2023-03-15_MC-85-PHASE-2A-CSA.PDF

Maricopa County — Formal (2023-03-29)

View PDF Item 56 Meeting page

Extracted text (via pymupdf_layout) 17037 characters
DocuSign Envelope ID: 57CA77C8-CF26-4DD9-8D80-2F2E3453E280
a,.s-, .-
· Delivering water and power"'
File: RD-12940
AGREEMENT FOR CONSTRUCTION OF SRP FACILITIES
This Agreement for construction, modification or relocation of SRP irrigation facilities
("Agreement") is entered into by and between the Salt River Project Agricultural Improvement
and Power District ("District") and Salt River Valley Water Users' Association
("Association"; collectively, "SRP") and Maricopa County, a political subdivision of the state
of Arizona ("MC"). SRP and MC may be referred to as "Party", or collectively as "Parties".
WHEREAS, MC has requested that SRP irrigation facilities be modified or relocated to
accommodate certain improvement or other development needs of MC for the project
referred to as MC85 - 107th Avenue To 75th Avenue with work located at Buckeye Rd, 107th
A venue To 95th A venue, and;
WHEREAS, SRP is willing to construct such accommodation, in whole or in pat1, or to permit
the MC to construct such accommodation in whole or in pat1 ("Work") with cet1ain
conditions.
THEREFORE, in consideration of the matters described herein and of the mutual benefits and
obligations set forth herein, SRP and MC agree as follows:
1) SRP shall perform the Work listed on the Construction Bid Summary Section I, and
optional Section II, if offered by SRP and selected by the MC. The Construction Bid
Summary is attached hereto as Exhibit A. The Work is further detailed in SRP's
Plans & Specifications, which are attached hereto as Exhibit B.
2) MC shall select the desired option below by checking the box.
□ OPTION A - Work that must be performed by SRP. (MC or District) shall pay
SRP's actual costs not to exceed the estimated amount of$ ___ as set forth in
Section I of the Exhibit A without prior written authorization.
q OPTION B - Work that must be performed by SRP and optional pipeline
construction by SRP. MC shall pay SRP's actual costs not to exceed the estimated
amount of $5,177,380.00 as set fotth in Sections I and II of Exhibit A without prior
written authorization.
3) a. SRP voluntarily agrees to use commercially reasonable efforts to comply with 49
U.S.C. 5323U) and 49 C.F.R. Patt 661 and 663 which provide that Federal funds may
not be obligated unless steel, iron, and manufactured products used in FI A-funded
projects are produced in the United States.
Regulations: 1). 49 U.S.C Chapter 53, specifically, Sect. 5323 U), Buy America
Regulations 49 C.F .R pat1 661, and pre award and post-delivery audits 49 C.F .R pat1
663;
II Page

DocuSign Envelope ID: 57CA77C8-CF26-4DD9-8D80-2F2E3453E280
-- , .-
· Delivering water and power"'
Guidance: 1). FTA's Buy America Audit Handbook, 2). OP 36 Buy America Review.
FTA's guidelines, regulations, handbooks, and examples are posted on the FTA's
website.
b. If SRP is unclear regarding its obligations under this provision, SRP may seek
clarification from MC by giving MC written notice of inquiry as soon as
reasonably practicable after discovery of the issue. Such requests are limited to only (i)
the items SRP cannot find a source to make a qualifying Buy America purchase, (ii)
items that SRP can find a source to make a qualifying Buy America purchase, but the
lead time for such purchase may unreasonably impact the Project Schedule, and (iii)
SRP is unable in good faith to determine whether the Buy America requirements apply
to a particular item. MC will respond to the inquiry in writing within 5 working days.
MC's response will include MC's recommendation to SRP on how to proceed, but
MC will not direct SRP's activities. SRP shall not be responsible for delays in
performance to the extent caused by MC recommendations or delays in MC providing
such recommendations.
c. As soon as practicable following the execution of this Agreement, SRP will provide
to MC a list of materials that do not comply with Buy America and an estimated cost
of purchasing such materials. MC will acknowledge receipt of this statement, but will
not make judgment as to the validity of the statement.
d. MC agrees, if it is determined that materials used are not in compliance with Buy
America requirements, the maximum SRP liability will be no more than 150
percent of the price attributable to the materials that are not in compliance with Buy
America requirements; provided, however, that if SRP has sought clarification of the
material requirement under the provisions of paragraph (b) above, and has followed
MC's written recommendations, SRP shall have no liability.
e. MC understands that SRP's compliance with the Buy America Act may result in
longer lead times for ordering materials, vendor-prescribed minimum purchase
quantities, and higher material costs. SRP will pass on to MC any additional costs it
incurs as a result of SRP's compliance with the Buy America Act, and SRP will not
be liable for schedule delays caused by longer lead times. If there is a minimum
purchase quantity requirement, SRP shall deliver and transfer title to excess materials
to MC at agreed locations within the Phoenix metropolitan area at no additional cost
to MC.
f. SRP shall not be responsible for delays caused by changes in the Project Design
made by or at the direction of MC.
4) The MC shall perform any Work not included in the Work to be performed by SRP
and comply with following conditions:
21Page

DocuSign Envelope ID: 57CA77C8-CF26-4DD9-8D80-2F2E3453E280
...
, .--
...... Delivering water and power ™
a. MC shall obtain such other licenses, permits, and agreements as required by any
governing bodies having jurisdiction over the location which is the subject
hereof.
b. Construction shall not commence until receipt of SRP's Notice to Proceed.
c. MC shall notify the SRP inspector and request a dryup ifnecessary to perform the
Work. SRP cannot assure a dryup, which may only be possible for brief periods and
cetiain times of the year.
d. MC shall indemnify, hold harmless, release and defend SRP, the United
States of America (USA), the Salt River Valley Water Users' Association
(Association) and each and every one of the members of their respective governing
bodies, their officers, agents and employees (the "Indemnified Parties") for, from
and against any and all claims, demands, suits, costs of defense, reasonable
attorneys' fees, witness fees of any type, losses, damages, expenses, fines,
penalties, and liabilities (collectively, "Losses") for injury to or death ofany person
or persons, including employees of SRP or of MC or its subcontractors, or
damage to property, including propetiy of SRP or ofMC or its subcontractors, to
which the Indemnified Patiies may be put or subjected by reason of any act or
omission on the part of MC, any subcontractor or supplier ofMC, or any of the
directors, officers, partners, members, managers, agents, servants or
employees of MC, or of its subcontractors or suppliers. MC's
obligations under this Section shall extend to Losses resulting from or arising out
of the inability of any irrigation structure constructed or modified pursuant to this
Agreement to contain or dispose of water entering the structure from a drainage
facility owned, designed, maintained or operated by the MC. MC's
obligations under this Section shall extend to the Indemnified Parties where they,
or any one of them, are allegedly concurrently negligent with MC, any
subcontractor or supplier of MC, or any of the directors, officers, partners,
members, managers, agents, servants or employees of MC, or of its
subcontractors or suppliers, in causing or contributing to the liability causing event.
MC shall also indemnify and hold harmless (and, upon notice so requiring from
SRP, also defend) the Indemnified Parties for, from and against any and all
Losses for contractual claims arising out of MC's agreements with third
parties. MC understands and agrees that MC enters upon the propetiy of the
USA, Association and/or SRP at MC's own risk.
e. MC warrants that construction shall conform to SRP plans and
specifications and be free from defects in material and workmanship. If defect
in materials or workmanship or other non-conformance with plans and
specifications appears within one year from the date of SRP acceptance, and
SRP so notifies MC within a reasonable time after its discovery, MC shall
correct the non-conformity at MC's sole cost and expense within thirty (30)
calendar days of notice by SRP, unless correction of the non­conformity
cannot reasonably be accomplished within 30 days, in which case
3IPage

DocuSign Envelope ID: 57CA77C8-CF26-4DD9-8D80-2F2E3453E280
-. , ...-
.. ..., Delivering water and power"'
MC shall commence correction efforts within 15 days of notice from SRP and
diligently prosecute such effotts to completion. If MC fails to correct the non-
conformity within the time period specified by SRP, SRP may correct the
non-conformity and MC will pay for the cost of performing the Work.
f. In the event the MC is unable to complete its Work, SRP shall have the
right, but not be obligated, to complete the Work by whatever method SRP
deems appropriate. This includes providing or obtaining any labor, materials or
equipment and perform any patt of the incomplete Work or Work that must be
redone. The cost of completing the Work, along with reasonable administrative
charges or other damages caused by delays in completing the Work shall be
charged to MC.
5) Changes to the plans and specifications may only be made by SRP. SRP shall provide
MC with prior written notice of any changes in costs. MC shall agree in writing to
any changes in cost to the MC.
6) This Agreement shall be governed in all respects by the laws of the state of Arizona.
7) Either Patty may terminate this Agreement at any time by providing thirty (30) days
written notice to the other Patty. In the event the MC desires to terminate this
Agreement prior to the completion of SRP's work, MC shall reimburse SRP for the
actual costs incurred as well as reasonable costs required to restore the facilities of
SRP, the USA or the Salt River Project Agricultural Improvement and Power District.
8) If MC's sub-contractor(s) file a lien against the premises where the Work and
services are being performed, MC shall, at its own expense, promptly take any and all
action necessary to cause any such lien to be released or discharged. If MC does not
satisfy the lien in a prompt manner, SRP may satisfy the amount of the lien and then MC
shall reimburse SRP for the amounts paid in settling the lien.
9) In the event of dispute involving the terms of this Agreement or an allegation of material
breach by either Patty, the Parties reserve all rights and remedies, arising by law or
equity, but shall waive any right to demand a trial by jury in an action commenced in
court with respect to any legal proceeding arising out of or relating to this Agreement.
10) No Waiver. The failure ofSRP to insist upon strict performance of any of the terms and
conditions hereof, or its delay or failure to exercise any rights or remedies provided
herein by law, or its failure to properly notify MC in the event of breach, shall not
release MC from any of the obligations of this Agreement and shall not be deemed a
waiver of any rights of SRP to insist upon strict performance hereof.
11) This Agreement is subject to the provisions of ARIZ. REV. STAT. § 38-511.
12) This Agreement is subject to the provisions of ARIZ. REV. STAT. § 42-17106.
13) Notices:
4IPage

DocuSign Envelope ID: 57CA77C8-CF26-4DD9-8D80-2F2E3453E280
-.. , .-
.,,...,, Delivering water and power ™
lfto MC
Ms. Kelly Roy
2901 W Durango St
Phoenix, AZ 85009
Ifto SRP:
SRP
Attn: Andrew Johnson, Manager
Water Engineering and Transmission, MS SSW 303
P.O. Box 52025
Phoenix, Arizona 85072-2025
14) This Agreement is binding upon the Parties hereto, and their respective successors and
assigns.
15) All data, regardless of form, including originals, images and reproductions, prepared by,
obtained by, or transmitted to SRP in connection with this Agreement is confidential,
proprietary information owned by the MC. Except as specifically provided in this
Agreement, SRP shall not disclose data generated in the performance of the services to
any third person without the prior written consent of the MC, or its designee.
16) In the event there is a breach of this Agreement, the prevailing Party to litigation shall
be entitled to its reasonable attorney's fees and court costs. It is fu1iher understood and
agreed that in the event any dispute arises regarding this Agreement or the tenns and
conditions hereof, the sole venue for litigation regarding this Agreement shall be in the
Courts of Maricopa County, Arizona.
17) This Agreement represents the entire agreement of the Parties and supersedes all
negotiations, representations, prior discussions or preliminary agreements between the
Pa1iies. No statements, warranties or representations of any kind not created in this
Agreement shall in any way bind the Pa1iies. This Agreement can only be changed or
modified by a writing signed by all of the Pa1iies hereto.
18) No term or provision of this Agreement that is determined by a court of competent
jurisdiction to be invalid or unenforceable shall affect the validity or enforceability of
the remaining terms and provisions of this Agreement. Any term found to be invalid or
unenforceable shall be deemed as severable from the remainder of the Agreement.
19) This Agreement is not intended to constitute, create, give rise to, or otherwise recognize
a joint venture, partnership or formal business association or organization of any kind,
and the rights and obligations of the Parties shall be only those expressly set fo1ih in this
Agreement. The Pa1iies agree that no individual performing under this Agreement on
behalf of SRP will be considered a MC employee, and that no rights of MC civil
service, MC retirement or MC personnel rules shall accrue to such
SI Page

DocuSign Envelope ID: 57CA77C8-CF26-4DD9-8D80-2F2E3453E280
.-.. , .-
· Delivering water and power ™
individual. SRP shall have total responsibility for all salaries, wages, bonuses,
retirement, withholdings, workers' compensation, other employee benefits, and all taxes
and premiums appurtenant thereto concerning such individuals and shall save and
hold harmless the MC with respect thereto.
20) SRP shall comply with all existing and subsequently enacted federal, state and local
laws, ordinances, codes, and regulations that are, or become applicable to this
Agreement. If a subsequently enacted law imposes substantial additional costs on SRP,
a request for an amendment may be submitted.
21) This Agreement is in the nature of a personal services agreement and SRP shall have no
power to assign its rights and obligations under this Agreement without the prior written
consent of the MC. Any attempt to assign without such prior written consent shall be
void.
22) This Agreement is may be canceled by MC for a conflict of interest pursuant to
Arizona Revised Statutes §38-511.
IN WITNESS HEREOF, each Party has caused the execution of this Agreement by the
undersigned, who is vested with authority to bind such Party to the terms and conditions herein.
"SRP" "MC"
Salt River Project Agricultural Maricopa County, a State of Arizona
Improvement and Power District and political subdivision
Salt River Valley Water Users'
Associatim
un ratt MC Representative
sociate General Manager
Customer Operations
2-23-z3
Date Signed Title of Representative
Date Signed
61Page

DocuSign Envelope ID: 57CA77C8-CF26-4DD9-8D80-2F2E3453E280
-.. , ---
™
illlftr Delivering water and power
EXHIBIT A e No: SRP # RD-12940
Construction Bid Summary
SRP # RD-12940
MC 85 95th Ave to I 07th Ave MCDOT Phase 2 (Part A)
MC 85 (Buckeye Road) 95th Avenue to I 07th Avenue
2/3/2023
SECTION I - Items bv SRP
Item Item Description Unit Quantity Unit Bid Net Bid
I. Piped Lateral Turnout Structure# 0326 (Sta. 26+81.2) LS I 96,137 96,137
2. Piped Lateral Turnout Structure# 0304 (Sta. 39+52.9) LS 128,522 128,522
± 3. Manhole Turnout Structure # 0303 (Sta. 0+60.4 ) LS 90,581 90,581
"4. Piped Lateral Turnout Structure# 0301 (Sta. 51+86.4) LS 164,338 164,338
± 5. Construction Engineering - S1111,ey, !11spection, & AsBuilrs LS 114,384 114,384
SECTION I TOTALS $593,962
SECTION II - Bid Items
Item Item Description Unit Quantity Unit Bid Net Bid
I. 24" RGR Cone Pipeline Class 5 LF 3474 260 904,823
2. 30" RGR Cone Pipeline Class 5 LF 4665 305 1,423,471
± 3. 36" RGR Cone Pipeline Class 5 EA 1024 385 394,422
.. 4. 54" RGR Cone Pipeline Class 5 LF 810 538 435,781
.. 5. Manholes EA 16 30038 480,600
± 6. Headwalls & Headwall/frashrack EA 7 35006 245,044
.. 7. Restoration of Sidewalk, Curb & Gutter, Asphault LS 25393 25,393
.. 8. Trucking & Dumping LS 377067 377,067
± 9. Miscellaneous Construction Items (Note ) LS 194756 194,756
± IO. Miscellaneous Removal Items (Note 5) LS 102061 102,061
SECTION II TOTALS $4,583,418
Swnmary: SECTION I - Items by SRP $593,962
SECTION II - Bid Items $4,583,418
NET BID = $5,177,380
71Page