for the delivery of the career services (that are
applicable to their programs) and made available through the ARIZONA@WORK one-stop delivery system. This budget includes
all costs, including personnel, related to the administration and delivery of these services.
Applic Career T-I Adult T-I DW T-I Youth T-II AEL T-III WP T-IV VR TANF
Services
Basic Career
Services:
T-I Eligib/Initial
Assess
Outreach, Intake,
Orient
Labor Exch/Job $2,613,531 $ 325,245 $ 0 $113,563 $19,5918 $2,345,599.75 $ N/A
Search
Referrals/LMI
Support Service
Info
UI Info/Fin Aid
Info
Applic Career Tech Ed T-V OAA Job Corps Native Am MSF YouthBuild TAA
Services
Basic Career
Services:
T-I Eligib/Initial
Assess
$0 $167,724 $0 $0 $0 $0 $ 0
Outreach, Intake,
Orient
Labor Exch/Job
Search
25

ARIZONA@WORK Infrastructure Funding Agreement
Referrals/LMI
Support Service
Info
UI Info/Fin Aid
Info
Applic Career Comm Act Housing UI Native Am Other Part Other Part Other
Services Part
Basic Career
Services:
T-I Eligib/Initial
Assess
Outreach, Intake,
Orient
Labor Exch/Job $0 $0 $0 $0 $ N/A $ N/A $ N/A
Search
Referrals/LMI
Support Service
Info
UI Info/Fin Aid
Info
Applic Career T-I Adult T-I DW T-I Youth T-II AEL T-III WP T-IV VR TANF
Services
Indiv Career
Services:
Comp
Assessment/IEP $2,067,631 $255,550 $1,793,914 $357,164 $228,664 $7,258,297.51 $ N/A
Career
Plan/Counsel
Short-Term
26

ARIZONA@WORK Infrastructure Funding Agreement
Prevoc
Internship/Wk
Exper
Financial Literacy
IET/ELA/WF Prep
Applic Career Tech Ed T-V OAA Job Corps Native Am MSF YouthBuild TAA
Services
Indiv Career
Services:
Comp
Assessment/IEP
Career
Plan/Counsel
$0 $167,724 $0 $0 $0 $0 $ 0
Short-Term
Prevoc
Internship/Wk
Exper
Financial Literacy
IET/ELA/WF Prep
Applic Career Comm Act Housing UI Native Am Other Part Other Part Other
Services Part
Indiv Career
Services:
Comp
Assessment/IEP
Career $0 $0 $0 $0 $N/A $N/A $N/A
Plan/Counsel
Short-Term
Prevoc
Internship/Wk
27

ARIZONA@WORK Infrastructure Funding Agreement
Exper
Financial Literacy
IET/ELA/WF Prep
28

ARIZONA@WORK Infrastructure Funding Agreement
Attachment F1: Optional ARIZONA@WORK Job Center Partner Agreement to Share Other Costs
and Services
Type of Cost to be Shared:
None Provided
Description of the Cost to Be Shared and What it Includes:
ARIZONA@WORK Job Center Partners Agreeing to Share This Cost
The following ARIZONA@WORK Job Center partners have agreed to share these costs:
The ARIZONA@WORK Job Center partners that agreed to share these costs will benefit by:
29

ARIZONA@WORK Infrastructure Funding Agreement
Shared Cost Budget for
(Identify the Type of Cost)
Line Item Budget Detail Cost
Total Budget for This Shared Cost $
Agreed Upon Cost Allocation Methodology to Share This Cost
30

ARIZONA@WORK Infrastructure Funding Agreement
Proportionate Share for ARIZONA@WORK Job Center Partners Agreeing to Share These Costs
(Identify the Type of Cost)
Partners Agreeing Agreed Methodology Initial Partner Share Amount in Cash Amount in Non-Cash
Partner 1: $ $ $
Partner 2: $ $ $
Partner 3: $ $ $
Partner 4: $ $ $
Partner 5: $ $ $
Partner 6: $ $ $
Total Budget for This Shared Cost $ $ $
31

ARIZONA@WORK Infrastructure Funding Agreement
Attachment F2: Signature of ARIZONA@WORK Job Center Partners Agreeing to Share Identified
Operating Costs/Shared Services
Signature Page for Partners Agreeing to Share (Identify the Type of Cost)
By signing below, these parties agree to the terms prescribed in the sharing of other costs.
Partner 1:
_____________________________________________________
Printed Name and Title
_____________________________________________________
Printed Name and Title _____________________________________________________
Signature and Date
_____________________________________________________
Signature and Date
Partner 4:
Partner 2:
_____________________________________________________
Printed Name and Title
_____________________________________________________
Printed Name and Title _____________________________________________________
Signature and Date
_____________________________________________________
Signature and Date
Partner 3:
32