FIGHTER COUNTRY PARTNERSHIP FM 2017.PDF

Maricopa County — Formal (2017-04-12)

View PDF Item 45 Meeting page

Extracted text (via pymupdf_layout) 5256 characters
Last updated: 02/10/2017
General information
Organization Fighter Country Partnership
Contact First name Ron
Contact Last name Sites
Contact e-mail rsites@fightercountry.org
Contact phone number 6236959244
Address
Street 500 N. Estrella Pkwy Suite B2 PMB 479
City Goodyear
State az
ZIP Code 85338
From what tribe is the organization requesting the grant?
Fort McDowell Yavapai Nation
Total grant amount request
375000
1 / 1















Honor Guard Building
Early SD Estimate 8/27/2015
RECAP
PROJECT DATA
Developed Site Area (approximate) 1.00 acres
Recreation Center:
Base
Gross Bldg
Area
First Floor sf 4,000
TOTAL sf 4,000
Note: Bldg areas indicated are based on our gross area measurements of the plans.
SD Estimate
Current SD
8/27/2015
Sitework $233,357 $ 58.34 /gsf
Honor Guard Building $688,120 $ 172.03 /gsf
Total Rec Base - Base $921,477 $ 230.37 /gsf
Clarifications
Site improvements:
-Site clearing
-Grade site for building and site improvements
-New sewer to building from adjacent street
-Water main for fire and domestic service from adjacent street
-Concrete walks as indicated
-Landscaping
-Electrical conduit for service to bldg
Building
The following items are included and/or assumed:
-Spread footing foundations
-Concrete slab on grade
-Pre engineered steel buildging structure, roof and wall panels
-Masonry wainscot
-Storefront systems as indicated
-Doors and hardware as indicated
-Millwork for lobby and lockers
-Drywall partitions as indicated
-Flooring, sealed concrete with carpet at offices and conference
-Acoustic ceiling throughout
-Typical misc specialties and metal lockers
-Blinds at all select windows
-Mechanical budget based on DX system
-Electrical and lighting system
The following are not included:
-Data and telecommunication equipment
-Emergency power
The following items are not included:
-Governmental or utility company permits and fees of any type.
-Preconstruction and/or design fees
-Furniture, fixtures and equipment (except as noted)
-Televisions or Monitors
-Solar energy systems (PV or Hot water)
-Data and telecommunication cabling or equipment
-AV, com or sound systems
-Security or CCTV systems
-Emergency power

Haydon Building Corp 8/27/2015
Fighter Country Partnership Honor Guard Bldg
Early SD Estimate Cost Breakdown 8/27/2015
Current
Site Bldg Total
1000 General Conditions 15,000 135,000 150,000
1202 Engr Staking 3,500 0 3,500
1203 Engr Testing 5,000 0 5,000
2110 Demolition 0 0 0
2200 Earthwork 43,018 0 43,018
2300 Asphalt Paving 0 0 0
2400 Piped Utilities 9,100 0 9,100
2420 Drain Structures 6,000 0 6,000
2500 Engineered Site Concrete 23,100 0 23,100
2600 Misc Site Construction 44,400 0 44,400
2700 Site Furnishings 0 0 0
2800 Landscaping 34,620 0 34,620
2800 Termite Pretreatment 800 0 800
3300 Concrete 0 27,750 27,750
3800 Floor Sealer 0 1,438 1,438
4200 Masonry 0 18,028 18,028
4300 Pavers 0 0 0
5100 Struct & Misc Steel 0 3,500 3,500
6100 Rough Carpentry 0 0 0
6200 Trim Carpentry 0 1,650 1,650
6400 Cabinetry 0 9,450 9,450
7100 Fireproofing 0 0 0
7200 Insulation 0 0 0
7500 Roofing 0 0 0
7600 Metal Panels And Flashings 0 0 0
7700 Roofing Specialties 0 0 0
7900 Caulking 0 1,500 1,500
8000 Doors 0 9,260 9,260
8700 Finish Hardware 0 0 0
8800 Windows & Glazing 0 14,180 14,180
9100 Drywall & Stud Framing 0 27,996 27,996
9200 EIFS/Stucco 0 0 0
9300 Ceramic Tile 0 10,500 10,500
9500 Acoustic 0 10,045 10,045
9680 Floor Covering 0 4,145 4,145
9700 Wall Coverings 0 0 0
9800 Final Clean 0 1,000 1,000
9900 Painting 0 5,833 5,833
10000 Misc Specialties 0 11,500 11,500
10800 Toilet Part/Access 0 2,000 2,000
11000 Equipment 0 2,000 2,000
12000 Furnishings/Window Coverings 0 1,032 1,032
13000 Special Construction 0 133,600 133,600
15400 Plumbing 0 30,500 30,500
15500 Fire Protection 0 9,000 9,000
15800 HVAC 0 40,000 40,000
16100 Building Electrical 0 48,000 48,000
16050 Site Electrical 5,000 0 5,000
Contingency 8.0% 15,163 44,712 59,875
60000 Subtotal 204,701 603,618 808,319
1800 Permits 0 0 0
1950 Builders Risk 0.50% 1,167 3,441 4,607
1950 Liability Insurance 0.80% 1,867 5,505 7,372
70000 Overhead & Profit 5.00% 11,668 34,406 46,074
1910 Bond 0.00% 0 0 0
80000 Sales Tax 5.98% 13,955 41,150 55,104
TOTAL CONST COST 233,357 688,120 921,477


DEPARTMENT OF THE AIR FORCE
WASHINGTON DC
OFFICE OF THE ASSISTANT SECRETARY
HAR 2 ? a{lg
SAF/IEE
1665 Air Force Pentagon
Washington DC 20330
Mr. Ron Sites, President
Fighter Country Partnership
500 N. Estrella Parkway, Suite 82
Goodyear, AZ 85338
Dear Mr. Sites:
The United States Air Force appreciates the generous conditional proffer from the Fighter
Country Partnership that will provide a new 4,000 square foot Honor Guard facility that includes
a2,300 square foot outdoor drill pad for a total value of $625K. The proffered facility will
provide a greatly needed training location for the Honor Guard located at Luke Air Force Base.
It is with pleasure that I accept your gift and conveyance of this real property pursuant to Title
10. United States Code, Section 2601.
Again, I wish to express my appreciation and thanks to the Fighter Country Partnership
for this very generous gift.
Sincerely,
?z
MARK A. CORRELL, P.E.
Deputy Assistant Secretary of the Air Force
(Environment, Safety and Infrastructure)
cc:
AFCEC/CI
56 FWCC