ATTACHMENT A
PLAN OF DEVELOPMENT
MOUNT ORD - Maricopa County Public Safety Communications Site Upgrade
I. Introduction
This Plan of Development (POD) describes the procedures proposed by Maricopa County, for
construction of a new Public Safety communications tower adjacent to the existing Maricopa
County communication facility. The current Communications Use Lease was granted June 15,
2011 and has a termination date of December 31, 2031. The County’s site currently includes an
equipment shelter, 80 foot tower, 1,000 gallon propane tank, and a 70 kW emergency power
generator. Maricopa County has identified the need for an upgrade to their existing critical
communications systems infrastructure. This upgrade includes interior improvements of the
existing communications shelter and construction of a new tower.
A. General Description
Maricopa County has initiated a Public Safety P25 Radio System Infrastructure Upgrade project,
which includes upgrades to the facility at Mount Ord, in Gila County, Arizona. The facility is
located on Tonto National Forest (TNF) Land administered by the Tonto Basin Ranger District.
Project activities will involve the installation of a new 150-foot-tall self-support tower with a 14
ft. lightning rod at the top, a waveguide ladder, and safety-climb system. The existing 80 ft.
tower will be removed after the new system is completed and cutover has occurred.
No antennas will be installed upon the new tower between heights of 95 ft. and 130 ft., in
order to maintain visibility of the surrounding terrain from the fire lookout.
The new 70 kW back-up generator with ice canopy has already been installed as part of an
emergency maintenance action caused by the failure of the old generator. The old generator was
removed.
The existing shelter interior will be renovated and a new Type 1 surge suppressor will be
installed on the existing main electrical panel “A”. The existing panel “EM” will be relocated to
accommodate new radio equipment racks. The existing Telco board will also be relocated to
accommodate the new equipment racks.
Exterior construction activities will disturb approximately 0.06 acre of land. There will be
ground disturbance for the installation of the new tower which includes a new foundation. This
foundation will be approximately 6’ below grade. All excess material will be taken off site and
properly disposed. No trails are being reconstructed. No new vegetation is being planted.
Access to the site is via existing road. No improvements or additional road construction is
planned as part of this POD.
MES811 AMENDMENT 1 - Tower replacement 1

ATTACHMENT A
II. Vegetation Treatments
A. Vegetation Description
The project area is located within the Petran Montane Conifer Forest biotic community as
described by Brown (1994). According to the US Geological Survey’s Southwest Regional GAP
Land Cover, the project area is near the convergence of the Southern Rocky Mountain Ponderosa
Pine Woodland and Madrean Pine-Oak Woodland vegetation types. The project area elevation is
approximately 7,120 feet above mean sea level and is located within the Mazatzal Mountain
Range of central Arizona. Vegetation at the top of Mount Ord is markedly different on the
northern and southern slopes of the mountain. The southern slope is open and more
characteristic of the Madrean Pine-Oak Woodland vegetation type, dominated by Emory oak
(Quercus emoryi) and sparse ponderosa pines (Pinus ponderosa). The top-most portion of the
southern slope has burned recently and is overgrown with non-native weeping lovegrass
(Eragrostis curvula). The northern slope is characteristic of the Rocky Mountain Ponderosa Pine
Woodland vegetation type and is dominated by ponderosa pine and Gambel oak (Quercus
gambelii), interspersed with alligator juniper (Juniperus deppeana), three-awn grass (Aristida
sp.), and Parry’s agave (Agave parryi). The very top of Mount Ord has been graded and a large
radio tower facility has been constructed. The project limits occur within this facility and stretch
from several existing buildings north to the edge of the tree-line on the northern slope. The
project limits have been completely graded and covered with gravel. No perennial plant species
occur within the project limits other than the limbs of a small stand of Gambel oaks (three
medium-sized trees) which overhang into the northern portion of the project limits. Limb
trimming or complete removal of these trees may be necessary to make room for construction
activities.
B. Clearing Prior to Construction
Any vegetation within the proposed grading area will be grubbed as part of the construction
process. With the planned area of work already disturbed, minimal amounts of organic debris is
anticipated. Spoils from the clearing process will be removed from the site.
C. Routine Vegetation Maintenance
Maricopa County will maintain the area of the tower according to its existing vegetation
management practices after the completion of the project.
III. Construction of Facilities
Motorola Solutions, Inc. will be performing the construction of the new communications facility
for Maricopa County in accordance to the plans submitted to TNF for approval. A copy of the
plans is attached as Exhibit A.
MES811 AMENDMENT 1 - Tower replacement 2

ATTACHMENT A
A. Equipment
Equipment to be used during the construction of the new communications facility will include
the following:
• 500 gallon water trailer
• Excavator
• Lowell or reach fork
• Compactors
• Hand and power tools
• Crew vehicles
• Trailers
• Crane for placement of tower
B. Design Characteristics
The following table represents the design characteristics to be adhered to during construction.
Table 1. Design Characteristics
Design Characteristics
Enclosure type Concrete Block Building
Enclosure Dimensions n/a
Fence Length n/a
Fence Area n/a
Enclosure type n/a
Tower type New
Tower Height 150’ (new)
Shelter Type Build In Place (existing)
Shelter Dimensions 11’ x 17’
Generator Type Liquid Propane
Generator Size 70 kW
Fuel Storage Type Liquid Propane tank
Fuel Storage size 1,000 gallon
Number of Ground rods 16
Utility type Underground electric
Enclosure access n/a
IV. Construction Sequencing and Timing
Construction will commence within 6 weeks of receiving the NTP and approval from TNF. The
construction on the new communications facility will last for an estimated 12 weeks.
MES811 AMENDMENT 1 - Tower replacement 3

ATTACHMENT A
V. Construction Methodology
Construction of the new communications facility will generally proceed as follows:
• Mobilization of excavation equipment to site
• Establish rough grade
• Construction staking for major components
• Excavation and placement of new tower
• Excavation and placement of site grounding
• Offload and set tower
• Install antenna and line including MW
• Demolition and removal of existing tower
The general site clear and grub includes the setting of the site rough grade, as well as establishing
the control points necessary to accurately locate the new tower and other construction items.
Once the site is construction staked, excavation will commence on the tower foundation. After
the foundation is installed and backfilled, excavation will begin for the site’s grounding trenches.
A ground ring and leads will be placed around each major component) and tied to all ancillary
site components, providing a single grounding system for the entire site. After the grounding
system subgrade components have been installed, the delivery of the tower will occur in a
manner intended to minimize the time the crane is on site. The crane is expected to be on site for
a single work day and will not be kept overnight.
VI. Mitigation Actions – Resource Concerns
The following mitigation measures were developed to reduce, avoid, and/or compensate for the
potential impacts the proposed activities may cause. Mitigation measures would be implemented
during construction and post construction.
A. Air Quality
• Dust generated during construction will be controlled by watering.
• Vehicles accessing the site for construction purposes will be properly maintained and
regularly inspected.
B. Heritage Resources
A Class III cultural resource survey was performed ("A Class III Cultural Resource Survey for a
Proposed Maricopa County and Motorola Wireless Telecommunications Tower on Tonto
National Forest Land on Mt. Ord, Gila County, Arizona," prepared for Patriot Towers by
Archaeological Consulting Services, Ltd. (“ACS”) – ACS Project No.13-142-CSUR4, dated
November 6, 2013 (the “ACS Survey")) and provided to TNF. No cultural resources were
identified during the current ACS survey. As a result, ACS recommends a finding of no historic
MES811 AMENDMENT 1 - Tower replacement 4

ATTACHMENT A
properties affected within the direct APE (Area of Potential Affect). No cultural resources are
located within the visual APE. ACS recommends a finding of no historic properties affected for
the project.
C. Hazardous Materials
• Maricopa County will ensure that vehicles and equipment used during construction are
properly maintained and regularly inspected.
• All fueling of equipment will be done on impermeable fabric, and no fueling will be done
within 100 feet of a watercourse or channel.
• Maricopa County will require all employees to adhere to Best Management Practice
guidelines, and all waste and spills generated on site will be disposed of in accordance
with state and federal regulations.
• Only emergency equipment maintenance will be performed at construction site locations.
Routine equipment maintenance will be conducted at offsite facilities.
D. Noise
• Construction machinery and equipment will be well maintained.
• Limit equipment on-site to the minimum necessary to complete construction.
E. Soils, Hydrology and Watershed
• During construction, Storm Water Pollution Prevention (SWPP) will be placed to control
any soils runoff during rain. This SWPP will remain in place until the site construction is
completed.
F. Vegetation
• No protected species were found in the construction area. Vegetation to be removed is
classified as invasive.
• Soil and vegetation removed within the project area will be removed from the site as
debris.
• Access to construction sites will be by existing roads.
• All construction vehicles shall be washed prior to entering the forest to avoid introducing
more weeds.
• Drivers will be instructed to avoid patches of weeds any time tires leave a paved surface,
to avoid the spread of invasive weeds.
G. Visual Quality
• All excavation spoils not able to be utilized on site will be removed from TNF lands.
• Rock excavation powder will be washed from the ground surface using water.
• No antennas will be installed upon the new tower between heights of 95 ft. and 130 ft., in
order to maintain visibility of the surrounding terrain from the fire lookout.
MES811 AMENDMENT 1 - Tower replacement 5

ATTACHMENT A
H. Wildlife
• The proposed activities will occur within a Mexican spotted owl (Threatened) protected
activity center. In order to reach a “No Effect” determination for this species, project
activities must occur outside of the breeding and nesting period (March 1 – August 31).
• If construction activities require the digging of holes and/or trenches, these will be
covered with plywood or other hard material at the end of each work day to prevent
wildlife from injury or entrapment.
• All trash and food items shall be contained in closed containers and removed daily.
• Solid waste will be contained and will be removed, at a minimum, weekly.
VII. Industrial Fire Plan Guidelines
Maricopa County, and their prime contractor, Motorola Solutions, Inc., will implement fire
prevention guidelines recommended by the National Wildfire Coordinating Group publication
PMS462, "Industrial Operations Fire Prevention Guide" (attached as Exhibit B).
Exhibits
Exhibit A – Mt. Ord Communications Facility Exhibit Documents