Report to the Board of Supervisors
Prepared by the Maricopa County Planning and Development Department
Board Hearing Date: February 7, 2024
Case #/Title: Z2023106 - PHO Marisol
Supervisor District: 4
Applicant/Owners: Declan Murphy / Jacqueline and Angel Delahaut
Request: Special Use Permit (SUP) for a wireless communication facility
(WCF), 80' lattice-tower stealth designed as a windmill, in the Rural–
43 zoning district
Site Location: Generally located 2,100’ west of the NWC of Montgomery Rd. and
163rd Ave. in the Surprise area
Site Size: Approx. 2,500 sq. ft. of a 33-acre parcel
County Island Status: N/A
Additional
Comments: The proposed SUP will allow a WCF on the subject property with a
reduced setback to the southern lot line and increased support
structure and antenna array diameters. The diameter increases are
needed to accommodate the proposed WCF design to mimic an old
style water pump windmill. The proposed WCF design will be an
aesthetic improvement over other WCF design options and will
blend in with the surrounding rural environs. Staff received no
public comment on the request. There are no outstanding concerns
from reviewing agencies.
Commission
Recommendation: On 1/11/24, the Commission voted 7-0 to adopt a motion
recommending the Board of Supervisors approve Z2023106
subject to conditions ‘a’ – ‘g’:
a. Development of the site shall be in substantial conformance with the Site Plan entitled
“PHO Marisol“, consisting of 6 full-size sheets, dated October 27, 2023, and stamped
received November 8, 2023, except as modified by the following conditions.
b. Development of the site shall be in substantial conformance with the Narrative Report
entitled ““PHO Marisol“, consisting of 4 pages, dated November 8, 2023, and stamped
received November 8, 2023, except as modified by the following conditions.
February 7, 2024
Z2024106
Page 1 of 3

c. The wireless communication tower shall retain the stealth properties as originally
designed. Any damaged or missing windmill components shall be replaced within 60 days
of such damage occurring.
d. The following Rural-43 SUP standards shall apply:
1. Minimum Setback to Southern lot line: 68’
2. Maximum WCF Structure Diameter: 14’ 6”
3. Maximum Antenna Array Diameter: 18’
e. The following Planning Engineering conditions shall apply:
1. All development and engineering design shall be in conformance with Section 1205 of
the Maricopa County Zoning Ordinance; Drainage Policies and Standards; Floodplain
regulation for Maricopa County; MCDOT Roadway Design Manual; and current
engineering policies, standards and best practices at the time of application for
construction.
2. Engineering review of planning and/or zoning cases is for conceptual design only and
does not represent final design approval nor shall it entitle applicants to future designs
that are not in conformance with Section 1205 of the Maricopa County Zoning
Ordinance and Drainage Policies and Standards; Floodplain Regulations for Maricopa
County; and the MCDOT Roadway Manual.
3. The WCF compound walls will require a turned block, every other block along the base
course to maintain historic drainage patterns.
4. The site contains areas of regulated floodplains. The project, as submitted, does not
appear to disturb any floodplain. Any disturbance would require issuance of a
floodplain use permit concurrent with building permits.
5. Any work in the Montgomery Road will require a permit from MCDOT.
6. The applicant must execute a wireless agreement with MCDOT for all equipment,
conduit, F/O and other work that will be within the MCDT ROW.
7. Approval of the US Bureau of Reclamation (BOR) is required to permit utility extensions
across federally owned property under their control.
f. This special use permit is valid for a period of thirty years and shall expire on January 11,
2054 or upon termination of the use for a period of 90 or more days, whichever occurs
first. All site improvements associated with the special use permit shall be removed within
90 days of such expiration or termination of use.
g. The granting of this change in use of the property has been at the request of the applicant,
with the consent of the landowner. The granting of this approval allows the property to
enjoy uses in excess of those permitted by the zoning existing on the date of application,
subject to conditions. In the event of the failure to comply with any condition, and at the
time of expiration of the special use permit, the property shall revert to the zoning that
existed on the date of application. It is, therefore, stipulated and agreed that either
February 7, 2024
Z2024106
Page 2 of 3

revocation due to the failure to comply with any conditions, or the expiration of the special
use permit, does not reduce any rights that existed on the date of application to use, divide,
sell or possess the property and that there would be no diminution in value of the property
from the value it held on the date of application due to such revocation or expiration of
the special use permit. The special use permit enhances the value of the property above
its value as of the date the special use permit is granted and reverting to the prior zoning
results in the same value of the property as if the special use permit had never been
granted.
Presented by: Joseph Mueller, Planner
Reviewed by: Darren Gérard, AICP, Planning Manager
Attachment: 1/11/24 P&Z Packet (23 pages)
Note: 1/11/24 Draft P&Z Minutes are not available as of the writing of this report, but can be
provided upon request later when available.
February 7, 2024
Z2024106
Page 3 of 3

Report to the Planning and Zoning Commission
Prepared by the Maricopa County Planning and Development Department
Case: Z2023106 - PHO Marisol
Hearing Date: January 11, 2024
Supervisor District: 4
Applicant: Declan Murphy
Owners: Jacqueline and Angel Delahaut
Request: Special Use Permit (SUP) for a wireless communication facility (WCF), 80'
lattice-tower stealth designed as a windmill, in the Rural–43 zoning district
Site Location: Generally located 2,100’ west of the NWC of Montgomery Rd. and 163rd
Ave. in the Surprise area
Site Size: Approx. 2,500 sq. ft. of a 33-acre parcel
Density: N/A
County Island: No
County Plan: White Tank Grand Avenue Area Plan – Single Family - Rural (0-1 du/ac)
Municipal Plan: City of Surprise – Neighborhood
Municipal Comments: None received
Support/Opposition: None known
Recommendation: Approve with conditions
Z2023106
Page 1 of 8

Project Summary:
1. The applicant is proposing an 80’ tall WCF on the subject property that will include a 2,500 sq ft
area with associated ground equipment surrounded by an 8’ masonry screen wall. The WCF will
be designed to mimic an old-style water pump windmill so that it blends in with the rural western
character of the surrounding area. The proposal includes a requested increase in allowed
structure diameter to 14’ 6” and increased antenna area diameter to 17’ 10”. The requested
diameter increases are to facilitate the chosen style of tower, as it will utilize a lattice style
structure in order to achieve the old-style windmill appearance. The applicant is also requesting
a setback reduction to the southern lot line from 160’ (2’ setback per 1’ height) to 68’ 5”, as
measured from the plane of the southernmost protrusion of the proposed antenna array to the
southern lot line. The WCF will be setback at least 2:1 from all other lot lines.
2. The subject property has no recent history prior to the pursuit of the current SUP request. The
initial pre-application meeting for the proposed WCF was held on July 25, 2023. It was determined
a SUP would be necessary due to the proposed WCF not meeting zoning code setback
requirements to the southern lot line as well as to facilitate increased diameters for the antenna
array and support structure. The formal submittal for the request was on September 7, 2023 and
the technical advisory committee meeting was held on October 3, 2023.
BASE ZONING
DISTRICT PROPOSED ZONING REGULATIONS
REGULATION REGULATIONS (Rural - (Rural – 43 SUP)
43)
Max. WCF Height 80’ 80’
160’ (2’ setback for
Min. WCF Setback 68’ 5” (to south lot line)
every 1’ in height)
Maximum Diameter
30” 14’ 6”
of Support Structure
Maximum Diameter
8’ 17’ 10”
of Antenna Array
Z2023106
Page 2 of 8

2023 Aerial Image
Zoning Map
Existing On-Site and Adjacent Zoning / Land Use:
3. On-site: Rural - 43 / Single-family residential
North: Rural - 43 / Single-family residential
South: Montgomery Rd then PAD (Surprise) / Canal
Z2023106
Page 3 of 8

East: Rural - 43 / Single-family residential
West: Rural - 43 / Single-family residential
Utilities and Services:
4. Water: N/A
Wastewater: N/A
School District: Nadaburg Unified School District
Fire: Rural Metro
Police: Maricopa County Sheriff’s Department
Right-of-Way:
5. The following table includes existing and proposed half-width right-of-way and the future
classification based upon the Maricopa County Department of Transportation (MCDOT) Major
Streets and Routes Plan.
Street Name Half-width Existing R/W Half-width Proposed R/W Future Classification
Montgomery Rd 25’ 25’ Minor collector
Adopted Plans:
6. White Tank Grand Avenue Area Plan (December 6, 2023), Single-Family – Rural: The rural land
use designation is designed to protect dedicated open space, scenic corridors, flood ways, and
to buffer designated growth areas.
7. City of Surprise General Plan 2035 (adopted December 19, 2015), Neighborhood: The Surprise
general plan calls for rural neighborhood areas consisting of low density residential and low
intensity neighborhood commercial to develop adjacent to suburban development areas in order
to preserve open space and provide necessary services for rural/residential uses.
Public Participation Summary:
8. The applicant met all minimum public participation requirements by sending notice of the request
to all property owners within 300’ of the site via USPS and installing two compliant posting signs
on site. The applicant reported no public comment as a result of their outreach efforts. Likewise,
staff has not received any public comment on the case.
Outstanding Concerns from Reviewing Agencies:
9. N/A
Staff Analysis:
10. Staff notes that WCFs of up to 80’ in height are an allowed use within the Rural-43 zoning district.
The proposed WCF does not meet the required 2:1 minimum setback distance to the southern lot
line nor maximum diameter for both the support structure and antenna array. The latter is chiefly
because of the design choice to mimic an old western style water pump windmill. This design
choice includes a lattice style tower, much like many antiquated windmills employed, that is much
wider than a monopole WCF design commonly employed. Since the surrounding area is
dominated by rural land uses, ‘western’ character, and densities this is an appropriate design
Z2023106
Page 4 of 8

choice aesthetically superior to a standard WCF design. As such, staff has no concerns over the
requested increase in diameter of both the support structure and antenna array. Staff notes the
property adjacent to the requested reduced setback is owned by the United State Bureau of
Reclamation (USBOR) and appears to act as a buffer for the canal to the south. As such there is
no foreseeable adverse impact with the 68’ 5” southern setback (assuming no future lot-splits).
Exhibit showing location of proposed WCF
Z2023106
Page 5 of 8

Elevation of proposed WCF
.
Recommendation:
11. Staff recommends the Commission adopt a motion recommending that the Board of Supervisors
approve Z2023106 subject to the following conditions ‘a’ – ‘g’:
Z2023106
Page 6 of 8

a. Development of the site shall be in substantial conformance with the Site Plan entitled
“PHO Marisol“, consisting of 6 full-size sheets, dated October 27, 2023, and stamped
received November 8, 2023, except as modified by the following conditions.
b. Development of the site shall be in substantial conformance with the Narrative Report
entitled ““PHO Marisol“, consisting of 4 pages, dated November 8, 2023, and stamped
received November 8, 2023, except as modified by the following conditions.
c. The wireless communication tower shall retain the stealth properties as originally
designed. Any damaged or missing windmill components shall be replaced within 60 days
of such damage occurring.
d. The following Rural-43 SUP standards shall apply:
1. Minimum Setback to Southern lot line: 68’
2. Maximum WCF Structure Diameter: 14’ 6”
3. Maximum Antenna Array Diameter: 18’
e. The following Planning Engineering conditions shall apply:
1. All development and engineering design shall be in conformance with Section 1205 of
the Maricopa County Zoning Ordinance; Drainage Policies and Standards; Floodplain
regulation for Maricopa County; MCDOT Roadway Design Manual; and current
engineering policies, standards and best practices at the time of application for
construction.
2. Engineering review of planning and/or zoning cases is for conceptual design only and
does not represent final design approval nor shall it entitle applicants to future designs
that are not in conformance with Section 1205 of the Maricopa County Zoning
Ordinance and Drainage Policies and Standards; Floodplain Regulations for Maricopa
County; and the MCDOT Roadway Manual.
3. The WCF compound walls will require a turned block, every other block along the base
course to maintain historic drainage patterns.
4. The site contains areas of regulated floodplains. The project, as submitted, does not
appear to disturb any floodplain. Any disturbance would require issuance of a
floodplain use permit concurrent with building permits.
5. Any work in the Montgomery Road will require a permit from MCDOT.
6. The applicant must execute a wireless agreement with MCDOT for all equipment,
conduit, F/O and other work that will be within the MCDT ROW.
7. Approval of the US Bureau of Reclamation (BOR) is required to permit utility extensions
across federally owned property under their control.
f. This special use permit is valid for a period of thirty years and shall expire on January 11,
2054 or upon termination of the use for a period of 90 or more days, whichever occurs
Z2023106
Page 7 of 8

first. All site improvements associated with the special use permit shall be removed within
90 days of such expiration or termination of use.
g. The granting of this change in use of the property has been at the request of the applicant,
with the consent of the landowner. The granting of this approval allows the property to
enjoy uses in excess of those permitted by the zoning existing on the date of application,
subject to conditions. In the event of the failure to comply with any condition, and at the
time of expiration of the special use permit, the property shall revert to the zoning that
existed on the date of application. It is, therefore, stipulated and agreed that either
revocation due to the failure to comply with any conditions, or the expiration of the special
use permit, does not reduce any rights that existed on the date of application to use, divide,
sell or possess the property and that there would be no diminution in value of the property
from the value it held on the date of application due to such revocation or expiration of
the special use permit. The special use permit enhances the value of the property above
its value as of the date the special use permit is granted and reverting to the prior zoning
results in the same value of the property as if the special use permit had never been
granted.
Presented by: Joseph Mueller, Planner
Reviewed by: Matthew Holm, AICP, Planning Supervisor
Attachments: Case Map (1 page)
Site Plan (reduced 8.5”x11”, 6 pages)
Narrative Report (4 pages)
DPR comments (2 pages)
AZGF Response (2 pages)
Z2023106
Page 8 of 8


Site Name: PHO Marisol
Address: 30651 N 167th Ave, Surprise AZ 85387
Parcel: 503-51-937A
Case #: Z2023106
Proposed WCF Location
Purpose of Request
Verizon is committed to improving coverage and expanding network capacity to meet customer
demand throughout Maricopa County. Verizon in cooperation with ANTHEMNET (Applicant) is
proposing a new Wireless Communication Facility (WCF) to be located at 30651 N 167th Ave,
Surprise AZ 85387.
The proposed WCF will provide residents, visitors and businesses with improved high quality
reliable wireless service for both personal & business, in addition to enhancing emergency
services in the area.

Details of Request
Applicant is proposing a new WCF to mimic an “Old-Style Water Pump” with an associated
equipment compound enclosed by a masonry wall as detailed on the attached site
plan/elevation. The proposed 2,500 sq/ft equipment compound will be enclosed by an 8’
Masonry wall, that will conceal the ground equipment from view.
SUP Request
Applicant is requesting a Special Use Permit to allow a new 80’ WCF, with an antenna diameter
of 17’- 10” (due to the style of tower). The Old-Style Water Pump type of site was chosen due
to the rural nature of this location, and this particular type of site has been very well received in
other rural neighborhoods throughout the State.
SUP Request Details/Standards that need to be varied
The specific type of WCF being proposed (based on the previously detailed rationale) will
require variations from the typical WCF standards outlined in MCZO 1202. WIRELESS
COMMUNICATION FACILITIES. Applicant is requesting the following:
Applicant is requesting to vary the maximum antenna array diameter from the required 8’ to
17’-10” (MCZO Art. 1202.3.1.h), due to the type WCF been proposed. The required 8’ diameter
is outdated relative to the type of antenna/radios in use nowadays from that period when this
section of code was introduced.
Applicant is requesting to vary the setback of the new portion of the 80’ tall WCF from the
required 160’ to 68’-5” (MCZO Art. 1202.3.1.g) as this proposed location is the only location the
property owner will allow the WCF to be placed, but is the furthest away location from the
nearest neighboring residential.
Proposed WCF Setbacks
From North Property Line: 904’-4”
From South Property Line: 68’-5”
From East Property Line: 774’-8”
From West Property Line: 528’-6”
Proposed Equipment Compound Setbacks
From North Property Line: 887’
From South Property Line: 51’-9”
From East Property Line: 758’-1”
From West Property Line: 512’-7”
Relationship to Surrounding Properties
The proposed WCF will not alter or impact conditions of the surrounding properties, or impact
traffic in the immediate area.
Property to North: County RU-43
Property to South: County RU-43
Property to East: County RU-43
Property to West: County RU-43


The proposed site maybe visited once a month for routine maintenance, or the event of a
breakdown, so the proposed use will not impact traffic or conditions in the area and will comply
with all local, state and federal laws & regulations.
Please let me know if you need any additional information.
Sincerely,
Declan Murphy for Verizon/ANTHEMNET
8283 N Hayden Road, Suite 258, Scottsdale AZ 85258
Tel: (602) 326-0111
Email: dmurphy@coal-creek.com

SITE NAME: PHO MARISOL
ADDRESS: 30651 N. 167TH AVE,
SURPRISE, ARIZONA 85387
CODE COMPLIANCE: PROJECT SUMMARY PROJECT TEAM SHEET INDEX
PM
ACCESSIBILITY REQUIREMENTS:
PHO MARISOL 12:45:21
5/10/2023,
TITLE SHEET, VICINITY
MAP & GENERAL
PROJECT DESCRIPTION
INFORMATION
SUBMITTED:
VICINITY MAP
RFDS
SITE LOCATION
DRIVING DIRECTIONS
T-1

APN: 503-51-145R APN: 503-51-110R APN: 503-51-325 APN: 503-51-315F APN: 503-51-315M APN: 503-51-315K APN: 503-51-1122
ZONING: RU-43 ZONING: RU-43 ZONING: RU-43 ZONING: RU-43 ZONING: RU-43 ZONING: RU-43 ZONING: RU-43
APN: 503-51-097A
ZONING: RU-43
APN: 503-51-149C
ZONING: RU-43
APN: 503-51-937A
ZONING: RU-43
APN: 503-51-097B
ZONING: RU-43
APN: 503-51-150K
ZONING: RU-43
PM
APN: 503-51-097D
ZONING: RU-43 PHO MARISOL 12:45:21
APN: 503-51-150U
ZONING: RU-43
5/10/2023,
OVERALL SITE PLAN
APN: 503-51-111
ZONING: RU-43 SUBMITTED:
APN: 503-51-961 APN: 503-51-096
ZONING: RU-43 ZONING: RU-43
RFDS
BOR PARCEL 503-51-964
BOR PARCEL 503-51-964
W. MONTGOMERY RD.
N
Z-1
OVERALL SITE PLAN SCALE: 1" = 80' 1

EXISTING
BUILDING PM
PHO MARISOL 12:45:21
EXISTING 5/10/2023,
BUILDING
SITE PLAN
SUBMITTED:
RFDS
N
Z-2
SITE PLAN SCALE: 1" = 20'-0" 1

PM
PHO MARISOL 12:45:21
5/10/2023,
ENLARGED SITE PLAN
SUBMITTED:
RFDS
N
Z-3
ENLARGED SITE PLAN SCALE: 1/4" = 1'-0" 1

N
ENLARGED DIMENSION PLAN SCALE: 3/8" = 1'-0" 1
PM
PHO MARISOL 12:45:21
5/10/2023,
COAX CABLE TABLE
ANT. RRH RAD ENLARGED
SECTOR AZIMUTH CABLE TYPE # OF LINES
POSITION # QTY. CENTER
ALPHA 1 0° 1 76'-0" N/A N/A DIMENSION AND
ALPHA 2 0° 2 76'-0" N/A N/A ANTENNA PLAN
ALPHA 3 0° 0 76'-0" N/A N/A
BETA 1 120° 1 76'-0" N/A N/A SUBMITTED:
BETA 2 120° 2 76'-0" 12X24 HYBRIFLEX 1
BETA 3 120° 0 76'-0" N/A N/A
GAMMA 1 240° 1 76'-0" N/A N/A
GAMMA 2 240° 2 76'-0" N/A N/A
GAMMA 3 240° 0 76'-0" N/A N/A
RFDS
N
Z-4
HYBRID CABLE INFORMATION SCALE: 1/2" = 1'-0" 3 ENLARGED VERIZON WIRELESS ANTENNA PLAN SCALE: 1/2" = 1'-0" 2

PM
PHO MARISOL 12:45:21
5/10/2023,
ELEVATIONS
SUBMITTED:
RFDS
Z-5
NORTH ELEVATION SCALE: 3/16" = 1'-0" 2 EAST ELEVATION SCALE: 3/16" = 1'-0" 1

Joseph Mueller (PND)
From: tsprague@azgfd.gov on behalf of Project Evaluation Program - Game and Fish
<pep@azgfd.gov>
Sent: Friday, October 13, 2023 2:54 PM
To: Joseph Mueller (PND)
Subject: Re: Z2023106 - PHO Marisol
Mr. Mueller,
Apologies for the delay in this response. The Department appreciates the opportunity to provide an evaluation of impacts
to wildlife or wildlife habitats associated with this project. Based on the information provided, the Department offers the
following general recommendations:
 Minimize the potential introduction or spread of exotic invasive species, including aquatic and terrestrial plants,
animals, insects and pathogens. Precautions should be taken to wash and/or decontaminate all equipment
utilized in the project activities before entering and leaving the site. The Department encourages the applicant
to review the Arizona Department of Agriculture’s website for a list of prohibited and restricted noxious
weeds and the Arizona Native Plant Society for recommendations on control methods. To view a list of
documented invasive species or to report invasive species in or near your project area visit iMapInvasives - a
national cloud-based application for tracking and managing invasive species.
 If vegetation removal/trimming is required, the Department recommends that a qualified biologist survey for
nesting birds within the project area if work will be conducted during the breeding season. The trees and/or
vegetation within the project area may provide nesting opportunities for avian species that are regulated under
the Migratory Bird Treaty Act (MBTA) and protected under state law. Breeding season for birds in the project
vicinity is generally January through late June. If it is anticipated the project will not be in compliance with
MBTA, the Department also recommends contacting the U.S. Fish and Wildlife Service (USFWS) for technical
assistance and options to comply with the MBTA.
 If trenching or digging of holes will occur, trenching/digging and backfilling crews should be close together to
minimize the amount of open trenches/holes at any given time. Avoid leaving trenches/holes open overnight.
Where trenches/holes cannot be back-filled immediately, escape ramps should be constructed, which can be
short lateral trenches or wooden planks sloping to the surface. The slope should be less than 45 degrees (1:1).
Trenches/holes that have been left open should be inspected and animals removed prior to backfilling.
This email serves as our official response.
If you have any questions regarding this email, please feel free to contact me.
TIFFANY SPRAGUE | PROJECT EVALUATION PROGRAM SPECIALIST
ARIZONA GAME AND FISH DEPARTMENT - WMHB
OFFICE: 623.236.7222
MOBILE: 623.670.0750
EMAIL: tsprague@azgfd.gov
azgfd.gov | 5000 W. Carefree Highway, Phoenix, AZ 85086
Join our new Conservation Membership program and ensure a wildlife legacy for the future.
On Mon, Sep 11, 2023 at 10:18 AM Joseph Mueller (PND) <Joseph.Mueller@maricopa.gov> wrote:
1

Good morning,
We have received a request for a Special Use Permit for a new WCF (cell tower) on APN 503-51-937A in the Surprise
area. It is notable that the proposed 80’ WCF is allowed by right on the subject property, but the SUP is necessitated
due to the proposed antenna array diameter and setbacks not meeting the ordinances requirements.
The TAC meeting will be held on October 3rd.
Please let me know if you have any comments, questions, or concerns over the proposed SUP.
Kind regards,
Joseph Mueller
PLANNING & DEVELOPMENT
301 W Jefferson St Phoenix, AZ 85003
Planner
O: 602-506-7629
MARICOPA.GOV
Facebook | Instagram | Twitter | YouTube
2

Planning & Development
Engineering Plan Review
Date: September 20, 2023
Krystina Aragon, PE
Planning & Development
301 W. Jefferson St., Suite 170 Memo To: Darren Gerard, Planning Manager, Planning & Development
Phoenix, Arizona 85003
Phone: (602) 506-8790
www.maricopa.gov/planning Attn: Joseph Mueller, Planner, Planning and Development
Email address:
krystina.aragon@maricopa.gov
From: Krystina Aragon, PE, Plans Examiner Engineer, Planning and Development
cc: Michael Norris, P.E., Engineering Manager, Planning and Development
Subject: Z2023106 – SUP/POD for New Wireless Communication Facility (WCF)
(E1 Memo)
Job Site Address: 30651 N 167th Ave, Surprise
APN(s): 503-51-937A
PND engineering plan review (DPR, FCD and PND Transportation) has reviewed the 1st
submittal of the SUP application routed for review on September 8, 2023. PND
Engineering has no comments or objections subject to the following conditions:
1. All development and engineering design shall be in conformance with Section 1205
of the Maricopa County Zoning Ordinance; Drainage Policies and Standards;
Floodplain Regulations for Maricopa County; MCDOT Roadway Design Manual;
and current engineering policies, standards and best practices at the time of
application for construction.
2. Engineering review of planning and/or zoning cases is for conceptual design only
and does not represent final design approval nor shall it entitle applicants to future
designs that are not in conformance with Section 1205 of the Maricopa County
Zoning Ordinance and Drainage Policies and Standards; Floodplain Regulations
for Maricopa County; and the MCDOT Roadway Design Manual.
3. The WCF compound walls will required a turned block, every other block along
the base course to maintain historic drainage patters.
4. Access to the WCF will be via a primitive dirt drive that crosses several washes.
Any improvements to these so called wet crossings will require a civil engineered
design, Likewise, for utility crossing(s) through the washes.

Page 2 of 2
5. The site contains areas of regulated floodplains. The project, as submitted, does
not appear to disturb any floodplain. Any disturbance would required issuance of
a floodplain use permit concurrent with he building permit.
6. Any work in the Montgomery Road will require a permit from MCDOT.
7. The applicant must execute a Wireless Agreement with MCDOT for all
equipment, cnduit, F/O and other work that will be within the MCDOT ROW. This
agreement must be coordinated with Ms. Kelly Roy, MCDOT Utility Branch
Coordination Manager, 602-506-8603 or Kelly,Roy@maricopa.gov.
8. The US Bureau of Reclamation (BOR) appears to own a strip of land north of
Montgomery Road. Approval from the BOR is required to permit utility
extensions across Federally owned property.
Please contact me if you have any questions or require any additional information.